JC – Cell Door and Frame Replacement (Phase 5)

PM: Matt Butz, Sam Hofmann

08/28/25 – Sheriffs provided scope of doors to be included in phase 5. Review set will be complete shortly.
09/25/25 – Review documents provided to county. Project will go out to bid on monday.
10/30/25 – Alpha is apparent low bidder. Bid vet occured 10/29. Alpha subbing out majority of the work to Cornerstone.
12/11/25 – Cornerstone is awarded the bid after contradictions in Alphas LOIs and Bid Vet statements came to light. Project in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract signed. Kick off to be scheduled in near future.
03/26/26 – Cornerstone has taken field measurements. Submittals incoming.
04/30/26 – No update.
05/28/26 – Submittal received and returned. Schedule needs to be determined by Sheriffs.
06/25/26 – No update. Tentative fall start.
07/30/26 – Delivery scheduled for end of August.
08/28/26 – Mobilization in 2 weeks.
09/24/26 – two phases complete. Work ongoing.
10/29/26 – Project ongoing.