Hamilton County Facilities

230 – Access Control System Upgrades 2023

PM: Matt Butz, Mike Barth
12/06/23 – TEI issues SOSS.
01/30/24 – TEI receives signed SOSS and PO.  Project documents to proceed.
02/28/24 – Project is ongoing
03/27/24 – On site investigation  and kick off meeting with DK occurred on 03/26/24
04/24/24 – Review set will be sent to HCFD upon completion.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations.  TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for HCFD review.
07/24/24 – Construction completed. HCFD and TEI completed punchlist walk.
08/28/24 – Project pending closeout documents.
12/11/24 – No Updates
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – Archive.