SPHQ – Academy Building Repurpose

PM: Sam Hofmann, Matt Butz
02/22/23 – SOSS received. Kick off to be held soon.
03/30/23 – Kickoff held on site with user. Matt to figure out budget and who pays for furniture. No movement until then.
04/27/23 – Design development on going. We will need one more meeting with users as we finish CDs
05/25/23 – Meeting held on site with users. Drawings in progress.
06/29/23 – Final review meeting held on 6/26. Discussed replacing clerestory windows. Window opening is not a glass block module so aluminum storefront and igu will be specified.
07/27/23 – Final review set submitted to county. Need to redo project manual with updated requirements.
08/31/23 – Project goes out to bid today.
09/28/23 – Bid opens today.
10/25/23 – Project was re-bid due to XBE paperwork not being filled out properly.
12/07/23 – Bids returned. Bid vet to be scheduled for this week.
02/29/24 – Projects kicked off. Submittals received and being returned.
03/28/24 – Construction to begin 4/1.
04/25/24 – Construction ongoing. Romex was found in the building not in conduit. We will get a cost to upgrade the electric to conduit on this job. We have removed the sink from the job and will take a credit for that work.
05/30/24 – Construction ongoing.
06/27/24 – Construction ongoing.
07/23/24 – Const Mtg onsite but little progress from last meeting.
08/29/24 – Progress being made. Tumlin removed wrong water fountain.
09/26/24 – Paint and casework mostly complete. Flooring getting installed next week. New wifi getting installed TTC to follow up.
10/31/24 – Punchlist issues, but additional work is needed. Deteriorated window sills needs to be fixed, EWC question sent today to TTE.
12/12/24 – Punchlist distributed. Sheriff are happy with new space. TTC replaced thermostats and put them on WIFI.
01/30/25 – Project complete. Closeouts to be submitted by Tumlin.
02/27/25 – Tumlin will be onsite for punch items. Closeouts outstanding.
03/27/25 – One punch item outstanding. Closeouts outstanding.
04/24/25 – Closeouts outstanding. Final pay app submitted by Tumlin will be held until closeouts are received.
05/29/25 – Parts missing. Tumlin to complete closeouts.
08/28/25 – No Updates.
09/25/25 – No Updates, we are still waiting on closeout documents.
10/30/25 – Closeout updates have been received from Tumlin. We will review to determine if they are acceptable.
02/26/26 – Closeouts given back to Tumlin to correct and return.
03/26/26 – Closeouts in Countys hands.