Hamilton County Facilities

JC – Condenser Pumps Replacement

PMs: Matt Butz, Terry Cannon
01/17/25 – SOSS Requested.
02/26/25 – SOSS received, TEI starting preliminary engineering.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. Our first design meeting to be in April.
04/23/25 – Project design has begun, we should have preliminary review ready in a couple of weeks, and then we can meet and talk particulars for this project.
05/28/25 – First round of internal reviews complete. We are picking up TTC markups, creating a construction cost estimate, and filling out electrical coordination sheet. We will have the mechanical drawing issued for owner review on 5/30.
06/25/25 – No comments back from anyone that I know of, should we move to bidding?
07/28/25 – We sent drawings back for comment and requested AIA documents for bidding. Ready to bid but ITB not requested until budget is set.
08/28/25 – Budget set at $200,000. Comments and AIA contracts forthcoming from Facilities for this project.
09/24/25 – Prebid held last Friday, it was well attended. Addendum 1 due out this week.
10/29/25 – Pre Award meeting held with Geiler today and they can be recommended for this project.
12/12/25 – In contract approval stage.
01/25/26 – Sent before BOCC on Jan 19 for approval. We are awaiting notice to proceed. We have reviewed submittals already and are waiting on project kickoff to send them back to Geiler.
02/25/26 – Contract and PO are ready. DEG preparing for project kickoff. Pump submittals are approved.
03/25/26 – No kickoff meeting yet, submittals are approved, awaiting go ahead from County to move on this one.
04/29/26 – Kickoff meeting held early this month. Geiler commented that pumps were bid to be replaced when entire chilled water system was down. We are going to get everything in place and start this project in November 2026.
05/27/26 – DEG approved first pay application for $5500 and will send to County. Project on hold until November.
06/25/26 – Payapp received. Equipment in town, DEG to review at Geiler warehouse.
07/30/26 – Equipment approved, waiting on next Payapp from Geiler.
08/26/26 – Hold till November start.
09/23/26 – On hold until November, TTC approved and sent in Payapp 1, Payapp 2 already paid.
10/23/26 – Payapp 1 has cleared at Geiler.
10/26/26 – Pre-const meeting November 5. TTC removed the tentative tag on the meeting and update the invite.