Hamilton County Facilities

JC – Emergency Power System Replacement

PM: Matt Butz, Mike Barth, Ken Orloff
09/26/22 – HCFD requests SOSS for project.  TEI submits SOSS.
10/26/22 – TEI receives signed SOSS and PO for Project.   TEI meets with Matt Butz to discuss project.  Kick off meeting with building staff to discuss scope and project details.
12/15/22 – TEI progressing with design.  Coordinating with Vendors and developing solutions to present to HCFD upon receipt of data from suppliers.
01/25/23 – TEI in receipt of product data from manufacturers.  TEi meeting with rigging company on 02/01/23 to review scope of removing the egens and installing new in existing locations, and determine if any additional modifications are required to move the equipment in/out of the building.
02/23/23 – TEI meets with Rigging company, equipment vendors, and THP on site to confirm constructability of design.   Design documents are progressing to a point where a review set will be sent to HCFD.
03/29/23 – TEI finalizing the coordination with multiple vendors for the equipment associated with this project.   80% complete project review meeting to be scheduled with HCFD.
04/27/23 – TEI has project ready to meet with HCFD and discuss final design direction.   Meeting to be scheduled first week of May.
05/16/23 – TEI and THP discussed increasing scope of work for this project. Adding CMU partition walls and second means of egress in the existing gears rooms in both north and south buildings.
05/17/23 – TEI and THP met onsite to review the existing conditions at gears rooms in both the north and south buildings.
05/23/23 – TEI working on code required upgrades for this project.  We are coordinating with IBI and THP on the redesign.
06/14/23 – THP sent Owner Review documents to ThermalTech.
06/28/23 – TEI submits review set of bid package to HCFD PM for review.  TEI and PM review comments on 06/28/23.  TEI to incorporate the review comments and develop final bid package for issuance after the 4th of July holiday.
07/10/23 – THP waiting to hear back from ThermalTech about Owner Review Comments, ITB #, and bid date in order to issue bid set.
07/26/23 – TEI holds issuance for updated XBE ITB package information.  TEI to develop spreadsheet and work thru issuing with XBE requirements .
08/23/23 – THP has not heard any update on this project.
08/24/23 – TEI issues XBE package and gets approval.  TEI finalizing project manual for HCFDF review and project issuance.
08/31/23 – Go ahead and get pre bid coordinated and final XBE items. Get out for bid.
09/27/23 – THP – Project tentatively out to bid on October 4th.
09/26/23 – TEI submits project manual to HCFD for final approval.  will issue for bidding once manual is approved.
10/04/23 – Project advertised to bid.
10/18/23 – Pre-bid meeting occurred at the Justice Center.
10/26/23 – TEI issues project for bidding.   Prebid meeting occurred on 10/18/23.  Bids are scheduled to open on 11/09.
11/02/23 – Addendum #1 issued.
11/22/23 – Bid Opening.
12/06/23 – (1) bid received, in awardable budget range, but DEI determined XBE submission was not in accordance with requirements and recommended for rejection.  Pending BOCC decision.
01/31/24 – No new updates from THP.
02/28/24 – THP no new updates from THP.
02/28/24 – Project to be re-bid with the fuel tank work bid as a separate project.
03/27/24 – TEI repackages project and will send to HCFD in next 2 weeks for review prior to ITB.
04/24/24 – No new updates from THP.
04/24/24 – TEI sends HCFD re-packaged documents for review.   Upon receipt of review comments, and approval of GSWS from DEI – project to be re-issued.
05/13/24 – THP sent updated drawings and specs to ThermalTech for rebid on 05/15/24.
05/29/24 – Project issued for rebid.  Project prebid meeting occurred on 05/29/24.  Bids Due on 07/11/24.
06/26/24 – Project bidding.
07/24/24 – Project bid opening on 07/24/24. NO BIDS received. TEI contacts electricals to see why no bids.
08/29/24 – No new updates from THP.
08/28/24 – No Updates.
09/25/24 – No Updates.
09/26/24 – No new updates from THP. County requested new SOSS and include the underground tank with the scope again as an Alternate. Bring Terracon in for the Geotech in this SOSS.
12/11/24 – TEI submits SOSS and receives signed SOSS and PO for re-bid. Project to be re-packaged for re-bid starting in January.
01/29/25 – TEI repackaging the documents – send to Purchasing on on 2/10, available for bidding 2/11.
01/30/25 – Ready to Archive, start new Project file.