Hamilton County Facilities

[General Services] – TEI-A

General Services – TEI
Archive

2026 Project Cost Estimates

PM: Rycca, Mike, Sam, Eryn, Terry, Mike, John

07/31/25 – We discussed the quantity of 2026 projects coming our way and we think about 20 project are new. The County will self-inflate the refresh cost estimates. Rycca will print and share the original list with us soon.
08/20/25 – ThermalTech received approved SOSS received from County.
08/28/25 – TTE Internal kickoff start, completion matrix created, Champlin assignments accepted and the TEI MBE partner engaged for work this year. Elevar SOSS submitted to HC 08/27.
09/24/25 – ThermalTech DEG working on estimates, most are done. Fieldwork in JC scheduled for this week. Gazelle will start uploading to Archibus this week.
09/25/25 – Elevar estimates ongoing and meetings with tenants scheduled.
10/30/25 – Elevar complete with estimates. ThermalTech complete with estimates.
12/11/25 – Complete. Davies partner creating binder PDF of each estimate before module is closed.

2026 Project Cost Estimates Read More »

2025 Project Cost Estimates

PM Watts, Murphy, Cannon, Millar, Barth, Thomas, Thamann
04/25/24 – Project module is open for 2025 projects.
06/27/24 – Murphy has assigned estimate leaders on each estimate, sent to all partners for approval.
06/27/24 – BW suggested that we meet with every requester and get their input on the submitted request. And we coordinate when the walk through will happen. Architectural they always needs to meet with county people. Budgets due on 7/12/24. This project is due end of August.
07/22/24 – Elevar – SOSSs submitted for CIP, New, and Resubmitted 2025 projects.
07/24/24 – ThermalTech – our approved SOSS was received last week, we’ve started the work, our electrical resubmittals are done, Champlin and Elevar are setting up field trips.
07/25/24 – Champlin submitted SOSS and has all the new projects fieldwork scheduled for last week of July and first week of August.
08/27/24 – Elevar: SOSSs approved and estimates ongoing.
08/28/24 – ThermalTech: Almost all field is compete. NEW and CIP estimates are progressing nicely, much of the data has already been entered. RESUBMITTED projects have been updated for Electrical Scope, Mechanical, Plumbing and Fire Scope are being update and reviewed this week. Mike Barth and Terry Cannon should begin QC reviews first of September. MBE currently entering all estimates that TTE has completed and turned over for entry. For New Estimates Completed 62% Elec, 31% Mech, 29% Plumbing, 28% Ready for Final Review.
09/24/24 – ThermalTech is complete with all entries. TTC and MCB are currently reviewing the data entered for the QC process except that TTC has to enter the 800 controls estimates manually. Elevar is complete with all entries.
10/29/24 – ThermalTech: all ThermalTech estimates are entered.
12/12/24 – ThermalTech has printed PDF binder files for its estimates.
12/31/24 – Ready to Archive.

2025 Project Cost Estimates Read More »

Barth Safety Prorgram

PM: Ted Graham, Mike Barth

03/28/24 –  Program started, poster created, training held, policies & procedures entered into the record for all to see 🙂


04/24/24 – Barth is still on the fritz, his doctor extended his convalescence another four weeks.  After that, they will probably just remove the foot and replace it with another hand so he can do three times as much work as he normally does.   One hand for CAD, one hand for the calculator one hand for a cell phone, his other foot will be used to kick the butt of all the coops at the office.


05/09/24 – Program membership has grown by 100%!  Welcome to the program Mr. Ted Graham!


06/18/24 –  Welcome to the program, Rycca!  This month’s safety topic is monitoring for Overexposure to UV Radiation.


07/24/24 – Hopefully no updates this month 🙂
08/28/24 – No updates to report.
09/24/24 – We have lost the tree, crying, grieving, and bemoaning has ensured.

Barth Safety Prorgram Read More »

2024 Project Cost Estimates

PM: John Nester, All Partners
06/29/23 – SOSS requested and approved for all partners
07/27/23 – Estimates underway. Vendor prices coming in for TTE new projects and estimates are being updated as we get information and quotes in. Re-estimates are also being updated with 2024 pricing. Discuss floor plans need with Champlin for New A/E estimates.
08/28/23 – ThermalTech has 40 of 48 new estimated ready for internal review. We have 68 of 179 re-estimates ready for internal review.
09/25/23 – Project estimates are complete. Champlin, THP and ThermalTech completed last Friday. TTC sent a summary of items for the Re-estimates to the team on Monday.
12/15/213 – Archive project.

