Hamilton County Facilities

[General Services] – Champlin-A

Champlin Architecture Archived General Service Projects

2026 Project Cost Estimates

PM: Rycca, Mike, Sam, Eryn, Terry, Mike, John

07/31/25 – We discussed the quantity of 2026 projects coming our way and we think about 20 project are new. The County will self-inflate the refresh cost estimates. Rycca will print and share the original list with us soon.
08/20/25 – ThermalTech received approved SOSS received from County.
08/28/25 – TTE Internal kickoff start, completion matrix created, Champlin assignments accepted and the TEI MBE partner engaged for work this year. Elevar SOSS submitted to HC 08/27.
09/24/25 – ThermalTech DEG working on estimates, most are done. Fieldwork in JC scheduled for this week. Gazelle will start uploading to Archibus this week.
09/25/25 – Elevar estimates ongoing and meetings with tenants scheduled.
10/30/25 – Elevar complete with estimates. ThermalTech complete with estimates.
12/11/25 – Complete. Davies partner creating binder PDF of each estimate before module is closed.

2026 Project Cost Estimates Read More »

2025 Project Cost Estimates

PM Watts, Murphy, Cannon, Millar, Barth, Thomas, Thamann
04/25/24 – Project module is open for 2025 projects.
06/27/24 – Murphy has assigned estimate leaders on each estimate, sent to all partners for approval.
06/27/24 – BW suggested that we meet with every requester and get their input on the submitted request. And we coordinate when the walk through will happen. Architectural they always needs to meet with county people. Budgets due on 7/12/24. This project is due end of August.
07/22/24 – Elevar – SOSSs submitted for CIP, New, and Resubmitted 2025 projects.
07/24/24 – ThermalTech – our approved SOSS was received last week, we’ve started the work, our electrical resubmittals are done, Champlin and Elevar are setting up field trips.
07/25/24 – Champlin submitted SOSS and has all the new projects fieldwork scheduled for last week of July and first week of August.
08/27/24 – Elevar: SOSSs approved and estimates ongoing.
08/28/24 – ThermalTech: Almost all field is compete. NEW and CIP estimates are progressing nicely, much of the data has already been entered. RESUBMITTED projects have been updated for Electrical Scope, Mechanical, Plumbing and Fire Scope are being update and reviewed this week. Mike Barth and Terry Cannon should begin QC reviews first of September. MBE currently entering all estimates that TTE has completed and turned over for entry. For New Estimates Completed 62% Elec, 31% Mech, 29% Plumbing, 28% Ready for Final Review.
09/24/24 – ThermalTech is complete with all entries. TTC and MCB are currently reviewing the data entered for the QC process except that TTC has to enter the 800 controls estimates manually. Elevar is complete with all entries.
10/29/24 – ThermalTech: all ThermalTech estimates are entered.
12/12/24 – ThermalTech has printed PDF binder files for its estimates.
12/31/24 – Ready to Archive.

2025 Project Cost Estimates Read More »

THP 2024 General Services (F093)

PM: Bert Watts, John Millar
10/24/23 – Hamilton County requested SOSS.
10/31/23 – THP provide SOSS for review.
11/08/23 – Hamilton County approved SOSS.
02/29/24 – Record Center roof was noted to be leaking in a number of locations. Roof is under warranty. THP documented the conditions and met with the manufacturer and contractor. Manufacturer’s warranty department has approved a repair approach. Contractor is pricing.
02/29/24 – 800 Broadway tile in NE stair tower had cracking at the first floor level. THP coordinated contractor stabilization, removal and repair. Repair is complete. THP to provide a summary report.
04/25/24 – THP no update.
06/27/24 – Record center roof repair started today and is planned for the next 2-3 weeks. THP scheduled to be on site Friday to review progress.
07/12/24 – Tremco completed warranty repairs and submitted reports for review.

THP 2024 General Services (F093) Read More »

2024 Project Cost Estimates

PM: John Nester, All Partners
06/29/23 – SOSS requested and approved for all partners
07/27/23 – Estimates underway. Vendor prices coming in for TTE new projects and estimates are being updated as we get information and quotes in. Re-estimates are also being updated with 2024 pricing. Discuss floor plans need with Champlin for New A/E estimates.
08/28/23 – ThermalTech has 40 of 48 new estimated ready for internal review. We have 68 of 179 re-estimates ready for internal review.
09/25/23 – Project estimates are complete. Champlin, THP and ThermalTech completed last Friday. TTC sent a summary of items for the Re-estimates to the team on Monday.
12/15/213 – Archive project.

