PM: John Nester, Mike Barth
12/06/23 – TEI receives approved SOSS and PO. COA to provide TEI with locations of cameras that were discussed with vendor.
01/30/24 – TEI to receive the locations and document on documents.
02/28/24 – TEI will document locations upon receipt.
03/27/24 – TEI, HCFD and DK meet, document locations, and develop drawing. Meeting with all team on 03/26/24 to review and finalize.
04/24/24 – Installation pending material procurement.
05/29/24 – Completion of this project pending punchlist once TEI notified all install work is complete.
06/26/24 – Cameras are installed and the users are working on getting the monitoring functioning (instructions from installer (DK) via email), and Matt Butz helped with Valerus integration to allow end users to utilize the system.
07/24/24 – TEI and HCFD perform punchlist on the project. Tenant confirms views are as desired.
08/28/24 – Project complete pending closeout documents.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.