2024 Project Cost Estimates Read More »

2023 Project Cost Estimates

PM: Bert Watts, All Partners
05/25/22 – All estimates sent to Partners for SOSS
06/29/22 – ThermalTech has started updating estimates in the Archibus module. Several reestimates are complete. We are gathering information on the new projects but we need them set to estimating and we have to give them updates on scope and equipment for estimating before they start entering new ones in earnest. We have started requesting prices from vendors as well. We will send the County list for access. It would be helpful to have a coordination meeting on who is leading and who is working on the combined estimates.
05/31/22- THP Issues SOSS for review by the County.
06/10/22 – THP SOSS approved.
06/30/22 – THP developed internal spread sheet for projects. Initial draft complete. THP will publish for possible use by other partners.
07/27/22 – THERMALTECH UPDATE. Most electric cost estimates are complete and ready for Barth review. Limited mechanical estimates are complete at this time. Architectural and Structural coordinated has started for the “new” estimate. Once we get the proposed floor plans, we will update the MEP estimates.
08/24/22 – ThermalTech Update – We are working on these estimates every day to meeting Sept 1 deadline. Champlin has provided SD drawings for almost ever project for our use on the “New” estimates. We are coordinating on individual estimates on a case by case basis. Electrically, all resestimates are complete. Mechanically we have about 25 estimates remaining. We have completed several new estimates and will spend the bulk of our time next week completing the new estimates with the new drawings we’ve received.
09/04/22 – ThermalTech projects are complete for both reestimated and new estimates. TTC will review as time permits.
01/22/23 – Met with John and Ben and reviewed details that would make the Cost Estimating module better for the partners.
01/24/23 – Ready to Archive

2023 Project Cost Estimates Read More »

EV Charging Stations RFP

PM John Nester, Mike Barth

10/26/21 – ThermalTech receives signed SOSS and PO for project. RFP in development.
13/13/21 – HamCo advises TEI to hold on the RFP development until a time when the county develops policy on the use/locations etc. of the EV Charging stations.   TEI on hold until directed otherwise from county.
01/25/22 – TEI receives notice from JN that the project will move forward as originally discussed.  TEI and JN to schedule kick off meeting the beginning of February
02/23/22 –  TEI submits list of questions for RFQ to HCFD.   Kick off meeting with HCES scheduled for 03/01/22 at 3:00 PM.  Upon receipt of direction from the HCES, RFQ will be finalized.
04/27/22 – HCFD determines that the Infrastructure needs to be bid separately from the service contract.  TEI develops infrastructure plan (SD level), includes power for the mobile coach, and has review meeting with HCES, HCPH, and HCFD on 04/26/22.  CD phase and implementation pending funding approval from County.
05/26/22 – TEI finalizes the SD package after review with the end users (drawings and revised opinion of probable cost).  TEI submits SOSS for CD thru CA phase of the work.  Work pending SOSS approval and PO.
06/28/22 – Work pending SOSS approval and PO.
07/27/22 – Work pending SOSS approval and PO.
08/24/22 – TEI receives Signed SOSS and PO.   JN states that funding for the install will be in 2023, and to work towards a first of 2023 issuance date for the project.
09/26/22 – TEI working towards an issuance at the end of the year for the infrastructure ITB for now. We can draft the RFP now but it has to be open for future stations.
10/26/22 – TEI working towards an issuance at the end of the year for the infrastructure ITB for now. We can draft the RFP now but it has to be open for future stations.
12/15/22 – Project documents in QC phase at TEI.  Will be sent to HCFD once QC review complete for review and then issued for bidding.
01/25/23 – TEI to send final review set to HCFD for review by 02/10/23.  Project bidding pending HC policy and procedures implementation decisions.
02/23/23 – Project bidding pending HC Policy and procedures implementation decisions.
03/29/23 – Project bidding pending HC Policy and procedures implementation decisions.
04/27/23 – Project bidding pending HC Policy and procedures implementation decisions.
06/28/23 – HC policy has been worked on by ES.   Location for the EV charging stations has been moved from 250 WHT to Civic Center  Drive (Comm  Center), and also to include the Regional Crime Lab in Blue Ash (common provider).  TEI and JN to discuss modifications to existing SOSS.
08/24/23 – TEI visits the site with the building manager and determines path/routing of power feeds for the EV charging equipment.  Discusses with JN, and will modify new SOSS for new location.
09/26/23 – TEI develops plan for drawings and sends to HCFD for review/approval.
10/26/23 – TEI has Underground detective locate existing utilities on site,  TEI shows on plan and HCFD submits to ODOT for approval.
12/06/23 – TEI submits documents to HCFD to submit to ODOT for approval.  Pending ODOT approval.
03/27/24 – Tracking this on other project.

EV Charging Stations RFP Read More »

JFS – General Services

PM: Bert Watts, John Millar
06/10/21 – County requested a general structural service proposal.
06/11/21 – THP sent SOSS.
07/12/21 – County approved SOSS for TEI, THP, and CHA.
10/28/21 – TTC provided an update on low flow plumbing issues at the A&D building. In the past month, we had a major leak at the main sanitary leaving the building. Plumbers called an underground detective to survey the pipe from the building to the street. TTC to get a test kit for testing in Fifth Floor East.
04/28/22 – Loading dock upgrades and striping and loading sign.