2024 Project Cost Estimates Read More »

2023 Project Cost Estimates

PM: Bert Watts, All Partners
05/25/22 – All estimates sent to Partners for SOSS
06/29/22 – ThermalTech has started updating estimates in the Archibus module. Several reestimates are complete. We are gathering information on the new projects but we need them set to estimating and we have to give them updates on scope and equipment for estimating before they start entering new ones in earnest. We have started requesting prices from vendors as well. We will send the County list for access. It would be helpful to have a coordination meeting on who is leading and who is working on the combined estimates.
05/31/22- THP Issues SOSS for review by the County.
06/10/22 – THP SOSS approved.
06/30/22 – THP developed internal spread sheet for projects. Initial draft complete. THP will publish for possible use by other partners.
07/27/22 – THERMALTECH UPDATE. Most electric cost estimates are complete and ready for Barth review. Limited mechanical estimates are complete at this time. Architectural and Structural coordinated has started for the “new” estimate. Once we get the proposed floor plans, we will update the MEP estimates.
08/24/22 – ThermalTech Update – We are working on these estimates every day to meeting Sept 1 deadline. Champlin has provided SD drawings for almost ever project for our use on the “New” estimates. We are coordinating on individual estimates on a case by case basis. Electrically, all resestimates are complete. Mechanically we have about 25 estimates remaining. We have completed several new estimates and will spend the bulk of our time next week completing the new estimates with the new drawings we’ve received.
09/04/22 – ThermalTech projects are complete for both reestimated and new estimates. TTC will review as time permits.
01/22/23 – Met with John and Ben and reviewed details that would make the Cost Estimating module better for the partners.
01/24/23 – Ready to Archive

2023 Project Cost Estimates Read More »

OMJ Accessibility Entrance Study

02/08/22 – Signed SOSS Received. Scope reduced to exterior entrance only.

03/31/22 – Field verification complete. Plan and estimate in progress.

04/28/22 – Work in progress.

5/26/22 – Civil Engineer to provide Champlin with drawings end of day friday 5/27. Final set can be ready to review the following week.

6/30/22 – Bid set and project manual submitted to County for final release.

07/28/22 – One bid came in above 50,000. Bid review to be completed to determine ITB advertised estimate.

08/23/22 – Project out to bid. Pre-bid meeting scheduled for 8/31.

09/27/22 – Bid awarded to Prus. Contracts in progress.

10/27/22 – Pre-construction meeting scheduled for 11/4

12/15/22 – Construction complete.  Punchlist by county and champlin complete. Punchlist by Kleingers to be scheduled.

01/26/22 – Punchlist sent to Prus. They are to fix items that need correcting and confirm slope conforms to code requirements.

02/22/23 – Punchlist completed. Waiting on closeout documents.

03/30/23 – Waiting on closeout documents.

04/27/23 – Close out documents received.

05/25/23 – Waiting on Prus to send final pay app.

06/29/23 – Close outs and final pay app received.

OMJ Accessibility Entrance Study Read More »

JFS – General Services

PM: Bert Watts, John Millar
06/10/21 – County requested a general structural service proposal.
06/11/21 – THP sent SOSS.
07/12/21 – County approved SOSS for TEI, THP, and CHA.
10/28/21 – TTC provided an update on low flow plumbing issues at the A&D building. In the past month, we had a major leak at the main sanitary leaving the building. Plumbers called an underground detective to survey the pipe from the building to the street. TTC to get a test kit for testing in Fifth Floor East.
04/28/22 – Loading dock upgrades and striping and loading sign.

JFS – General Services Read More »

2022 Project Request Cost Estimates

04/21/21 – Cannon created post from Bert Watts email for 2022 Project Request.
05/27/21 – Bert sent the preliminary list out to the partners for SOSS authoring. Kickoff meeting next Tuesday with TEI, THP, and Champlin.
06/11/21 – Started research on 230 MEP upgrades including new above grade boiler and chiller room.
06/22/21 – Met at Comm Center to discuss project scopes for repurposing and academy rework.
06/25/21 – User meetings held to discuss the scope for most Champlin lead estimates.
07/28/21 – Work continues on the individual estimates. Some will be complete by July 31 and all will be complete by August 31. Cost, data and scope still coming in the CH controls, Mechanical Yard items which are the “biggies” for TTC. Champlin is making progress. Smaller estimates will be done by 7/31, the rest by 8/31.
08/20/21 – Champlin has provided almost all of the floor plans we need to complete estimates. TEI is currently putting together the cost and scope documents for the remaining estimates.
08/24/21 – Teleconference held on the 230 East 9th estimates between all partners to finalize the scope and estimating. TTC followed an update later that day with additional information after speaking with BW about the #2105 estimate.
08/26/21 – TEI – work continues and we plan on making the 8/31 completion date as discussed. Estimate and drawings are being uploaded daily.
10/28/21 – Project complete. A couple of final projects have been added and updated to the list.

