PM: Matt Butz, Mike Barth
12/06/23 – TEI receives signed SOSS. Design kickoff to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet to kick off project. Locations and desired coverages discussed. TEI can develop documents based on meeting on 01/30. Roof camera replacements are first priority.
02/28/24 – TEI developing plans based on meeting. Will coordinate the issuances with HCFD.
03/27/24 – Drawings to be completed in April/May.
04/24/24 – Drawings in process.
05/29/24 – No updates
06/26/24 – TEI hand delivers drawings to HCFD for review.
08/28/24 – Project complete pending closeout documents.
12/12/24 – OK to Archive.