JFS – General Services Read More »

2022 Project Request Cost Estimates

04/21/21 – Cannon created post from Bert Watts email for 2022 Project Request.
05/27/21 – Bert sent the preliminary list out to the partners for SOSS authoring. Kickoff meeting next Tuesday with TEI, THP, and Champlin.
06/11/21 – Started research on 230 MEP upgrades including new above grade boiler and chiller room.
06/22/21 – Met at Comm Center to discuss project scopes for repurposing and academy rework.
06/25/21 – User meetings held to discuss the scope for most Champlin lead estimates.
07/28/21 – Work continues on the individual estimates. Some will be complete by July 31 and all will be complete by August 31. Cost, data and scope still coming in the CH controls, Mechanical Yard items which are the “biggies” for TTC. Champlin is making progress. Smaller estimates will be done by 7/31, the rest by 8/31.
08/20/21 – Champlin has provided almost all of the floor plans we need to complete estimates. TEI is currently putting together the cost and scope documents for the remaining estimates.
08/24/21 – Teleconference held on the 230 East 9th estimates between all partners to finalize the scope and estimating. TTC followed an update later that day with additional information after speaking with BW about the #2105 estimate.
08/26/21 – TEI – work continues and we plan on making the 8/31 completion date as discussed. Estimate and drawings are being uploaded daily.
10/28/21 – Project complete. A couple of final projects have been added and updated to the list.

2022 Project Request Cost Estimates Read More »

Blackout Vulnerability Study 2021

PM: Bert Watts, Mike Barth
03/25/21 – New post started by TTC and assigned to MCB.
06/23/21 – TEI working on Study. Site visits to the buildings to be scheduled by TEI with building managers over the next few weeks. Study proceeding.
07/28/21 – TEI continuing to work on study, researching existing conditions and vulnerabilities.
08/26/21 – No updates.
02/23/22 – No updates per discussion with HCFD.
10/26/23 – TEI assigns work to EE Conn Gerard, who is reviewing the study and working on completing the study.
12/06/23 – Conn for TEI is continuing to work on study.
02/29/24 – Conn has report ready to review with Barth.
10/30/24 – Conn sends out questionnaire to bldg mgrs. If they are replying to conn, he on honeymoon and will address upon his retturn.
12/11/24 – Conn returned and finalized information from the buildings has report ready for my review. will send to HCFD once QC review complete.

Blackout Vulnerability Study 2021 Read More »

