Hillcrest – Fire Alarm System Fiber Connectivity
PM = Rycca Thacker, Mike Barth
10/28/2026 – HCFD Requests SOSS for project.
Hillcrest – Fire Alarm System Fiber Connectivity Read More »
PM = Rycca Thacker, Mike Barth
10/28/2026 – HCFD Requests SOSS for project.
Hillcrest – Fire Alarm System Fiber Connectivity Read More »
PM: Eryn Thamann, Bert Watts, John Nester
08/27/24 – Initial meeting held with HCFD, Juvenile Court, Elevar.
09/24/24 – SOSS submitted for strategic planning efforts. Juvenile Courts waiting on larger funding of Hillcrest projects/programs before approving.
09/26/24 – On hold.
10/30/24 – No update.
12/09/24 – No update.
01/29/25 – No update.
02/25/25 – No update.
03/26/25 – No update.
04/24/25 – No update.
05/28/25 – No update.
Hillcrest – Campus Long Term Strategic & Master Planning Read More »
PM: Megan, Mike Murphy, Terry Cannon
12/20/23 – THP – Champlin request SOSS for incidental structural support work.
12/21/23 – THP submitted SOSS to Champlin for review.
01/30/24 – Kickoff meeting with Facilities, Juv Court, Champlin and ThermalTech.
01/31/24 – Meeting notes distributed, TE started drawings packages for Phase 1.
02/28/24 – Scope for phase 1 finalized. Meeting scheduled for March 13, 10AM to review finishes and answer any remaining questions.
03/22/24 – ThermalTech Phase 1 drawings and cost estimates pretty close for final review. TTC working through individual items with Facilities. TTC requested meeting with Facilities to coordinate final scope of each building to nail down equipment repairs, replacement, upgrades. Verified that the four cottages are Elm, Evergreen, Hickory and now Maple is an Alternate.
03/22/24 – Champlin close to complete with review set as well. Final review meeting set for 4/3. Estimates to follow on 4/12.
04/24/25 – Final review drawings sent this month. Revised estimates were sent to Bert for review. Breakouts were formatted so they can see the assessment vs final design.
05/30/24 – County approved funding. Drawings modified accordingly. User requested a meeting to be scheduled in near future. BW said that the project can go out for bid as soon as we are ready to bid this project. TTC, MCB, and SH said the drawings and specifications are ready. BW and MM discussed the fence alternate around the building. Be ready to bid June 11-13 timeframe.
06/27/24 – Project is out to bid. Pre-bid scheduled for 7/9. Partners to invite local contractors for bidding on July 9.
07/25/24 – Project is still in bid phase. Final addendum to be posted by next Wednesday.
08/29/24 – Bids came in awardable. Accepting different alternates will determine lowest bid. County to decide what they are accepting.
09/26/24 – Project is in contract phase. County still finalizing alternates. Champlin to send recommendation letter for recommended bidder and note we have not finalized the accepted Alternates.
10/31/24 – Contract in process. Variance package for the fence is nearly complete.
12/12/24 – Contract awaiting on PO approval. Submittals incoming. HVAC and Plumbing submittal are done, TTC needs to approve and send along. BW said to go ahead and submit permit and fence variance for this job.
01/02/25 – ThermalTech starting on submittals this week for Phase 1.
01/30/25 – Kick-off held 1/29. Submittals are in progress. Zoning is complete. Permit has been submitted. Zoning application for fence to be submitted this week. Graybach ready to mobilize by mid February.
02/26/25 – We met with Aramark on Tuesday to review kitchen operational needs. TTE has been reviewing and working on HVAC, Plumbing and Electrical submittals on an ongoing basis. We are in good shape. Two AHU’s have delayed ship dates because the manufacturer is not producing R-454B refrigerant yet.
02/27/25 – Submittals in progress. Notice to proceed will be provided to allow Graybach to start on site work. Zoning application for fence to be submitted this week
03/27/25 – Submittals ongoing. Demolition ongoing. Permits approved and picked up. Fence application in HC lawyers hands.
