PMs: Tony Matre, Terry Cannon
01/27/25 – Wireless space pressure sensors installed 1/24. Initial pressure readings indicate the water heater room is slightly negative (0-0.025 in WG) compared to both outside and the elevator machine room. The observed airflow showed consistent flow from the elevator machine room into the water heater room and from the water heater room to outside, suggesting the pressure would be elevator machine room > water heater room > outside. The observed draft on the water heater was a slight backdraft from the flue into the water heater room. The thermal camera was used to look for temperature gradients in the flue which could indicate a clog, but none were observed. ThermalTech is continuing to observe pressure readings and look for irregularities.
02/26/25 – Wireless equipment has been installed and we are monitoring the room. We have had one incident where the air seemed to be moving into the elevator room. TTC discussed with Glen cover all transfer openings and continuing to monitor for another 30 days.
03/13/25 – Covers were placed on the VAV duct and the transfer grill between the mechanical room and elevator to isolate the room from draft influences. Another test was conducted when there was little draft by opening the door to provide combustion air, but this did not fix the issue either.
03/25/25 – Draft still an issue. ThermalTech camera the flues and found them to be clear.
TTE brought in a Enervex for a third party review of the installation. They suggested extending the flues another 6ft each and thought the additional elbows added below the heaters might be a problem, they are running flue calcs for us to review.
04/23/25 – Project recommendations sent to Tony and Glenn and some additional conversation was had, but we have not been given direction to where to go next. We recommend new roof penetration and longer flue pipes to eliminate the issues.
05/28/25 – Project on hold.
06/25/25 – Waiting on County direction for next steps.
07/30/25 – Prices came back too high and too much scope. Barrett reached out to DK to realign cost and scope.
08/28/25 – Prices updated and given to Tony and Glen for next steps.
09/24/25 – Archived.