PM: Matt Butz, Mike Barth
02/28/24 – TEI, HCJC, and HCFD meet on site to discuss the project objectives and locations where coverage is needed. Review set to be sent to HCFD on 3/1/24.
02/29/24 – Jaime will get Mike a set of review drawings EOD today, sent to Matt tomorrow hopefully.
03/27/24 – Documents completed and Dent to HCFD. Meeting with Juv Ct, HCFD, Telecom, and Jason/Todd on site to review and adjust. Documents completed for installation.
04/24/24 – installation pending material procurement.
05/29/24 – TEI has received no updates. BW asked if O’Rourke has provided any of county paperwork yet? Answer, no.
06/26/24 – DK arrives on site to begin installation. Installation ongoing. Risk Mgmt has decided that the NVR will be located on the downtown campus and feed will come back downtown.
07/24/24 – HCFD and TEI to perform punchlist pending HCFD availability.
10/31/24 – Need change order to relocate NVR to Security Bldg.
12/11/24 – Punchlist issued and DK sends back signed completed punchlist.
02/26/25 – project complete pending final closeouts.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – OK to Archive.