TEI General Service – Archive

01/01/14 – County has approved a new SOSS for 2014. The 2013 SOSS however is not expired yet.
06/26/14 – Minimal work and time charged. Website updates mostly.
08/26/14 – TTC sent in new SOSS for energy, watchdog, 2015 project estimates projects to Bert.
01/27/15 – Updated website, worked on B201, etc.
05/25/15 – Reformatted tables on website, fixed some broken links in the Archive section, moved old buildings out of the main pages.
06/11/15 – Doteasy had to restore the FrontPage extensions this week. TTC had to remake all the user ID and send out new username and passwords.
06/24/15 – Website Updated.
08/26/15 – Website updated, Prevailing Wages Updated.
09/23/15 – Website updated. Facilities requested new General Service SOSS. TEI collected the Hourly Rates bid for plumbing and electric today. We will drop those bids to Bert tomorrow at the Partner meeting.
10/02/15 – Website updated for partner meeting.
12/08/15 – Website updated. ThermalTech working on new MSA agreement with Bert Watts.
01/08/16 – FrontPage extensions corrupted. TTC trying to fix.
01/15/16 – FrontPage extensions fixed, website data missing, TTC Website Updated.
01/21/16 – hamco.biz fully fixed. $45 restore cost from Doteasy. TTC will download a local copy from now on every month after the partner meeting for safekeeping.
01/26/16 – Bert said the contract is over a Prosecutors Office. We will wait until Friday Jan 29 and then move forward with the edits that we have approved.
04/25/16 – Created updated Archibus and Building Operation pages for Tim and Tony.
05/25/16 – Performed some maintenance and cleanup on the website this month.
06/27/16 – Website update and backed up locally by ThermalTech.
09/28/16 – Website updated. Building Ops renamed.
10/26/16 – TTC made a change in Tony project page on the server.
12/29/16 – Website updated for end of year and backed up by TTC to local server for archive purposes.
02/17/17 – Website is updated and formatting is updated too.
02/23/17 – TTE to investigate replacement website for hamco.biz that is compliant with Windows 10 and partner editing moving into the future. Try to find something that we can host and make better moving forward.
03/09/17 – TTE investigated WordPress at this time as an alternative and we updated the website for data.
03/21/17 – In an effort to find an easier method to edit the hamco.biz website, I have tested four new website locations. One at Wix, Penzu, Bluehost and sub-domain on hamco.biz. So far Penzu seems the easiest to use but cost money to get the full functionality, Doteasy does not support WordPress without an upgrade, Wix seems possible but so far no luck in creating multiple forums for each building and Bluehost was installed tonight. I need to find a way to upload a new theme on the website.
04/26/16 – Minimal work on website this month. Regular website was updated.
06/06/17 – TTC edited the new Wix website some more and had people enter comments, its seems to be working. It still requires a lot of formatting and work.
07/24/17 – Website updated. TTC contacted WebFeat for website design as well. No return emails.
08/30/17 – TTC contracted WebFeat for finishing the website design this week, $2800 total, $1400 now, $1400 at completion. Kickoff meeting next week for design, look, feel of the website. We will share some prelim looks when they draft the up.
09/25/17 – WebFeat sent preliminary look at new website. ThermalTech returned initial comments back to designer for security, NAV menu’s and content to fill the database. They immediately responded with a follow up email about working on this this week, very nice. The temporary website is located here: http://hamco.wfcstaging.com/
10/24/17 – WebFeat has made decent progress on the website. TTC is working on populating the site with the old data now and tweaking the security, input, active projects, archived projects and tony projects pages along with the management console and eventually migrating the test site to a live server.
11/28/17 – Had another round of emails with WebFeat and they made some final changes in their opinion of the scope of work. TEI has to integrate the remaining data into the website.
02/22/18 -All partners updated projects on new website. ThermalTech postponed final conversion to new hamco.biz until mid-March. WebFeat updated and added the new pages on the new website. TTC must create the Tony Matre projects on new website. Terry has created a copy of all the old data on the hamco.biz website so when we update the site to WordPress we still have the data saved.
03/24/18 – New website is published and live. ThermalTech input new usernames and sent to the group for editing.
04/01/18 – This is a test edit using the new inline editing too. Works inline editing plugin is activated.
04/26/18 – Website updated. Several plugins were updated several times this month for security reasons. The website domain name and server were updated for another year with Doteasy.com for hosting.
05/30/18 – Prevailing Wages updated, security patches applied and new projects created for use on the site this month.
06/30/18 – Prevailing Wages updated.
07/26/18 – Prevailing wages updated, security applied, some project management for formatting completed.
08/29/18 – Prevailing wages are updated, no other security updates were required this month however TTC edited and fixed some naming and category discrepancies, also updated all Tony Projects and created a new category for them.
09/24/18 – Website Updated, PW uploaded, Security Patches applied.
10/23/18 – Website has been updated. TTC to add October PW soon.
01/15/19 – Website updated. PW uploaded. Database updated.
02/28/19 – Website has been updated this week for meeting.
03/28/19 – Website was updated on 3/26 and 3/27. TTC and Bert agreed to extend the annual renewal with Doteasy for hosting the website. Note that hosting is not the same as domain name renewal. Each year there are two renewals.
04/25/19 – Website updates complete earlier this month. PW rates downloaded and uploaded to this site but TTC needs to do script updates for end of month and upload April PW rates.
05/28/19 – Updated the website for County meeting, saving widget updates until after the Partner meeting.
05/29/19 – Created Champlin Login, migrated all Terry Cannon post to TEI and updated our Archive projects to clean up migration of old project.
08/28/19 – Website has been updated for this weeks Partner meeting. TTC will update scripts and website next week.
09/24/19 – Website updated, PW uploaded, scripts updated but two more need to be updated soon.
10/30/19 – TTE Update website and update PW rates last week. Created new projects and categories for several projects and performed website cleanup. Assisted Champlin with front end documents.
12/05/19 – Updated scripts on website, upload PW information, start updating website for next meeting on 12/12.
01/27/20 – Website update, PW rates uploaded a couple of weeks ago. Scripts not updated this month yet.
01/30/20 – Called to 800 Broadway to troubleshoot boiler issues and was onsite 1/30, 1/31, and 2/1 to resolve the issues. TTC will send Tony a field report as several things were found to contribute to the issues at 800 Broadway this year. It was a good bit of troubleshooting and quite the enigma to figure this one out but we got it.
02/02/20 – General Service names were renamed to [General Service] so they appeared at the top of the list form now on.
02/27/20 – PW updated and website updated Monday-Wednesday.
03/13/20 – TEI issued Work from Home mandates for all employees limited access out of the office, for fieldwork or meetings for all projects starting 3/20/20. We are to continue servicing clients as best as we can remotely and only do onsite meetings as necessary.
03/23/20 – Doteasy renewal is up for next 12 months for hamco.biz. TTC and BW agreed to renew another 12 and TTC sent in renewal.
03/24/20 – Website updated for PM meeting. We are not meeting in person but will have details updated for Facilities.
07/29/20 – Website updated, PW rates uploaded and fixed for some hyperlinks.
08/26/20 – Website due for major updates including WordPress 5.5. PW rates updated for August and September will be early for JC Project.
09/18/20 – Block editor was automatically installed. TTC trying to disable that feature on the website. Updated the website mid-month this month. September PW waged already updated.
10/28/20 – Scripts updated, working on classic editor settings, PW rates updated.
12/10/20 – Website updated mid-November although there was no meeting. Reupdated in December for 12/10 meeting.01/26/21 – Website updated, jquery issued addressed, 3 plugins updated, PHP security issued researched.

