JC – Fire Pump Replacement (085-24)

PM: Matt, Terry Cannon
Closeout: Haeli Johnson, hjohnson@tritonservicesinc.com, Dayna O’Brien, dobrien@davieseg.com

 


01/24/24 – Post created for tracking.
02/01/24 – TE to submit SOSS for this project.
02/23/24 – Coty will be working on this job.
03/22/24 – Initial fieldwork started this week. SOSS submitted. Electrical review scheduled for next week to ensure fire pump feeders meet current code. Life safety code updates may apply to this upgrade.
04/08/23 – Met with our electrical group this week to discuss the power feeders to the fire pump. We decided the best course of action that saves the County the most money is to let the Emergency Power project go first and update the MCC disconnects to isolate the fire pump disconnect in its tub so that it meets current code. Once that work is complete, we can bid out the replacement of the fire pump with out running into issues with the new NEC requirements for feeders in concrete or the fire pump being fed first before ancillary equipment.
04/24/24 – The preliminary drawings are ready for TTC review.
05/29/24 – TTC marked up drawings for owner review. TEI working with Fire Marshal on component required for replacement versus new NFPA code. This has to be bid this year even though it will be installed after the Emergency Gen update.
06/26/24 – Final drawings are ready for review, changes have been made from our field trip with Andy earlier this month. CFD not willing to provide pumper truck for weekend, we are checking on rental fire pumps and fire watch. SA believes a fire watch can be used.
07/24/24 – We were waiting on the JC Emergency project to be awarded so we could move forward with bidding our design out. The FPC will provide the fire watch as needed to make these piping changes and replace the pump vs using the CFD. I have not seen any CFD response in writing to our design request.
08/28/24 – Final internal review scheduled Friday.
09/24/24 – Project is out for bid. Prebid scheduled for Oct 8 at 9am. Bid Opening is Oct 30.
10/30/24 – Bids opened with four bids under budget, two of which were non-awardable due to a bond issue. TTE to interview KFI on Friday for compliance to bid specs.
12/12/24 – Triton was the low bidder via the base bid and Alternates accepted, we await the contract and PO to have the kickoff meeting.
01/30/25 – Contract going to commissioners tomorrow for approval.
02/26/25 – Contract is back, we are setting up Pre-Const meeting.
03/25/25 – Pre Const meeting was held and meeting notes distributed. Schedule, SOV, and equipment submittals have been requested.
04/23/25 – Construction Meetings started. Stamped permit drawings have been sent to Triton for submissions. Submittals have been requested. Other project startup documents have been requested.
05/28/25 – ThermalTech received written direction on suction valve controller which is not required on this replacement as long as we have the low suction cutoff report as a supervisory back to the FACP. We are approving the Fire Pump Controllers and rejecting the Fire Pump and Jockey pump due to under sizing and rotation issues.
06/25/25 – Equipment ordered and waiting on equipment delivery. The latest ship date is September 18, 2025.
07/30/25 – Pump submittals are finally approved. Bulletin #1 drawings sent for pricing to fix test header.
08/28/25 – Latest update is that the fire pump will arrive 9/19. Triton to coordinate replacement with Owner.
09/24/25 – Work being scheduled now including fire watch requirements.
10/29/25 – The fire pump has arrived. The test header was repaired by SA Comunale, now the wall and patching work needs to be completed. A new test ring needs to be installed on the outside FDC. Quality Fire has two people badged, checking on TJ Williams badged contractors. We need to iron out Fire Watch details with Triton.
12/12/25 – Triton and Quality ready to begin the project. Final fire watch details being negotiated. Inspection test header has been repaired, outdoor placard spacing is loose.
12/22/25 – Construction meeting held, we are working out details of shutdown, fire watch and submittal approvals.
01/12/26 – Const Mtg, finalizing shutdown details, fire watch, and schedule for work. Fire Watch must be provided by Triton for non-secure areas, DEG to issue drawings for scope. Electrical shutdown may require Courthouse to provide steam for Justice Center based on weather.
01/21/25 – Adding additional details and scope to the shutdown and next phase of work. USPA does not have background checks complete for fire watch yet. Electrical changes submitted to IBI. Feb 3 will be electrical emergency crossover and Feb 10 will be the primary crossover. Pump replacement scheduled for Feb 23.
02/25/26 – Emergency power is connected. Normal power has become a power struggle between Duke and IBI and DEG is working through those requirements and obstacles with both parties. the pump install will be coordinated after the power requirements are resolved.
03/25/26 – Normal & Emergency power are connected and ready to go. CFD required paperwork submitted & 3 of 4 FDC did not pass inspection. March 23rd replacement rescheduled until FDC are repaired. SA coming in on Friday to begin repairs and assessment.
04/29/26 – 3 of 4 of the FDC are repaired. The fourth FDC is currently under repair but SA is having trouble sourcing an access panel for the wall opening. TTC asked to open the wall now and repair the FDC which should only take a day, temporarily install a wall covering to keep the fire pump job moving along. The fire pump is currently scheduled to be replaced May 18-22.
05/18/26 – Replacement started on the fire pump today. Triton and DEG providing 24/7 fire watch.
05/19/26 – Repairs and fire watch continues.
05/20/26 – Repairs and fire watch continues. 99% of electrical and mechanical work is complete. Corporate equipment pre-inspected the fire pump installation and it passed. We are trying to move up final inspection to Thursday at 1:00PM.
05/21/26 – Replacement complete. Fire pump tested at 1:00PM with full water test, manual and automatic starts with City of Cincinnati and Cincinnati Fire Department in attendance. All system passed, the new fire pump was put online about 4:00PM and the fire watch was completed.
05/27/26 – DEG provided the punchlist for the project and will distribute later this week.
06/25/26 – Project in closeout.
07/30/26 – Working on latest change orders for this project. COR-1.
08/26/26 – Change Order #2 in the works? Working on other closeout documents.
09/23/26 – Change Order #2 COR #1 data all updated and sent in for approval to County.
10/26/26 – Final change order approved and signed the project is in closeout. TTC reached out to Triton to get all closeout documents by 10/31.