PM: John Nester, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Field verification complete. work in progress.
06/27/24 – CDs in progress.
07/25/24 – No Update.
08/29/24 – Project will be issued for bid in next couple of weeks. Send to JN for review including the base bid and three alternates (bullet glass).
09/26/24 – Project is out to bid. Pre-bid scheduled for 9/30.
10/31/24 – No bids received. Project is back out today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future.
2/27/25 – Contracts finalized. Kick off to be scheduled.
03/27/25 – Kickoff held. Submittals to be submitted.
04/24/25 – Submittals in progress.
05/29/25 – Pricing for frosted glazing received. We need to decide if spandrel glazing is remaining in the project.
06/26/25 – Change order cost to remove spandrel glazing and add frosted glazing to project received. Jesse to confirm.
07/31/25 – Changes confirmed. Scope will potentially be added to make use of deduct funds.
08/28/25 – Provided confirmation of scope change and permission to start. An offical cange order will be settled at the end of the project after any additional scope is added.
09/25/25 – No update
10/30/25 – Work is complete. Scaffolding removal and final cleaning to take place next week.
12/11/25 – Scaffolding removed and punch items addressed. Closeouts in review.
01/28/26 – County to provide scope for additional change order work.
02/26/26 – Field visit to determine additional work attended by Sam and Rycca. Bulletin #1 to be posted shortly.
03/26/26 – Bulletin #1 sent to Alpha to include glazing replacements on floors 5-10 and window cleaning of first floor windows.
04/30/26 – Alpha provided pricing. Waiting on clarification on pricing.
05/28/26 – No update.
06/25/26 – Change order approved. Schedule to be sent after submittals are approved.
07/30/26 – No firm delivery date yet.
08/28/26 – Tentative delivery date of 9/14
10/29/26 – Glazing installed. Windows washed this weekend.