PM: Matt Butz, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Field verification complete. Project in progress. ThermalTech has been onsite and updated mechanical drawings for the potential future pans. Sam to setup kickoff project for this job.
06/27/24 – Kickoff to be scheduled in near future. BW asked to add the North Bldg Lobby to be added as an Alternate to this job, lower ceilings etc.
07/25/24 – Meeting held to discuss scope. Field visit to North building will take place soon. Bid set will be ready for owner review by end of August.
08/29/24 – Owner review set submitted. Project will be issued for bid in the next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Triton is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project is in contract phase.
01/30/25 – Contract is still in process. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract finalized. Kickoff to be scheduled in near future.
03/27/25 – Kickoff held. Submittals in progress.
04/24/25 – Submittals still in progress.
05/29/25 – No update.
06/26/25 – No Update.
07/31/25 – Submittals returned. Triton to schedule mobilization.
08/28/25 – Pre-mobilization meeting to be scheduled. Duration schedule received.
09/25/25 – Background checks approved. Triton mobilized this week. Demo to begin next week.
10/30/25 – Demo complete in both buildings. Installation has started.
12/11/25 – Plumbing and drain pan rework saved cost and simplified the system. Ceiling grid and pads to begin in North Lobby next week.
01/25/26 – Diffuser RFI answered earlier this month, should be an easy install. DEG reminded the county that they were working on Geiler replacing bad p-traps at ceiling before new ceilings are going back in. Fire dampers accessible only through this ceiling should be getting done by NKYHC (see Tony).
01/28/26 – North Building insulation tested for asbestos and came back negative. Triton providing pricing for insulation and mastic removal.
02/26/26 – CO#1 approved to remove insulation and mastic. Work is ongoing. Scheduled to be complete March 5th. Fire damper work is complete. Plumbing repairs being finalized. Fire alarm worker can use Triton lift to facilitate progress.
03/26/26 – Ceiling installation ongoing. CO Trap work to begin next week. Project tentatively to be complete mid april.
04/30/26 – Electric sub never got plan review approval. Issue has been resolved and inspections can be scheduled. Once inspections are passed, padding out ceilings will be final step.
05/28/26 – Final inspection passed. OKI to be on site for pad installation this week. Punch to be scheduled week of 6/8.
06/25/26 – Punch complete and final work to be complete this week.
07/30/26 – Punch work complete. Closeouts ongoing.
08/28/26 – Back punch complete. Closeouts received.
10/29/26 – No Update.