PM = Rycca Thacker, Mike Barth
01/25/23 – TEI Submits SOSS. Project pending SOSS approval and PO.
02/23/23 – TEI receives approved SOSS and PO. Project kickoff to occur and work to be completed.
04/27/23 – TEI to submit review set to HCFD by 05/03/23
05/23/23 – TEI submits drawings to HCFD for review. TEI receives comments from HCFD. TEI to update the drawings from the comments and develop bidding documents.
06/28/23 – TEI and HCFD PM finalized small projects bid package and issues to selected XBE companies for bidding. Bids due back to TEI on 07/13/23.
07/26/23 – TEI invites 8 XBE and 1 non-XBE bidders to give costs on project. Recieved (1) bid. bids came in higher than expected. TEI sends bid information to project manager and waiting for further decisions.
8/24/23 – TEI vets bid from Glenwood electric, and makes recommendations to HCFD. Project pending contract approval.
09/26/23 – TEI approves submittals. Installation pending product procurement.
10/26/23 – Glenwood electric has equipment ordered and scheduled to ship beginning of November. Upon receipt of all materials, installation will be schedules.
12/06/23 – Glenwood working on install schedule.
01/30/24 – Project install complete. TEI and HCFD perform punchlist. Upon completion of all punchlist items, and receipt of closeout documents, project will be complete.
02/28/24 – The Original bid portion of the project punchlisted. CO work waiting on material procurement and scheduled install date.
03/27/24 – The Air Curtian Fan is installed. Final punch items be completed this week. Then project can be closed.