PM: Jesse Estes, Sam Hofmann
09/25/25 – Project kickoff held and scope determined. Review documents will be ready for County next week.
10/30/25 – Project in bid phase. Bids open 12/1.
12/11/25 – Triton is low bidder. Project in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – Bulletin #1 issued to include emergency L31 scope. Triton to provide schedule to begin work asap.
04/30/26 – Submittals approved. Triton to provide schedule.
05/28/26 – Triton mobilized 5/26. Epoxy demo ongoing.
06/25/26 – Half of South 3rd floor pods are complete. 5th floor Hall is next.
07/30/26 – First phase grinding and polishing is complete. Furniture will be installed next week.
08/28/26 – Furniture install ongoing. Backpunch scheduled for next wednesday.
09/24/26 – Phase 2 in progress.
10/29/26 – 2 pods complete in phase 2. Work ongoing.