PM: Bert Watts, All Partners
05/25/22 – All estimates sent to Partners for SOSS
06/29/22 – ThermalTech has started updating estimates in the Archibus module. Several reestimates are complete. We are gathering information on the new projects but we need them set to estimating and we have to give them updates on scope and equipment for estimating before they start entering new ones in earnest. We have started requesting prices from vendors as well. We will send the County list for access. It would be helpful to have a coordination meeting on who is leading and who is working on the combined estimates.
05/31/22- THP Issues SOSS for review by the County.
06/10/22 – THP SOSS approved.
06/30/22 – THP developed internal spread sheet for projects. Initial draft complete. THP will publish for possible use by other partners.
07/27/22 – THERMALTECH UPDATE. Most electric cost estimates are complete and ready for Barth review. Limited mechanical estimates are complete at this time. Architectural and Structural coordinated has started for the “new” estimate. Once we get the proposed floor plans, we will update the MEP estimates.
08/24/22 – ThermalTech Update – We are working on these estimates every day to meeting Sept 1 deadline. Champlin has provided SD drawings for almost ever project for our use on the “New” estimates. We are coordinating on individual estimates on a case by case basis. Electrically, all resestimates are complete. Mechanically we have about 25 estimates remaining. We have completed several new estimates and will spend the bulk of our time next week completing the new estimates with the new drawings we’ve received.
09/04/22 – ThermalTech projects are complete for both reestimated and new estimates. TTC will review as time permits.
01/22/23 – Met with John and Ben and reviewed details that would make the Cost Estimating module better for the partners.
01/24/23 – Ready to Archive