Hamilton County Facilities

All Bldgs

All Buildings – Space Allocation Drawings

PM: Rycca Thacker, Eryn Thamann
12/11/25 – SOSS requested for space allocation drawing updates. Awaiting final building priority list from HCFD to finalize SOSS.
01/29/26 – Elevar working on SOSS.
02/26/26 – Elevar provided SOSSs.
03/26/26 – SOSSs approval pending.
04/30/26 – SOSS approved for three buildings. Need schedule from HCFD for access hours, building priority, and deadlines.
05/28/26 – Waiting for Elevar badging to be finalized.
06/25/26 – Started scanning of 1701 06/22 and will last the week. Drawings will be updated as scans come back and starting with JFS areas for leasing diagrams.
07/30/26 – Working thru 1701 set and met with HC IT Dept to review on 07/23. Scanning complete for 111 Tri-Co. Scanning scheduled at TPC for 08/10-08/14.
08/27/26 – Provided 1701 CAD and pdf files. Just received pdfs files of the parking garage and will bgin on those soon. Scanning completed at TPC and 111 Tri-Co. As staff area vailable, these drawings will be checked against scans.
09/24/26 – CAD files received of 1701 parking garage from Champlin to complete that portion of work. Files for 111 are almost complete and sent to HCFD for indications of tenant spaces. Templates for 138 are complete.
10/29/26 – Working thru TPC now.

All Buildings – Space Allocation Drawings Read More »

All Buildings – Emergency Switchgear PM

PM: Rycca Thacker, Mike Barth
10/30/25 – The project is out for bid, prebid is scheduled for November.
12/10/25 – Bid opening occurred. Zero bids received.
01/28/26 – HamCo asks DEG to re-package and resend out to bid.
02/25/26 – No updates this month. DEG will compile all data and send list of buildings that information is still pending.
06/23/26 – DEG contacts all building managers to confirm that there have been no modifications to the critical load lists for each building. A review set will be sent to HCFD end of June.
07/29/26 – DEG has not received responses from buildings.
08/26/26 – ITB pending the advertised estimate from HCFD and then goal setting worksheet approval.
09/23/26 – Project in bidding phase. Prebid meeting was held on 09/22. Bids are due 11/12/26.
10/28/26 – Project in bidding phase. (2) Addendums Issued.

All Buildings – Emergency Switchgear PM Read More »

All Buildings – Fire Damper Testing & Inspection

PM: Tony Matre, Terry Cannon
05/22/25 – Tony Matre asked for an SOSS to rebid this project in 2025.
06/25/25 – SOSS submitted.
07/30/25 – SOSS approved this month. Internal meeting conducted for kickoff to collect as-builts and setup new drawings.
08/28/25 – Drawings are nearing review status. Coty and Luke made good progress, but we have a lot of as-built items to incorporate from the last bid.
09/24/25 – We are updating the drawings for the new buildings including 525, EMA, and Mercy. Drawings should be ready for review in a couple of weeks for the whole bid package.
09/25/25 – 525 does not have any fire rated walls. CHA answered Coty about Dane.
10/30/25 – Still putting new buildings together.
12/12/25 – Original building drawings updated. New building drawings added, ready for TTC review. We noticed that several fire dampers missed in the Justice Center because of the spline ceiling are open and accessible. TTC worked with NKYHC to get a quote to update the fire dampers in the JC lobby now before the new ceilings go back in. NKYHC working with Triton to use their lift.
01/25/26 – Review sets sent to Tony Matre for distribution and review. After comments are received, we will setup the bid schedule for this project.
02/25/26 – No comments received yet, ttc checked in a couple of times.
03/25/26 – We are waiting on green light from Tony before bidding. Review sets are in for comments.
04/26/26 – Project on hold awaiting green light from Tony.
05/27/26 – DEG needs to add to buildings to the the bid and then we will start putting together the ITB.
06/25/26 – Finalized scope for new buildings, updated and found missing data from previous bid and addendums, final items being added to scope for bid package.
07/30/26 – Talked to Tony and we are removing 1701 and 111 from scope. We don’t have to wait for any additional comments from Facilities, TTC can package this up for bidding.
08/26/26 – Coty reviewed drawings this month and made changes but said he needs to clean up some items from the Coop work and he will get that done this month for my final review.
09/23/26 – Review project with Tony, putting 2026 budget together for Tony, but he also said to get the job out for bidding in October 2027.
10/26/26 – TTC will review drawings before Partner meeting.

All Buildings – Fire Damper Testing & Inspection Read More »

All Buildings – Life Safety Drawings

PM: Rycca Thacker, Eryn Thamann
01/29/25 – SOSS requested. JN to confirm what buildings are included in SOSS.
02/25/25 – Pending approved PO.
03/26/25 – First site walk 03/27 at 230. Other buildings shall be scheduled after initial 230 bldg walk.
04/24/25 – 230 Building progressing. Examples with a few questions sent to HCFD for review/approval on 04/22. Elevar is scheduling other buildings with onsite facility managers.
05/28/25 – Example of 230 building was approved by HCFD. Site walks for TPC, 800, CH buildings have also been performed. Need updated drawings for JC care pods and TPC to accurately show floor plans. Need facility manager contacts for remaining locations to schedule site walks.
06/26/25 – JC walk-thru scheduled for 07/02 – 07/03.
07/31/25 – JC walk-thru occurred and Elevar has questions re: JC. Elevar received CH comments from Court Admin and an additional walk-thru is needed to confirm map orientation. Remaining buildings have not been walked yet.
08/28/25 – Evac maps for 230 building provided to HC on 08/27. Other buildings are ongoing.
09/25/25 – All maps will be provided before 11/01. Building 230 has been turned over.
10/30/25 – Evac maps are progressing and on schedule for 11/01 deadline except for a few floor plans where Elevar doesn’t have updated plans and can’t get updated plans.
12/11/25 – All buildings except Hillcrest campus and 6th Floor CH plans have been provided to HCFD with additional JC detainee-area evac plans.
01/29/26 – One floor of CH and Hillcrest to be completed by end of next week. Awaiting Tri-County drawings.
02/26/26 – Elevar working on final 111 Tri-Co drawings now and expect completion in approx. one week.
03/26/26 – Complete with 111 Tri-Co. Portion of Hillcrest remains until further notice.
04/30/26 – Complete. Keep project open for Hillcrest?
05/28/26 – No update.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – SOSS provided to complete 1701.
09/24/26 – No update on SOSS for 1701. CAD/pdfs provided to HCFD for other completed buildings.
10/29/26 – No update.

All Buildings – Life Safety Drawings Read More »