Hamilton County Facilities

TPC – Hydraulic Elevators Modernization

PM: Matt Butz, Mike Barth
09/26/22 – HCFD requests SOSS for Upgrading the Hydraulic Elevators at the TPC.  TEI submits SOSS.
10/26/22 – TEI receives signed SOSS and PO for Project.   TEI meets with Matt Butz to discuss project.  Kick off meeting with building staff to discuss scope and project details.
12/15/22 – TEI progressing with design.  Working towards submitting owner review set to HCFD on or before 12/23/22.
01/25/23 – TEI issues project for bidding.   Prebid Meeting scheduled for 02/09/23.  Bids scheduled to open on 02/22/23.
02/23/23 – a single bid was received (graybach) and it was double the advertised estimate (nearly triple the cost bid 6 months ago as an alternate to the original elevator project).  Bids were rejected.
03/29/23 – Project pending revised scope and/or revised budget discussions with HCFD.
04/27/23 – Project pending revised scope and/or revised budget discussions with HCFD.
05/23/23 – project has been re-designed with the scope of base bid being the aesthetic upgrades to match the traction elevators, and the mechanicals of the upgrades being bid as alternates.   TEI sends drawing to HCFD for review.  HCFD to update the AIA’s, and TEI to send project manual for final review.  By June 1, issue dates, and ITB to be received from purchasing and project to be re-issued for re-bid.
06/28/23 – Project issued for bidding.  Prebid meeting scheduled for 07/06/23 and bids are due on 07/19/23.
07/26/23 – Project bids received.  (2) awardable bidders submitted bids (Alpha Const and Graybach).  Alpha was apparent low bid, had clerical errors in bid and submitted a retraction letter for retract bid.  TEI and Champlin  vetted the Graybach bid and are recommending acceptance of the Graybach bid.
08/24/23 – Project in submittal phase and product procurement phase.
09/26/23 – BOCC approves project.  Project to commence upon PO and kickoff with Graybach.
10/26/23 – project is in submittal approval phase.   Once all submittals are approved, equipment will be procured.  Upon receipt of equipment, installation schedule will be developed.
12/06/23 – All submittals have been returned.  equipment in procurement phase.
01/30/24 – First Hydro unit (elevator #5) scheduled to begin the refresh work in mid February.  To allow new Traction to be run (open to public) for 4-5 weeks prior to taking the second traction out of service for modernization.
02/28/24 – Schedule of elevator #5 pushed until after the second tractor elevator is completed.  Materials received at American elevator, and ThermalTech to certify materials upon confirmation that Graybach and American have confirmed that the materials are the correct equipment.
03/27/24 – TEI certifies material.  HCFD requests CO pricing for additional scope.  Graybach pricing up the changes.
04/24/24 – Project progressing.   Schedule pending inspections of Elev #2
05/29/24 – Hydro units scheduled to start Modernization upon completion of Freight elevator (approx Beginning of Aug)
06/26/24 – No Updates.
07/24/24 – The first Hydro elevator to be taken out of service for the modernization in next week or two (pending no issues with Freight Elevator inspections.
08/28/24 – Elevator #5 out of service being worked on. Graybach indicates that they are on schedule.
09/25/24 – Elevator #5 passes elevator inspection. Generator test completed during building power outage for switchgear cleaning.
10/30/24 – Final elevator nearly complete. Graybach requesting punchlist mid week of 11/04.
12/11/24 – Fianl elevator inspection passed and complete. Punchlist complete. Project pending final closeout documents.
01/29/25 – Graybach sends closeout docs to TEI for review. Pending MCB review.
03/26/25 – TEI reviews and submits closeout docs to HCFD.
04/23/25 – Project can be closed out.

Scroll to Top