PM: Matt Butz, Mike Barth
12/06/23 – TEI receives approved SOSS. Design Kick off meeting to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet to discuss project objectives and kick off project on 01/30. Options and existing conditions were discussed. Card reader to be connected to the VAX system in the building managed by Risk Management. Door across the hall from Lincoln Base to be added to access control system as an alternate.
02/28/24 – TEI developing plans for this project. Based on kick off meeting for Council Rooms – the VAX controller may be upsized to accommodate additional doors that are desired to be on VAX system.
03/27/24 – TEI Proceeding with documents. Upon VAX confirmation, will complete documents.
04/24/24 – Documents in progress. Review set to be sent to HCFD upon completion.
05/29/24 – no updates.
06/26/24 – Documents near complete. TEI will send HCFD review set in next couple of weeks.
07/24/24 – TEI to deliver review set by end of week of 8/5/24.
08/28/24 – TEI sends documents to HCFD for review. Will issue bid package once review comments received and included in documents.
12/11/24 – HCFD and TEI meets with HCFD to review documents. Final comments to be incorporated and project issued for bidding first of year.
01/29/25 – Documents sent to DK for GSA Pricing.
02/26/25 – DK sends GSA pricing for project to HCFD and TEI. Project pending contract.
03/26/25 – Pending contract approval.
04/23/25 – Pending contract approval.
05/28/25 – Project in contract phase.
06/25/25 – DK, DEG and HCFD have construction KO meeting. Construction to commence approx 06/27.
07/30/25 – DEG reaches out to DK for installation update.
08/27/25 – All equipment installation nearly complete.
09/24/25 – Base bid work complete. Pending CO work (added door).
12/10/25 – Change order issued for additional work. Pending procurement and installation of additional devices.
01/28/26 – Project pending the completion of the CO work.
02/25/26 – No update
03/25/26 – no update.
06/23/26 – Project closeout and final pay apps requested from DK.
07/29/26 – DEG follows up with DK for Closeouts.
08/26/26 – no updates
09/23/26 – Grant extended. Additional security measures drawing by DEG and priced by DK.
10/28/26 – Installation of additional items in progress.