TEI General Service – Archive Read More »

Arc Flash – Heliport, P&D Garage and Records Center

03/24/21 – HCFD requests and TEI submits SOSS to provide Arc Flash Electrical System modeling and labeling at the Sheriff’s Heliport, the P&D Garage, and the Records Center. Project Pending SOSS approval and PO.
04/28/21 – Project Pending SOSS approval and PO.
5/26/21 – TEI receives signed SOSS and PO. TEI scheduling kickoff meeting with JN to begin field investigation and calculation phase of the study at all three facilities.
06/23/21 – TEI requests available fault information from Duke Energy for all 3 facilities. Upon receipt of data from Duke Energy, field work will be scheduled for each of the 3 facilities and studies will be completed.
07/28/21 – TEI receives data from Duke on Heliport and P&D garage, still waiting (and repeated requests) on Records Center Data. Upon receipt, we will schedule field work for input into models.
08/26/21 – Data from Duke still pending for record center. Multiple phone calls, when we talk to a rep, they pass along to someone else and the process starts over again.
10/26/21 – Data received from Duke. All buildings have been visited. Conn (EE on project) will schedule Phasor with Ian Zellner upon his return from vacation.
12/13/21 – site visits with EC to confirm feeder sizes etc.  Finalize the model and submit to Charlie for final approval prior to application of labels.

02/23/22 – TEI submits finalized model calculations and report to CMI for review.   We will schedule application of labels upon receipt of approval from Charlie.

04/27/22 – TEI receives CMI comments – and incorporated into the model.  TEI printing labels on 04/27/22 and scheduling time with building manager to apply labels (week of 5/2/22).

05/26/22 – All labels complete and applied at building sites.   Project complete.

Arc Flash – Heliport, P&D Garage and Records Center Read More »

Covid HVAC Study

07/21/20 – First field trips for the Covid HVAC study scheduled.
08/12/20 – First draft of the report submitted for review.
08/21/20 – First draft of the report resubmitted and comments returned.
08/20/20 – Started integrating the Portable HEPA filtration units into the report and finding truly equal manufacturers, lead times, and cost.
08/21/20 – Final Study Report submitted to County with floor plans.
08/23/20 – BW asked to break out the building improvements and send to Tony for each building manager. Send directly to Tony Matre.
08/27/20 – Reports were well received with the County. Phase 2 for HEPA placements and safety PM coming up next.
09/14/20 – Sent building reports to Tony Matre and final information to Prosecutor Office. Answered some additional questions for the prosecutor this week and followed up on some additional articles emailed to me.
06/26/20 – Sent touchless water review to County for review of Ameresco proposal.
10/01/20 – Bid questions sent to bidders who submitted bids on the Portable HEPA Units.
10/05/20 – PO was release to the vendor for the purchase of Portable HEPA units.
10/06/20 – ThermalTech released building Recommendations to Tony Matre for Bldg Mgr use.
10/09/20 – Created cross reference guide for filter replacements from Tony
10/13/20 – County asked for SOSS for PM creation for the HEPA filtration units.
10/28/20 – Safety consultant has submitted a price to TTC to update our SOSS for the PM work on this project.
12/04/20 – Talked to Bert and Joe this past week about delivery of the HEPA units. The UV lights are on a delayed delivery schedule. We are seeing how this affects equipment.
12/30/20 – Working on excel format for equipment PM.
01/15/21 – TTC talks to Tim Schuh about setting up unit PM for this job.
01/21/21 – HEPA units are arriving disassembled. Joe sends serial numbers to TTE.
01/26/21 – TTC sends email response to RWL request for BOMA review.
02/19/21 – TTC commissioned Comm Center Unit to final CFM and moved closer to the plug. Gave county option for the longer plug if needed.
02/24/21 – TTC and RAJ commissioned 230 East 9th & 2020 HEPA units. One HEPA at 2020 has been sent back to the factory for repairs. We will be visiting the other sites in the next two weeks.
02/25/21 – BW asked for TTC email to be rolled up into a memo, general update and usage, add Charlie safety to PM, add Komisky report as an appendix to the memo.
03/25/21 – All buildings CX fieldwork is complete. Several units have had additional issues and CAI has visited the buildings to troubleshoot. Two have to be fixed by the factory, one was reprogrammed in the field and that data shared with building managers for future troubleshooting. TEI starting on the final CX summary report.
04/29/21 – Bert revised the worksheet and request ThermalTech to get all final serials numbers for the remaining units. TTC dispatched Ryan to collect the information.
05/26/21 – This month we retrieved the rest of the serial numbers on the HEPA units, filled out, and sent in the equipment worksheet for Archibus. We assisted with some problem units at 2020 and TPC and we visited the Law Library and provided a recommendation on units in the Law Library.
06/25/21 – Final worksheets were sent to the County on Admin 6th floor waiting and BOCC meeting room and 2020 Multipurpose Rooms. Teh final equipment list including missing serial numbers is in.
07/28/21 – DEV PM entered for County review and comments were sent back this week. We are ready to move to actual PM for these entries. LOTO safety procedures can be uploaded as a PDF with the PM to be performed.
08/25/21 – TTC visited 800 Broadway 6th floor today and took field measurements. Created worksheets and sent out floor plan to facilities. HEPA units not required in this space per the existing HVAC serving this area.
10/28/21 – TTC submits recommendations for the Ohio Means Jobs building. All PMs were uploaded to Archibus on 10/5/21.
10/28/21 – Portable HEPA units PM are uploaded and ready for November 1. Tony found better filter pricing for these units.
11/09/21 – Covid report sent to Rycca for A&D 2nd, 4th, and 5th-floor lobbies. None of these spaces required additional Portable HEPA at this time.
01/22/22 – The lower level study for OMJ is complete and we did add one Portable HEPA in this space.
07/27/22 – No updates to the Covid study this month.
02/22/23 – Met with Rycca and Glen on A&D conference room Covid needs. Backed existing unit down to 100 to 200 cfm each per new calculation worksheet.
04/26/23 – No updates but in May the emergency mandate may expire and we will address the use of the Portable HEPA during that time.
05/21/23 – Units were removed from operation this week in some buildings.
06/28/23 – Update Ralph et al. on Covid updates from his email. No changes necessary.

