JC – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after fist walk of 230 bldg. Need updated drawings from Champlin and door labels from HCFD that match fire door report.
04/24/05 – Walk-thru not scheduled yet.
05/28/25 – Elevar needs building info that matches between original LSS report and building plans. Current plans don’t have door numbers listed and LSS report has inaccurate photos of doors. Walk-thru on hold pending further info.
06/26/25 – JC walk-thru scheduled for 07/02 – 07/03.
07/31/25 – Walk-thru performed but drawings have not been updated yet.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates almost complete but can review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – Paint removal will occur at JC. Elevar reviewed JC with Sheriff’s and a few items will be revised. No updates on progressing project into bidding.
07/30/26 – Elevar had questions regarding anti-ligature closer locations at JC and emailed to HCFD. List of doors needing paint removed sent to HCFD. Need final allowance amount from HCFD to add to bidding docs for door re-certificaiton/replacement if paint removal doesn’t work.
08/27/26 – Questions still remain for JC anti-ligature items but will be confirmed prior to bidding. HCFD to provide allowance figure for re-certification.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.