2022 Project Request Cost Estimates Read More »

Homeless Shelter COVID Mods

08/20/20 – SOSS signed and returned. Initial provider meetings starting this week.
08/25/20 – 09/15/20 CA, CMTA, GBBN visit all shelter sites.
09/17/20 – 09/22/20 CA, CMTA, GBBN zoom meetings with all property managers to confirm scope of work.
09/22/20 – GBBN provides CA with SD drawings for CA to proceed with implementation.
09/23/20 – CA provides Messer with preliminary drawings for pricing.
09/28/20 – Target date for getting Messer final drawings for pricing.
10/29/20 – Bid packages and Permit ready. Waiting for authorization to proceed.
12/10/20 – Waiting for Authorization to proceed
01/26/21 – Meeting with Lisa Webb and City of Cincinnati to reassign Champlin contract.
02/25/21 – No update. Final stages of dividing contract between county and city.

03/25/21 – No Update

04/29/21 – No Update

05/18/21 – Meeting with City to discuss scope and remaining fee.

06/07/21 – Final signed assignment agreement received.

07/27/21 – Contract transfer complete.

08/26/21 – Project no longer a County project.

Homeless Shelter COVID Mods Read More »

Project Cost Estimates 2020

07/24/19 – Bert discussed 2020 project schedules with team today. All partners can edit this project for updates this year.
08/28/19 – ThermalTech has received our SOSS back from Facilities and fieldwork has been started. HVAC and Plumbing have bee updated for Admin air compressors, auto title and vestibule projects. We should discussed a revised completion date for all the partners.
08/22/19 – THP provided SOSS for project cost estimates.
08/28/19 – County approved THP SOSS.
09/01/19 – ThermalTech completed preliminary estimates awaiting schematic design documents for changes.
09/10/19 – County approved Champlin SOSS.
09/26/19 – THP completed loading dock estimate and information loaded into Archibus.
10/07/19 – We met back at the Admin Building on vestibule job and modified the MEP cost a little bit. All ThermalTech projects are updated and ready to go.
10/03/19 – Project request made Scott Weikel for glass security panels to be installed at public counters on the 9th and 10th floor of the Taft Building.
10/07/19 – THP attended kick off meeting for review CAB entry project. Based on current project request, THP will not have a role in this project.
10/31/19 – THP estimate up loaded into Archibus.
11/01/19 – Champlin scheduled for field visit to verify locations and dimensions of work area.
11/05/19 – CA cost estimate for Justice Center Security Barriers uploaded to Archibus.
11/08/19 – CA updated SD plan for Autotitle project.
11/12/19 – CA cost estimate for Autotile uploaded to Archibus
11/18/19 – Cost estimate uploaded to Archibus. SD drawings sent to County.
11/11/19 – Bert Watts provided CA with new contact information for someone to walk the scope of JC Door replacement.
12/02/19 – CA cost estimate for Cab Entry uploaded to Archibus.
12/13/19 – CA visited Justice center to review scope for Justice Center Frame Replacement
12/17/19 – TEI updated plans and cost for 2020 Projects for CAB Auto Title and Vestibule project in Archibus.
01/16/20 – CA received list of doors and frames to be replaced in Justice Center from Sgt. J. McAuliffe.
02/25/20 – CA reached out to vendors for more information. In the process of putting together cost estimate based on vendors information.
02/27/20 – PDF 2020 estimates by Friday 2/28 and share with Bert when complete. No binders required for this year.

03/09/20 – Champlin reached out to Sgt. McAullife for questions regarding Justice Center Door Replacement project. Waiting on Stg. to schedule a meeting with higher ups to discuss scope.

05/01/20 – Stg. McAullife provided answers to questions of scope. Reached back to to clarify scope

06/17/20 – Scope finalized. Estimate uploaded to Archibus.

 

Project Cost Estimates 2020 Read More »