JC – Selective Cell Door Replacement 2024 (Ph. 4)

PM: Matt Butz, Sam Hofmann
03/28/24 – SOSS received. Sheriffs to locate doors included in this project.
04/25/24 – No update.
05/30/24 – Sheriffs provided doors to be included. Work in progress.
06/27/24 – Work in progress.
07/25/24 – No Update.
08/29/24 – Owner review set submitted. project to be bid in next couple weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Cornerstone is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project in contract phase.
01/30/25 – Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff scheduled for 3/31.
04/24/25 – No Update.
05/29/25 – Submittals received.
06/26/25 – Submittals to be returned and a schedule provided by Cornerstone.
07/31/25 – Submittals returned. Cornerstone to schedule mobilization.
08/28/25 – No update.
09/25/25 – No update.
10/30/25 – Cornerstone to mobilize Monday to finish phase 3 work and begin phase 4.
12/11/25 – Phase 1 complete. Moving to phase 2 after the new year.
01/28/26 – Project ongoing.
02/26/26 – Project is ongoing. 2 pods left until completion.
03/26/26 – Project ongoing. second to last phase has been started. Final phase to pause for 1 month until Triton completes phase 2 work.
04/30/26 – No update.
05/28/26 – Cornerstone to complete this project after tritons project is complete.
06/25/26 – No update.
07/30/26 – Final pod is ongoing.
08/28/26 – Work is complete. Closeouts in progress.
09/24/26 – No update