Hamilton County Facilities

230 – Façade Repairs (F016)

PM: Matt Butz, Fateme Shahiyan

08/29/24 – County request THP rebid Alternate Façade repair package from SOSS F003. SOSS Hamilton County.
09/23/24 – THP published review drawing to County.
09/23/24 – County provided review comments to THP.
09/26/24 – Final bid to be released to purchasing with Advertise to bid scheduled for 9/30/24. Bid opening scheduled for 10/30/24.
10/16/24 – THP issued Addendum No. 1 – (prebid minutes and updated prevailing wages).
10/21/24 – THP issued Addendum No. 2 – (update to sheet metal prevailing wages).
10/30/24 – Bids were received.
10/21/24 – THP issued Addendum No. 2 – (update to sheet metal prevailing wages).
10/30/24 – Bids were received and BCR was the lowest bid.
11/05/24 – THP had a Bid Review with BCR
11/14/24 – THP sent the bid summery and recommendation letter for BCR to Hamilton County.
01/16/25 – Preconstruction meeting completed.
01/29/25 – Progress meeting completed.
01/30/25 – Project status – BCR has rigged and complete the first knock down survey of the north elevation. Work will progress north to west to south.
02/21/25 – Crew moved to the west elevation to do the knock down and have the spots ready to patch when temperature gets better in the next week.
02/24/25 – BCR send out Pay App No.1 for THP review and THP approved that.
03/17/25 – BCR Completed all repairs at TPC. THP did the final site visit and did not observe any problem with repairs.
03/26/25 – BCR start installing the swing stage on roof for the north return wall of the building.
03/31/25 – BCR completed the work and sounded the north return wall. No major sports or damage.
04/04/25 – BCR submitted pay app No.2 and was approved by THP. BCR needs to provide the closeout documents.
05/27/25 – BCR is working on the closeout documents, and they are planning to provide all documents by end of the week.
06/10/25 – BCR has provided all closeout documents, which have been approved by THP. BCR is in the process of sending the notebooks and USB drive containing the documents to the County. Once that is completed, THP will send the signed final pay application to HC.
07/30/25 – Project status: All closeout documents approved. Waiting on project notebooks.
08/26/25 – BCR planning on complete the closeout documents and send it to the county by end of the next week along with the TPC project.
09/15/25 – BCR dropped off the closeouts documents to HC/Matt Butzz. However, the electronic documents, notarized warranties and 2 payrolls for the project were missing. BCR is planning to provide the documents by end of this week.
12/11/25 – All project closeout sent to County and final pay application approved.

Scroll to Top