PM – John Nester, Mike Barth
01/28/20 – TEI authors and submits SOSS for approval as requested by facilities.
02/26/20 – TEI receives signed SOSS and PO for the project. TEI to set up kickoff meeting with HCFD.
03/26/20 – Project pending COVID-19 restrictions.
04/30/20 – Project pending COVID-19 restrictions.
05/27/20 – Project pending COVID-19 restrictions.
06/23/20 – Project pending COVID-19 restrictions.
07/29/20 – TEI has kick off meeting with Bryan Collins. TEI and Bryan visit all sites to review gear that is included in the scope of the project. Upon receipt of questionnaires from the building managers, the specifications will be drafted for HCFD to review.
08/21/20 – TEI issues request for information from building managers to include in the specifications. Upon receipt of the information from the building managers, specifications can be completed and issued for bidding, once HCFD says to issue.
09/23/20 – TEI waiting on completed forms from building managers. Upon receipt of the information from the building managers, specifications can be competed and bid package issued.
12/09/20 – Project bids received, CE Power apparent low bidder, and contract sent to Prosecutors office for review and approval. Building priority and schedule TBD once contract is returned and PO cut.
01/26/21 – JN with facilities sends CE Power PO and contract, with instructions for background checks. Upon receipt of approved BGCs, pre-construction meeting to be scheduled. CE Power contacts TEI to request walk through of all facilities prior to evaluate the building and access issues to be prepared to speak intelligently at the pre-construction meeting. TEI instructs CE Power to start the BGC process, and then send request in email.
02/23/21 – Upon notification from JN that CE power has BGC’s completed and passed, a pre-construction meeting will be scheduled to prioritize and develop an anticipated project schedule.
3/24/21 – Background checks are coming back for CE Power staff. HCFD and TEI meet at P&D garage with CE Power to discuss first building to get work completed on. P&D garage work to occur on 03/27/21.
04/28/21 – P&D Garage work completed. 2020 is next – and meetings have occurred at the site to develop plan of execution of work at the 2020 facility.
05/26/21 – TEI and HCFD have meetings with 2020 staff to discuss options with performing the PM. HCJC looking at options to make the PM work. Facilities and HCJC working together with TEI to develop plan.
06/23/21 – work at 2020 facility pending approval of plan from HCJC.
07/28/21 – work at 2020 facility postponed till later in the year (cooler weather). HCFD and TEI walks A&D and 800 Broadway with Bldg managers and CE Power. CE Power to submit outage schedules and durations for both facilities and then PM to be scheduled.
08/26/21 – TEI, HCFD, and CE Power met at A&D to review the project. A solution to make the PM procedures easier in the future was suggested. RT and MB spoke with JFS, and decided to work on the solution to keep the computer room powered (see A&D computer room emergency power). Discussing 800 Broadway now with CE power to keep project moving.
10/26/21 – CE power has sent several of thermal scans for review. 800 Broadway work still to be scheduled. CE power to provide availability.
12/13/21 – CE power reviewed 800 Broadway for outage plan. No outage plan submitted from CE Power to date. CE power receives PO for emergency power and HCFD requests schedule for this work and 800.
01/25/22 – Outage plan received and under review with TEI and HCFD for 800 Broadway.
02/23/22 – Outage plan approved for 800 Broadway – TEI and JN reach out to CEPower for schedule.
04/27/22 – HCFD and TEI pushing CE Power to schedule work. Pending CE Power Availability.
06/28/22 – 222 cleaning scheduled on 07/09/22. meetings for balance of buildings to be scheduled the week of 07/11/22.
08/24/22 – CE power to provide proposed schedule for balance of buildings. CE Power stated that they will be providing load monitoring (proposed dates are 09/01/22 and 09/02/22). The proposed schedule for the balance of the buildings is due to John Nest and Mike Barth by end of day on 08/25/22.
09/26/22 – A&D building work site work performed. Duke issues with identifying the location of the emergency feed, caused a re-schedule of the outage.
10/26/22 – Next building (2020) outage plan meeting with users scheduled for 10/31/22.
01/25/23 – 2020 work completed with minimal issues. Pre-outage walk throughs occurred for the CH and for the TPC. Outage plans are in development with CE Power and outages will be scheduled upon approval of outage plans.
03/29/23 – CH work completed. There were issues with one server circuit not backed up and 120 gear maintenance was aborted. 480 gear completed. TPC gear remains to be PM’ed.
04/27/23 – TEI places to call to Qualus to discuss TPC. Qualus not returned call to date.
05/23/23 – TEI and HCFD meet with Qualus on site to discuss the project, alternates to the project, and the possibility of moving the Duke Energy bus duct. Pending quotes from Qualus.
06/28/23 – Pending quotes from Qualus.
10/26/23 – TEI and HCFD working to get Qualus to coordinate and work with Beam repair in basement. Once the coordination is complete, the work at TPC will be scheduled and project will then be complete.
12/06/23 – HCFD send Qualus CO for additional work. Upon receipt of CO the final work to be scheduled.
03/27/24 – TPC work to be completed likely in June/July of 2024. NOTE – add the Emergency generator gear on loading dock to list of gear to be maintained.
05/29/24 – HCFD, TEI and Qualus coordinating dates for final building. Once scheduled, website will be updated with date scheduled.
08/28/24 – TPC work scheduled for 09/07/24. Project will be complete once TPC work is completed and all reports and closeout documents received for Qualus.
09/25/24 – Switchgear cleaning occurred at TPC. Project complete pending final closeouts.