SPHQ – ALC Upgrade BAS Commissioning 2024

PM: John Nester, Terry Cannon

01/24/24 – Post created for tracking.
01/31/24 – Two punchlist sent to ALC for work on the current job. Training scheduled for Friday with Mike Bowman and Emcor.
02/02/24 – Training went well. Ian, Kendall, Curtis, Terry and Barrett attended. We made a few adjustments while reviewing.
03/22/24 – Project completed, just waiting on some summertime use before we close it out.
04/24/24 – Emcor onsite this week trying to get AHU-1, AHU-4 worked out for dual circuiting. AHU-1 VFD installed on 4/23. NKYHC replacing refrigerant and ambient.  Emcor wrapping up they Comm Center and starting the 250 WHT building next week.
05/29/24 – Controls work has been completed and VFD installed. We need to check back with Ian to see if its working better.
06/26/24 – DK currently working at 250, will check on progress.
07/24/24 – 250 WHT is almost complete. 486 next, then Comm Center. TTC checks the graphics and there is work to do before we say they are done.
08/28/24 – Working on final stages of 250 WHT.
09/24/24 – 250 WHT graphics are not complete, points are being programmed now. SPHQ appears that most upgrades are complete. Comm Center graphics are intact but no space temperatures are shown on floor plans, none of the mechanical equipment is shown on a site plan anywhere, found it in the Basement but there is no chiller shown on the plans. Public Works Garage has updated controls on the new work from the renovation has not been programmed and we have no feedback on space temperatures yet. The Records Center has no space temperatures on graphics.
10/30/24 – All buildings are complete except for Records Center according to Emcor. They are waiting on an outdoor enclosure for the outdoor RTU.
12/12/24 – TTC reviewed SPHQ and asked that Emcor put space temperatures on the floor plans with the thermal graphics maps like we did at SPHQ.
01/28/25 – Progress ongoing. All buildings are either done or partially complete. Price received for temps on floors and passed along to Tony for consideration.
02/26/25 – TTC reached out for an update from Mike and Steve yesterday.
02/27/25 – Emcor received final IP address for last building. Mike Bowman will be out to add the last building and then TTC to punchlist.
03/25/25 – ALC should be complete with all buildings. TTC will create a punchlist for each building in the next 30 days.
04/23/25 – TTC working on punchlist right now.
05/28/25 – Archived.