PM Jesse Estes, Sam Hofmann
09/26/24 – Project to go out to bid next week.
10/31/24 – Project is out to bid. Bid opening is 11/8.
12/12/24 – No bids received. Project went back out to bid and is opening today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future. Permit to be submitted in near future.
2/27/25 – Contract in progress.
03/27/25 – Kick-off scheduled for 4/2.
04/24/25 – Kick-off held. Submittals received. Mobilization to be scheduled.
05/29/25 – No update.
06/26/25 – No update.
07/31/25 – No update.
08/28/25 – Waiting on background checks to clear to begin.
09/25/25 – Concrete grinder sub walked out on project. Alpha is searching for replacement.
10/30/25 – Alpha found replacement grinder sub. Alpha discovered that all furniture on the 5th floor of the north building has been tack welded to the bolts. all furniture in the day space area will be removed and re anchored. All cell furniture will be grinded around as best as possible.
12/11/25 – Pods are complete. Alpha to begin central hallway.
01/28/26 – Scope Complete. Waiting on closeouts.
02/26/26 – Closeouts received and missing items requested.
03/26/26 – Items still outstanding.
04/30/26 – Items returned. Hard copies outstanding.
05/28/26 – No Update.
07/30/26 – Closeouts delivered to County.