PM: Matt, Mike Barth
01/25/23 – TEI Submits SOSS. Project pending SOSS approval and PO.
02/23/23 – Project pending SOSS approval and PO.
03/29/23 – TEI receives signed SOSS and PO. Project kickoff to be scheduled with TEI and HCFD.
04/27/23 – TEI performs preliminary review of existing model. TEI and HCFD to meet to discuss next steps.
05/23/23 – TEI to set up meeting with HCFD to discuss next steps. Proposed time of 9:00 AM, on 6/8.
06/08/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC.
07/26/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC.
08/24/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC
09/26/23 – TEI develops drawings and submits to HCFD for review.
10/26/23 – TEI issues project for bids. Prebid meeting occurred on 10/25/23. Bids are scheduled to open on 11/22.
12/06/23 – Bids received and opened on schedule. Stem Electrical is apparent low bid. TEI vets bid and submits letter of recommendation. Contracts are at prosecutors office for approval.
01/30/24 – Project awaiting BOCC approval
02/28/24 – Stem Electric receives signed contract and PO. Preconstruction meeting to be scheduled in the next couple of weeks.
03/27/24 – Pre-construction meeting scheduled for 04/15/24
04/24/24 – Pre construction meeting occurred. submittals receieved , and approved. Project pending procurement of materials (approx 12 month ship date). Stem electric to confirm shipping schedule.
05/29/24 – Project pending material procurement. TEI requests Stem Electric to send in Ship date.
06/26/24 – No Updates. Project pending material procurement.
07/24/24 – No Updates.
08/28/24 – No Updates, project pending procurement of materials.
09/25/24 – Project pending material procurement.
12/11/24 – Project installation pending material delivery.
02/26/25 – Project installation pending material delivery.
04/23/25 – Project installation pending material delivery.
05/28/25 – No updates.
05/25/25 – No updates.
07/30/25 – Stem electric and DEG and HCFD meet to KO project. Gear has arrived and DEG certifies at Crane yard.
08/27/25 – Stem to begin the construction phase of this in first week or two of September.
09/24/25 – Gear is rigged into place. Outage/tie in to be coordinated.
10/30/25 – MCB to call Stem to schedule a shutdown meeting.
12/10/25 – DEG to follow up with Stem again to schedule the shutdown.
01/28/26 – Stem ready for the outage. John Nester requested pricing on refurbish breaker in the main gear. Stem is sending email of availability to DEG for meeting to discuss/schedule outages.
02/25/26 – Stem to send in proposed schedule and timelines.
02/25/26 – Stem sends in multiple proposed dates in May for tie in schedule. DEG, HCFD, Tech Svrcs, and Juv Courts to meet to discuss outage plans and select date.
04/29/26 – DEG and HCFD meet with all building tenants and discusses power outage plans. Tentative dates for outages are 5/30 for the 2nd floor and 6/19 for the sub-basement gear.
05/27/26 – 5/30 outage cancelled due to the contractor not having BGC staff. 6/19 outage still on the schedule.
06/23/26 – Second floor switch tied in on 06/19. TJW Electric provided staff that had current BGC and badge to perform the work. Basement level work to be scheduled.
07/29/26 – DEG has a virtual meeting with HCFD and Stem Electric. A list of possible Saturdays was emailed to HCFD and Stem to coordinate the next outage. HCFD to confirm the procurement of bad breaker for the distribution panel serving the computer room to be replaced by trades during the outage.
08/26/26 – HCFD states that the replacement breaker has been purchased by trades. Stem has confirmed 09/26/26 date with ESI, still pending confirmation from TJW. DEG states lets work towards making outage #2 happen on 09/26/26 so not to delay other projects. Stem to confirm with TJW and finalize the date.
09/23/26 – 9/26 date was postponed due to staffing issues with Stem Electric. New Date is 11/11/26 – starting at 07:00 AM. Pre-outage conference call scheduled for 10/28/2026.
10/28/26 – Outage is scheduled for 11/11/26. Meeting held with courts, HCSO and HCFD to discuss outage on 10/28/26.