PM: John Nester, Mike Barth
12/15/22 – ThermalTech submitted SOSS and it’s approved. TEI to schedule fieldwork next week.
01/06/23 – TEI met Ian on site for kickoff meeting. MCB, Alex, TTC onsite to review.
01/25/23 – Bert said to concentrate on immediate needs first.
02/23/23 – TEI submits immediate needs draft report to HCFD.
03/29/23 – TEI to develop schedule for Phase II of report. TEI submits SOSS for implementation of Phase I study results.
04/27/23 – See Emergency Power upgrades for Phase 1 updates. TEI and HCFD to develop schedule for phase 2 study.
10/26/23 – TEI and HCFD develop schedule (preliminary with options focusing on emergency heat in winter) to be sent to Bert on 10/27/23, and final draft sent to Bert on 11/10/23