TPC – Access Control System Upgrades 2023

PM: John Nester, Mike Barth
12/06/23 – TEI submits SOSS.
01/30/24 – TEI receives signed SOSS and PO.   Project to Proceed.
02/28/24 – TEI and HCFD discuss project schedule based upon system needs (existing system failures and parts unavailability).  TEI commits to getting project upon MCB return from medical issues.
03/27/24 – Project in the works.  TEI Submits SOSS for Small Projects bid for installation costs
04/24/24 – Project documents in progress.  review set to be sent to HCFD upon completion.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations.  TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – Project issued for small bids project bidding. Prebid meeting conducted. Addendum #1 to be issued by 07/26/24.
08/28/24 – Bids received opened for project (2 bids, Glenwood and DK). DK apparent low bid. TEI vets bid on 08/28/24.
09/25/24 – Project in contract phase.
10/30/24 – HCFD, HCSO, HCRM, TEI and contractor meet for preconstruction meeting. Anticipated start date at completion of Jax cameras (Mid December)
12/11/24 – Construction to commence upon completion of the JAX camera Project.
01/29/25 – Project construction kick off occurred on 01/28/25. Construction to commence upon receipt of people to integrate into the system and access levels from Risk Mgmt.
02/26/25 – Construction ongoing on this project.
03/26/25 – Construction complete. HCFD and TEI perform punchlist.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – No updates.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – OK to Archive.