Covid HVAC Study Read More »

Fire Alarm & Sprinkler Testing

07/29/20 – SOSS received for these projects. TTE already about 75% done updating the specifications. We have updated three buildings with new Fire Alarm inventories (A&D, Courthouse).
08/26/20 – TTC to finalize testing manuals this week for Tony review.
09/18/20 – Finalized all documents this week, went over project specifics and update the manuals. Got two new ITB and issued for bidding today. Prebid 9/29 and Bid Opening 10/14.
10/06/20 – Addendum 1 issued. Bid extended to 10/28.
10/08/20 – Addendum 2 issued.
10/23/20 – Addendum 3 Issued. Bid extended to 11/04.
10/28/20 – Questions Due.
10/29/20 – Addendum 4 issued.
12/04/20 – TTC reviewed final contracts several times prior to signature by the contractor. TTC participated in research on the bid documents and called the vendor for a post-bid interview prior to recommending this work. At this time the project is set to be awarded to SA Comunale for both Fire Alarm and Fire Suppression.
12/30/20 – Project to be Archived.
07/28/21 – Rebid complete and final documents turned over to Tony.

Fire Alarm & Sprinkler Testing Read More »

Electrical Switchgear PM Specs – 2020

PM – John Nester, Mike Barth

01/28/20 – TEI authors and submits SOSS for approval as requested by facilities.
02/26/20 – TEI receives signed SOSS and PO for the project. TEI to set up kickoff meeting with HCFD.
03/26/20 – Project pending COVID-19 restrictions.
04/30/20 – Project pending COVID-19 restrictions.
05/27/20 – Project pending COVID-19 restrictions.
06/23/20 – Project pending COVID-19 restrictions.
07/29/20 – TEI has kick off meeting with Bryan Collins. TEI and Bryan visit all sites to review gear that is included in the scope of the project. Upon receipt of questionnaires from the building managers, the specifications will be drafted for HCFD to review.
08/21/20 – TEI issues request for information from building managers to include in the specifications. Upon receipt of the information from the building managers, specifications can be completed and issued for bidding, once HCFD says to issue.
09/23/20 – TEI waiting on completed forms from building managers. Upon receipt of the information from the building managers, specifications can be competed and bid package issued.
12/09/20 – Project bids received, CE Power apparent low bidder, and contract sent to Prosecutors office for review and approval. Building priority and schedule TBD once contract is returned and PO cut.
01/26/21 – JN with facilities sends CE Power PO and contract, with instructions for background checks. Upon receipt of approved BGCs, pre-construction meeting to be scheduled. CE Power contacts TEI to request walk through of all facilities prior to evaluate the building and access issues to be prepared to speak intelligently at the pre-construction meeting. TEI instructs CE Power to start the BGC process, and then send request in email.
02/23/21 – Upon notification from JN that CE power has BGC’s completed and passed, a pre-construction meeting will be scheduled to prioritize and develop an anticipated project schedule.
3/24/21 – Background checks are coming back for CE Power staff. HCFD and TEI meet at P&D garage with CE Power to discuss first building to get work completed on. P&D garage work to occur on 03/27/21.
04/28/21 – P&D Garage work completed. 2020 is next – and meetings have occurred at the site to develop plan of execution of work at the 2020 facility.
05/26/21 – TEI and HCFD have meetings with 2020 staff to discuss options with performing the PM. HCJC looking at options to make the PM work. Facilities and HCJC working together with TEI to develop plan.
06/23/21 – work at 2020 facility pending approval of plan from HCJC.
07/28/21 – work at 2020 facility postponed till later in the year (cooler weather). HCFD and TEI walks A&D and 800 Broadway with Bldg managers and CE Power. CE Power to submit outage schedules and durations for both facilities and then PM to be scheduled.
08/26/21 – TEI, HCFD, and CE Power met at A&D to review the project. A solution to make the PM procedures easier in the future was suggested. RT and MB spoke with JFS, and decided to work on the solution to keep the computer room powered (see A&D computer room emergency power). Discussing 800 Broadway now with CE power to keep project moving.
10/26/21 – CE power has sent several of thermal scans for review. 800 Broadway work still to be scheduled. CE power to provide availability.
12/13/21 – CE power reviewed 800 Broadway  for outage plan.  No outage plan submitted from CE Power to date.  CE power receives PO for emergency power and HCFD requests schedule for this work and 800.
