Project Managers: Mike Murphy, Bert Watts
05/26/22 – SOSS requested to move forward with design. BW provided updated scope for access to the Animal Shelter buildings.
06/30/22 – SOSS approved for Northside building to be converted to animal shelter. Preliminary schedule provided to County. Site visit to be scheduled.
08/25/22 – Site visit performed. Held user meetings to define scope. Work in progress.
09/25/22 – ThermalTech directed to submit their own SOSS’s for this project for regular and small scopes.
09/29/22 – Conceptual plan and estimate to be submitted 9/30
09/29/22 – TEI SOSS has been submitted to BW for approval.
09/30/22 – Conceptual plan and estimate submitted to County.
10/27/22 – ThermalTech electrical & mechanical cost estimates are done. We are working on drawings and plumbing estimates now.
12/15/22 – SD plans and estimates complete
01/26/23 – No Update
02/22/23 – No Update
03/30/23 – No Update
04/27/23 – No Update
05/25/23 – No Update