PM = Matt Butz, Mike Barth
12/06/23 – TEI receives approved SOSS. Project kick off meeting to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet on 01/30 to discuss project objectives and kick off the project. Network switches for the Kiosks and Camera systems shall be put in a lockable rack that will prevent local CO’s from tampering with them. The outlets that serve the overhead rack and the floor mounted Telecor Intercom racks will have lockable covers over them such that they can not be unplugged.
02/28/24 – Project is ongoing.
03/27/24 – Project is ongoing with documentation.
04/24/24 – Review set to be sent to HCFD upon completion.
05/29/24 – no updates
06/26/24 – TEI selects lockable racks. TEI recommends racks with solid doors (versus glass doors), but the glass doors are slightly less costly. ($100-$150 per rack).
07/24/24 – TEI to deliver review set to HCFD end of week of 08/05.
08/28/24 – TEI submits documents to HCFD for review and comments. Project will be issued for bidding upon receipt of comments.
12/11/24 – HCFD and TEI meets with HCFD to review documents. Final comments to be incorporated and project issued for bidding first of year.
01/29/25 – Small projects bid to be issued on 01/31/25
02/26/25 – Project in bidding phase.
03/26/25 – Received (2) bids. Dunn Electric and DK. Dunn apparent low bidder. TEI vets Dunn bid.
04/23/25 – Project in contract phase with prosecutors office.
05/28/25 – Project in contract phase.
06/25/25 – Project in contract phase.
07/30/25 – Const KO to be scheduled with Dunn and HCFD.
08/27/25 – HCFD, HCSO and DEG have const kick off with Dunn Electric. Materials roughly a month out.
09/24/25 – DEG approves submittals. Dunn Electric orders equipment. Dunn sends an email to DEG re equipment cost increase from bid time.
12/10/25 – All LC racks are installed, except G22. Ceiling by rack needs to be raised for the proper NEC clearances for the existing solenoid panels.
01/28/26 – Waiting for HCSO to move their equipment to move ceiling to wrap up the G22.
02/25/26 – Waiting for HCSO to move their equipment to move ceiling to wrap up the G22.
03/25/26 – Triton on site moving ceiling 03/25. Dunn to install new enclosed rack upon completion of ceiling work.
04/29/26 – All work completed. Punchlist completed. Contractor to submit closeouts.
07/29/26 – Project in closeout. DEG discusses with EC closeout docs needed.
08/26/26 – no updates.
09/23/26 – Project complete – pending closeouts.