01/25/22 – Outage plan received and under review with TEI and HCFD for 800 Broadway.
02/23/22 – Outage plan approved for 800 Broadway – TEI and JN reach out to CEPower for schedule.
04/27/22 – HCFD and TEI pushing CE Power to schedule work.  Pending CE Power Availability.
06/28/22 – 222 cleaning scheduled on 07/09/22.   meetings for balance of buildings to be scheduled the week of 07/11/22.
08/24/22 – CE power to provide proposed schedule for balance of buildings.  CE Power stated that they will be providing load monitoring (proposed dates are 09/01/22 and 09/02/22).  The proposed schedule for the balance of the buildings is due to John Nest and Mike Barth by end of day on 08/25/22.
09/26/22 – A&D building work site work performed.   Duke issues with identifying the location of the emergency feed, caused a re-schedule of the outage.
10/26/22 – Next building (2020) outage plan meeting with users scheduled for 10/31/22.
01/25/23 – 2020 work completed with minimal issues.   Pre-outage walk throughs occurred for the CH and for the TPC.  Outage plans are in development with CE Power and outages will be scheduled upon approval of outage plans.
03/29/23 – CH work completed.   There were issues with one server circuit not backed up and 120 gear maintenance was aborted.   480 gear completed.   TPC gear remains to be PM’ed.
04/27/23 – TEI places to call to Qualus to discuss TPC.  Qualus not returned call to date.
05/23/23 – TEI and HCFD meet with Qualus on site to discuss the project, alternates to the project, and the possibility of moving the Duke Energy bus duct.  Pending quotes from Qualus.
06/28/23 – Pending quotes from Qualus.
10/26/23 – TEI and HCFD working to get Qualus to coordinate and work with Beam repair in basement.   Once the coordination is complete, the work at TPC will be scheduled and project will then be complete.
12/06/23 – HCFD send Qualus CO for additional work.  Upon receipt of CO the final work to be scheduled.
03/27/24 – TPC work to be completed likely in June/July of 2024.  NOTE – add the Emergency generator gear on loading dock to list of gear to be maintained.

05/29/24 – HCFD, TEI and Qualus coordinating dates for final building.  Once scheduled, website will be updated with date scheduled.
08/28/24 – TPC work scheduled for 09/07/24. Project will be complete once TPC work is completed and all reports and closeout documents received for Qualus.
09/25/24 – Switchgear cleaning occurred at TPC. Project complete pending final closeouts.

Electrical Switchgear PM Specs – 2020 Read More »

Electrical Findings Study and Report

06/26/19 – TEI authors and submits SOSS for project. Project pending approval of SOSS and PO.
07/24/19 – TEI receives approved SOSS and PO. TEI to establish kickoff meeting with facilities and begin project.
08/27/19 – TEI to kick off this project once server room project is issued for bidding
09/25/19 – TEI is gathering data from the other projects for this report. TEI to schedule meeting with HCFD for kick off meeting.
10/30/19 – TEI working on report – and is scheduling site visits to the buildings included in the report to visit sites. The report is in process.
12/11/19 – TEI working on report – and is scheduling site visits to the buildings included in the report to visit sites. The report is in process.
01/28/20 – TEI has report well in process and will submit draft upon completion.
02/26/20 – TEI has report near completion – pending one manufacturer (GE) responses. Draft report to be submitted upon receipt and review of GE data.
03/26-20 – TEI to send to Facilities draft of report by 04/01/20.
04/30/20 – TEI send draft report to facilities for review. TEI receives comments from facilities. TEI modifying final report.
05/27/20 – TEI to finalize report for submission to facilities.
06/23/20 – TEI to finalize report for submission to facilities.
07/29/20 – TEI to finalize report for submission to facilities.
08/21/20 – TEI to finalize report for submission to facilities.
04/28/22 – Ready to archive.

Electrical Findings Study and Report Read More »

PBS Z-Ramp Replacement

09/14/09 – Additional documentation has been sent to Kerry for contract approval.

08/25/09 – Joe needs additional bid information for the project. United needs to provide final bid paperwork to Joe.

0729/09 – Project has been bid. Prices were tabulated and sent to bidders. Final contract was $16,300 and included $500 in allowance monies. TEI has written the contract and given to the County for signing.