04/24/25 – Bulletin #1 released. Already received a $25,000 add for the window changes. The rest of the pricing is outstanding.
05/21/25 – Met with Graybach, Champlin, Facilities on Change Order log, we do not have EC cost yet. Review deducts and approved a couple of them. Verbally approved Windows change order.
05/28/25 – ThermalTech regularly meeting contractors on site working on RFI and Change Orders for this project. The big items are the R-454B units for School and Dining, Water Closets on new tile walls, ductboard repairs and controls for the Admin building.
05/29/25 – Change order #2 for the windows is approved. Several potential change orders have pricing submitted. Rycca needs to finalize which will be approved or not. Change orders 3 and 4 approved. The remaining items have been priced and submitted to the board for a PO increase. Work may have to pause while this process takes place.
07/31/25 – Request for funding all change orders went before the board. No update on their decision yet. Work is in progress. Rycca reported that LaForce found a control key and it is getting cut and shipped to our site. The hope is to stay with the existing manufacturer. Rycca further said that they need final change order cost for all remaining COR so she can take final numbers to the BOCC. HVAC final cost, plumbing underground cost, electrical final change order needed. Sam is working on the frosted glass specs but must be ligature proof. TTC to confirm if County self performs repair if warranty is intact.
08/26/25 – Construction meetings continue. We agreed on the items to be included in Change Order 5 and now we are working on reconciling the cost associated with them. TTE sent two items for HC plumbers to fix, but while on site they had questions. TTC to meet them on site to review.
08/28/25 – County requested $800k for Phase 1 repairs. Plus CO#5 is approved and sent to Josh for approval.
09/24/25 – TTE sent a long list of field conditions to Graybach after last const meeting for them to address before the project gets to the punchlist phase. Graybach responded with action items and concerns over some of the comments. One item was that the County agreed to allow the return diffusers to remain as installed but they should be changed out before occupancy.
09/25/25 – Change order request goes in front of the board this week.
10/30/25 – Change order request was approved by the Board. Work continues in full force. No word on the fence yet.
12/11/25 – More change order requests came in. Scope removal to cover permit required work is being considered. Project competition is tentatively scheduled for end of February.
12/12/25 – DEG met onsite to review lighting change order and work out several nice compromises with the EE and GC. MCB to send Rycca and proposed update. Parks & Graybach to update and send in revised change orders for review.
01/23/26 – Const Mtg. DEG walked the site, check plumbing, heating, and electric. Chris Hofmeister called us back to the cottages to ask about external conduit adjacent to the receptacles. This turn out to be communication wiring not power wiring. Habegger will be out Tuesday to check temperatures in school, the two wings felt cold, but the core was warm. HVAC and plumbing are released to perform their punchlist.
01/28/26 – Campus is nearing completion. Bulletin to address change in fence scope to be issued in near future and variance submitted.
02/26/26 – Work ongoing. Waiting on approval for change in fence height to issue bulletin. Mechanical punch completed.
03/26/26 – Fence bulletin issued. Waiting on pricing to determine exact scope. Punch of school and admin building complete. Punch for remainder of buildings to be scheduled in near future.
04/30/26 – Punch work in progress. Fence application still in County hands.
05/28/26 – Variance application submitted. Hearing scheduled for 6/16. Owner punch walk through school. The rest of the buildings will be walked on 6/5.
06/25/26 – Variance approved. Survey to be scheduled in near future. Majority of punch work to be complete by mid July.
07/13/26 – TTC on site working on plumbing and HVAC items all week.
07/20/26 – TTC on site working on plumbing and HVAC trends all week.
07/22/26 – DEG on site doing back punchlist work.
07/23/26 – DEG on site doing back punchlist work.
07/24/26 – DEG on site doing back punchlist work.
07/30/26 – Final back punch complete. Minor items outstanding. Fence location needs final approval.
08/28/26 – Punch items have been progressing. Fence location not yet approved.
09/24/26 – 3 items remaining according to Graybach. Fence location has been approved, just waiting on confirmation of supposed easement.
10/29/26 – Back punch complete. Fence work ongoing.
Hillcrest – Campus Repairs Phase 1 Read More »