Hamilton County Facilities

SPHQ – Arc Flash Remediation 2024

PM = Matt, Barth

04/24/24 – TEI submits SOSS for approval.
05/29/24 – Project Pending SOSS approval.
06/26/24 – TEI receives signed SOSS and PO.  TEI has conversed with building manager re existing system and electrical needs.
07/24/24 – Project in progress.
08/28/24 – TEI to meet with building manager to discuss updated model and options.
09/25/24 – TEI meets on site with building manage and Matt Butz. A list of possible upgrades developed. TEI sends schematic dwg and costs to HCFD for review and direction.
10/30/24 – TEI issues project for bidding. Prebid meeting scheduled for 11/12/24 at 11:00 AM.
12/11/24 – Bids open at 11:00 AM on 12/12/24.
01/29/25 – No bids received. HCFD to advise if re-bid funds are available.
02/26/25 – No updates on rebid funding.
03/26/25 – No updates on rebid funding.
04/23/25 – No updates on rebid funding.
05/28/25 – No updates
06/25/25 – No updates
07/30/25 – No updates on rebid funding.
08/27/25 – No updates on rebid funding
09/24/25 – Project pushed to 2026 project.
01/28/26 – DEG to submit SOSS for re-package and rebid for 2026 project.
02/25/26 – DEG submits SOSS for approval.
03/25/26 – Project pending approval of SOSS
04/29/26 – DEG receives signed SOSS and PO. Reaching out to bldg mgr to confirm scope.
05/27/26 – DEG meets with Ian Zellner – confirms scope. Finalizing drawings and OPC for HCFD review.
06/23/26 – DEG to submit 100% review set to HCFD by end of June.
07/29/26 – Per HCFD – Project on HOLD until further notice.
08/26/26 – DEG to update labels and apply then close out the project.
09/23/26 – No updates
10/28/26 – All labels have been applied to the gear on site. Project complete.

Scroll to Top