Hamilton County Facilities

A&D – Plumbing Modifications

PM: Rycca Thacker, Terry Cannon
10/28/21 – TTC provided update on low flow plumbing issues at the A&D Building. In the past month, we had a major leak at the main sanitary leaving the building. Plumbers called Underground Detective to survey the pipe from the building to the street. TTC to get a test kit for testing in Fifth Floor East.
12/13/21 – TTC in contact with RC Frey & Associates to order the part for testing purposes.  A new SOSS was created for this part of th Study.  Once I get the part in town, i can coordinate with Danny on the installation needs of this part of the test.
01/25/22 – TTC needs to coordinate and pick this part up or have it ordered by County.
02/24/22 – TTC has to get this done this week. I will talk to Danny about getting this ordered.
03/31/22 – TTC stopped at Ferguson earlier this week and the part is special order, order into “inside sales” and as soon as they confirm, we will put on order through TTS.
04/28/22 – TP-4 is here and TTC picked it up and will drop it off today at the meeting. The next step is to coordinate with Danny and Steve on installation.
05/25/22 – Plumbing fixes relocated to the Furniture design job. I spoke to Danny about piping changes inside the chase when we open it open. I plan to discuss at Friday Champlin meeting on a Furniture project. I have also searched out what may be an even easier fix with a new Zurn product but I don’t have the specifics quite yet.
06/30/22 – Need to schedule 5E wall opening with County. Ask at the meeting.
07/27/22 – I was able to get into the chase with three existing chases on the 6th floor and found what I needed for plumbing design.
08/24/22 – Setting up a field trip with Danny, hopefully on Friday at 8:30 am to go over installation.
09/22/22 – Found the flush timers online and there is some discussion to try the flush timers first instead of installing the trap primers first.
09/29/22 – TTC to provide equipment selection to Danny to purchase and install.
10/26/22 – Working out final order details with GenieFlush from California. We should be able to order the equipment by Friday.
12/15/22 – Parts are in, TTC needs to meet with Danny to install and test.
01/24/23 – Two auto flushers were installed two weeks ago and set to two hours intervals. WE will monitor and keep track of clogging.
02/21/23 – One flusher is on 4E and one is on 5E. The fifth floor is working just fine, the fourth floor has a sticky flush rod, TTC to reach out to the vendor for a replacement part.
03/29/23 – We reached out to the vendor for a replacement part and he would like pictures of the bad module.
04/26/23 – No updates.
05/21/23 – No updates.
06/28/23 – Archive.