PM: Matt Butz, Mike Barth
01/25/23 – TEI submits SOSS. Project Pending SOSS approval and PO.
02/23/23 – TEI receives approved SOSS and PO. DK to procure equipment and project in commencement phase.
03/29/23 – DK has initiated the installation. TEI and HCFD to provide punchlist upon Notice of substantial completion.
04/27/23 – DK working on project. Const progress meeting scheduled for 05/03/23.
05/23/23 – TEI, DK, HCSO and HCFD provide punchlist. TEI documents locations of cameras and network switches for record drawings. TEI to submit the record drawing to HCFD upon completion.
06/28/23 – upon receipt of all close out documentation from DK, project will be closed out.
10/26/23 – TEI reached out to DK (Electrical division at DK under major changes – several EEs have transitioned out of DK) for final closeout documents so project can be closed and archived.
12/06/23 – TEI to document the as-built conditions for this project with the Exterior Camera project II.
02/29/24 – Ready to archive.