PM: Jesse Estes, Sam Hofmann
08/28/25 – Field visit to confirm scope.
09/25/25 – Review set submitted to county. Project will be going out to bid next week.
10/30/25 – Project in Bid phase. Bids open 12/1.
12/11/25 – Triton is low bidder. Project is in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No update.
04/30/26 – Submittals are coming in. County to schedule mobilization.
05/28/26 – Tentative start date of 7/6/2026.
06/25/26 – No Update.
07/30/26 – Tentative start has been pushed back to 9/8.
08/28/26 – No update
09/24/26 – Project has not started yet.
10/29/26 – 16 doors and frames have started. Project ongoing.