Hamilton County Facilities

Hillcrest – Campus Repairs Phase 2

PM: Megan, Sam, Hofmann, Terry Cannon

01/27/25 – Create new project for tracking.
02/26/25 – ThermalTech has preliminary started creating the second phase floor plans for MEP.
02/27/25- Because this is tied to Federal Grant money, Phase 2 may not proceed and potentially fall back to Trades to do the work hodgepodge in the future. CCF Grant Funding in summer 2025 at state level and make give us some indication of what we are doing future.
03/25/25 – Project on hold until further notice.
04/23/25 – Project on hold.
05/28/25 – Project on hold.
06/25/25 – Project on hold.
07/30/25 – Project on hold.
08/28/25 – Project on hold.
09/24/25 – Project on hold.
10/30/25 – Project on hold. High level cost was sent to Rycca for grant purposes include the updated cost for design partners. updated Kitchen cost also sent to County.
12/11/25 – No update.
12/12/25 – Some items in Phase 1 being moved to Phase 2 for example school sink solids interceptor, repairs in Maple cottage, dining rec RCP.
01/28/26 – No Update.
02/26/26 – No Update.
03/26/26 – No Update.
04/30/26 – Grant is pending. Scope will be reduced to fit budget of grant. SOSS incoming to right size fee for reduced scope.
05/28/26 – No Update.
06/25/26 – 1.5 million grant awarded. Phase 2 scope meeting held. County to determine budget and design partners to provide updated SOSSs.
07/30/26 – No Update. Remove from list.

Scroll to Top