06/23/09 – This project is out for small project bidding.

PBS Z-Ramp Replacement Read More »

Emergency Generator PM Bid

02/24/16 – Tony called and said that this project and PO are approved. Bid in March, Award in April, current contract runs out in May.

03/30/16 – Barth has made progress on the specifications they are about 90% complete. We are ready to get dates and an ITB and for Owner review.

04/26/16 – Project manual is ready. Date of Issuance will be 4/28/16. Bid Opening 5/26/16.

04/27/16 – Bid package sent to purchasing on 04/26/16. Pending bidding process.

05/25/16 – Bids open tomorrow. Two Addendums on project so far. All seems to be going well.

06/17/16 – Bids opened and there were anomalies. Tony to get information to ThermalTech as to which bidder each of the user groups has selected (Facilities, Cell Towers, Engineers).

06/27/16 – TTC to write a contract for Cummins for the Facility project. OK to share this contract with other departments if they need this. I told Tony this would be done last week, I will try to finish today.

07/18/16 – Tony is discussing with Kerry and is trying to stick with Cummins for the this contract. Kerry questioned the Alternate no bids by Cummins as legitimated on this job.

07/22/16 – Kerry and JoAnn and Tony are discussing rebidding this project due to Cummins not submitted Alternate bids for years 4 & 5.

07/25/16 – Talked to Tony and Gina today about the Alternate items in the Egen bid and we are going to rebid this project and we have change front ends to the standard county non-prevailing wage front end document and change Alternates to Optional Years. New ITB is 059-16.

07/28/16 – Talked to Tony and we are going to rebid all departments. I discussed a small SOSS to just pay for the the hours of this bid. We have a new ITB but no bid schedule yet.

08/03/16 – Tony said he approved my SOSS-A for rebidding this work. TTC to proceed.

08/25/16 – Egen PM Rebid sent out for bidding.

09/02/16 – No substantial questions on rebid yet. Bid opening scheduled for 9/8/16.

09/08/16 – Bid opening is today. Results to follow.

09/23/16 – IC won the second bid but didn’t include any battery replacement in year three. After several emails and reviews with Purchasing and the Prosecutors department, they are going to let their bid stand if they provide the battery replacements in year three.

10/25/16 – Post bid and Pre-Award meeting was held last Friday. Everything seems to be in order and TEI will write the contract for IAC today.

11/10/16 – All three revised contracts sent to Tony today for use on the Rebid work. IAC is the new vendor.

Emergency Generator PM Bid Read More »

Electrical Switchgear PM Specs 2018

07/25/18 – ThermalTech working to finalize specs, will deliver to John Nester by 07/31/18 for review.
08/29/18 – ThermalTech Issues project for bidding. Pre-Bid meeting is scheduled for 08/30/18 at 2:00 PM. Bids open 09/13/18 at 11:00 AM.
09/26/18 – Bids received for project. 3 bids received, one disqualified for not having any form of bond. ThermalTech qualified apparent low bid who did not include multiple scope items and withdrew their bid. DK next apparent low bid, and has all scope included.
10/23/18 – ThermalTech authors a contract for DK after Wells Engineering withdraws their bid because they did not include all of the scope of the work in the project. Project start is pending contract approval and issuance of PO.
11/28/18 – DK received PO for work from HCFD. DK to work with JN to schedule the work.
02/26/19 – DK performes PM and cleaning at the Comm Center on 02/16, and then on the SPHQ on 2/23. 250 WHT and 230 East 9th Street PM and Cleaning pending, to be scheduled with John Nester and Building Managers.
03/26/19 – Dates for the 230 E9 and 250 WHT services still pending.
03/28/19 – 250 WHT May 4. 230 Coordinating with PDO.
04/24/19 – TEI, HCFD, Electricians, DK meet with building manager and building staff to review plan for outage. Walk the building site and plan the outage for 5/4/19. 230 E9 will likely be in June for outage.

05/29/19 – 230 E9 switch gear cleaning will be performed on 06/02/19. 250 WHT was delayed due to issues at the building. New tentative date will be 06/15/19.

06/26/19 – all buildings cleaning and PM complete. DK to submit reports for each building including Thermal Scans of equipment. TEI has not received any reports for any of the buildings to date.

07/24/19 – TEI requests written reports from DK for all of the buildings. Final payment pending submission of the final reports.

08/27/19 – HCFD issues a change order for DK to repair the non-functional circuit breaker discovered during the cleaning and PM. Field verification of circuits served underway, and then the breaker will be swapped out. DK to submit final reports from cleaning the Thermographic reviews.

10/30/19 – TEI identifies in report that the non-functioning breaker that DK identified is not as indicated in the report. DK to confirm the proper breaker that is non functional prior to swap out. DK to schedule with the owner’s occupancy requirements the replacement of the breaker.

01/28/20 – Once DK submits final PW reports and AIA docs, this project will be archived.

Electrical Switchgear PM Specs 2018 Read More »

Scroll to Top