Hamilton County Facilities

A&D – South Entrance Access Control

PM = Rycca Thacker, Mike Barth

01/25/23 – TEI Submits SOSS.  Project pending SOSS approval and PO.
02/23/23 – TEI receives approved SOSS and PO.   Project kickoff to occur and work to be completed.
04/27/23 – TEI to submit review set to HCFD by 05/03/23
05/23/23 – TEI submits drawings to HCFD for review.  TEI receives comments from HCFD.  TEI to update the drawings from the comments and develop bidding documents.
06/28/23 – TEI and HCFD PM finalized small projects bid package and issues to selected XBE companies for bidding.  Bids due back to TEI on 07/13/23.
07/26/23 – TEI invites 8 XBE and 1 non-XBE bidders to give costs on project.  Recieved (1) bid.  bids came in higher than expected.  TEI sends bid information to project manager and waiting for further decisions.
8/24/23 – TEI vets bid from Glenwood electric, and makes recommendations to HCFD.  Project pending contract approval.
09/26/23 – TEI approves submittals.  Installation pending product procurement.
10/26/23 – Glenwood electric has equipment ordered and scheduled to ship beginning of November.   Upon receipt of all materials, installation will be schedules.
12/06/23 – Glenwood working on install schedule.
01/30/24 – Project install complete.  TEI and HCFD perform punchlist.  Upon completion of all punchlist items, and receipt of closeout documents, project will be complete.

02/28/24 – The Original bid portion of the project punchlisted.  CO work waiting on material procurement and scheduled install date.

03/27/24 – The Air Curtian Fan is installed.  Final punch items be completed this week.  Then project can be closed.

Scroll to Top