PM = John Nester – Mike Barth
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO.
01/29/25 – TEI and HCFD to conduct study walk thru of building in next 2 weeks.
02/26/25 – TEI requests time with HCFD to perform study walk thru
03/26/25 – TEI and HCFD walk the building to locate/document the existing WiFi system devices. Report is in progress.
04/23/25 – TEI to have draft report for review by HCFD/2020 staff by mid May.
05/28/25 – TEI has a draft review meeting with the HCFD/2020 staff. TEI finalizing a few modifications to the draft and will distribute to team for review/comments.
08/27/25 – DEG sends final report with HCJC comments included.
10/29/25 – DEG addresses C Walsh questions via email
12/10/25 – No updates this month