Elevar – General Services 2025 (F021)

02/25/25 – PO approved.
08/28/25 – CH fifth floor interior sign code summary provided to HC on 08/27.
12/11/25 – No updates.
01/29/26 – Combine with General Services F015.
03/26/26 – 230 exterior lighting study and 111 Tri-Co smoker’s hut performed under Gen. Services.
04/30/26 – Submitted SOSSs for additional PM and CA time to support HCFD and a Prevailing Wage Coordinator.
05/28/26 – SOSSs not approved for PM and PW Coordinator. Juvenile Assessment Center walkthru occurred and Elevar/DEG to issue report.
06/25/26 – Elevar SOSS not approved yet for Juvenile Assessment. Complete the report under Gen Services?
07/30/26 – 230 Court Admins wanted this work to be completed faster than if combined into 230 Lobby Security project.
07/30/26 – Elevar Juvenile Assessment report complete and need DEG portion to fully integrate.
08/27/26 – 230 Exterior Lighting Project back to DEG for electrical design. Fixture options provided to Rycca.
08/27/26 – Does HCFD want Elevar’s Juvenile Assessment report without DEG’s report?
09/24/26 – Elevar assessment report provided to HCFD without DEG’s portion. Site visit was made to review potential relocation of operable partition but put on hold.
10/29/26 – No update.