02/08/22 – Signed SOSS Received.
03/29/22 – DD Kickoff meeting.
04/15/22 – Comments received from Scott and plans adjusted accordingly. 100% review meeting mid may.
05/17/22 – Review meeting with With Scott. Plans adjusted according to his comments.
05/26/22 – Project combined with Mediation. Review set due June 2 Arch and MEP.
06/30/22 – Project in bidding phase.
07/28/22 – bidder recommendation letter sent.
08/25/22 – Building Permit applied. Contracts in progress
09/29/22 – Contracts finalized. kick off meeting to be scheduled in the near future. Construction Project move to a combined construction project.