PM: Tony Matre, Terry Cannon
05/22/25 – Tony Matre asked for an SOSS to rebid this project in 2025.
06/25/25 – SOSS submitted.
07/30/25 – SOSS approved this month. Internal meeting conducted for kickoff to collect as-builts and setup new drawings.
08/28/25 – Drawings are nearing review status. Coty and Luke made good progress, but we have a lot of as-built items to incorporate from the last bid.
09/24/25 – We are updating the drawings for the new buildings including 525, EMA, and Mercy. Drawings should be ready for review in a couple of weeks for the whole bid package.
09/25/25 – 525 does not have any fire rated walls. CHA answered Coty about Dane.
10/30/25 – Still putting new buildings together.
12/12/25 – Original building drawings updated. New building drawings added, ready for TTC review. We noticed that several fire dampers missed in the Justice Center because of the spline ceiling are open and accessible. TTC worked with NKYHC to get a quote to update the fire dampers in the JC lobby now before the new ceilings go back in. NKYHC working with Triton to use their lift.
01/25/26 – Review sets sent to Tony Matre for distribution and review. After comments are received, we will setup the bid schedule for this project.
02/25/26 – No comments received yet, ttc checked in a couple of times.
03/25/26 – We are waiting on green light from Tony before bidding. Review sets are in for comments.
04/26/26 – Project on hold awaiting green light from Tony.
05/27/26 – DEG needs to add to buildings to the the bid and then we will start putting together the ITB.
06/25/26 – Finalized scope for new buildings, updated and found missing data from previous bid and addendums, final items being added to scope for bid package.
07/30/26 – Talked to Tony and we are removing 1701 and 111 from scope. We don’t have to wait for any additional comments from Facilities, TTC can package this up for bidding.
08/26/26 – Coty reviewed drawings this month and made changes but said he needs to clean up some items from the Coop work and he will get that done this month for my final review.
09/23/26 – Review project with Tony, putting 2026 budget together for Tony, but he also said to get the job out for bidding in October 2027.
10/26/26 – TTC will review drawings before Partner meeting.