PM: Tony Matre, Terry Cannon
09/26/24 – SOSS Requested.
10/30/24 – SOSS submitted. Preliminary project setup has begun. TTE needs to add three buildings to the bid this time around, 111, 525, 4210 Dane, Crime Lab and Coroners Office.
12/12/24 – Approved SOSS and PO not received yet.
01/28/25 – PO received. Preliminary specs assembled by Barrett. We need to scheduled fieldwork to confirm quantities. We heard the first deadline for draft review is end of February.
02/26/25 – Limited updates, we will be working on this one in March.
03/25/25 – No updates. We still plan on bidding this job by end of April.
04/23/25 – Fieldwork is completed. New buildings are added, old buildings are removed. Specs have been updated for 2025 Code references. The Project manual is ready for Tony Matre review.
05/28/25 – TTC compiling proposed bid cost to request the ITB number for this project. Trying to scheduled a two day prebid for this project. Bid will be in June.
06/25/25 – Prebid meetings scheduled for July 9,10.
07/21/25 – Addendum #1 sent to bidders.
08/28/25 – Bids opened and awardable. SA Comunale had only openable bid. Next steps by County.
09/24/25 – Contract being drafted. We answered some questions about the give year testing.
10/29/25 – Archive.