111 – Retention Pond Repair
PM: Rycca, Mike
08/27/26 – New project notice.
10/29/26 – Mike and Rycca working on this job.
111 – Retention Pond Repair Read More »
EMA/911 at 111 Tri-County Parkway
PM: Rycca, Mike
08/27/26 – New project notice.
10/29/26 – Mike and Rycca working on this job.
111 – Retention Pond Repair Read More »
PM Rycca Thacker, Mike Barth
06/23/26 – DEG receives PO and signed SOSS. Arc Flash Study initiated.
07/29/26 – DEG has nearly the entire single line from the KZF project modeled in SKM software. Next step is to field verify make/model numbers and serial numbers. DEG to schedule with the building manager.
08/26/26 – Study in progress.
09/23/26 – Study progress continues.
10/28/26 – Study complete. Labels to be printed and be scheduled with building manager to apply.
111 – Arc Flash Model and Labeling Read More »