Hamilton County Facilities

RSC

RSC – Regional Safety Complex Phase 2

PM: Rycca, Murphy, Toombs
09/25/25 – Design schedule has been updated such that final CD documents to be completed and bid in November 2025. Design documents are about 60% complete at this time.
10/29/25 – 90% Drawings, specifications, and cost estimates sent to Owner this week.
12/12/25 – Phase 2 drawings are in for owner comments. Bert said that he would get those back later this week. We are shooting for bidding first of January.
01/25/26 – MEP drawings and specification sent to Champlin Issued for Bid. They are stamped and signed. The targeted bid date is 02/02/26, Champlin reviewing all final documents in the set now. DEG is trying to onboard an AV and IT specialist for this job. We have not received his PO yet, Bright Technologies.
1/28/26 – THP submitted Bid & Permit set 1/21/26. will go out 2/3. Construction is expected to start in April.
02/26/26 – Budget has been approved and sent to Robert Bell for approval. Waiting on Cincy approvals to go out to bid. We are shooting for mid March issuance.
03/26/26 – Project is out to bid. Pre-bid scheduled for 4/2.
04/30/26 – Bid opening pushed back to 5/21. Sniper tower scope was pulled out as an alternate.
05/28/26 – Graybach was apparent low bidder. Bid vet to be scheduled in near future.
07/30/26 – A305’s requested from bidders. Waiting on direction from County. Not sure we have received them yet.
08/28/26 – Graybach awarded the project.
09/22/26 – THP – CA on going, reviewing RFI’s/Submittals.
10/29/26 – Permits submitted and almost ready. Dave commented that general waiting on fire inspector. Driveway permit is expiring next month. Plumbing submittals received and returned. Mechanical submittals received and returned.

RSC – Regional Safety Complex Phase 2 Read More »

RSC – City Water Main Extension

PM: Rycca, Terry Cannon
04/24/24 – Kleingers sent preliminary survey to County and ThermalTech for approval. Two items were tagged for review from the survey, the creek crossing and box culvert.
04/25/24 – SOSS approval going in front of the Board on May 2. BW needs all the TE paperwork by Monday for this work.
05/17/24 – Bert checked on status of submission to GCWW for water permit. TEI working on fire calculations for the load. We have the city water demand at 90 GPM.
05/28/24 – Colerain Township asked for the cost to extend the water line past the property. TEI and Kleingers will have to discuss additional cost.
05/29/24 – TEI to have preliminary application ready to discuss at Stated meeting this Thursday and completed by Friday.
06/26/24 – Preliminary application submitted this month. HC asked us to submit a SFHA permit too, which Kleingers is taking care of.
07/24/24 – Kleingers submitted both applications. TTE will check on progress with Doug.
08/28/24 – Update meeting scheduled for next week with County and City.
09/24/24 – Kleingers is currently working updating the drawings and its going well. It’s pretty straight forward except for the creek crossing, that might be tricky.
10/30/24 – Kleingers, ThermalTech and GCWW met onsite two weeks ago. TTE and Kleingers group sent out updates from meeting. The plan is agreed upon, Kleingers continue to design the routing and scope for new water line. GCWW says they will probably run a 12″ main in the street for current and future growth.
12/12/24 – Kleingers spoke with Bert this week and received the okay to proceed with the final construction drawings creating for the new water line.
01/28/25 – Kleingers sent an update to Bert. TTE sent review comments to Kleingers. Doug inquired if there was any progress on easement around bridge for new line.
02/26/25 – We had a progress meeting with GCWW, HamCo, Kleingers, adn ThermalTech and reviewed progress. TKG will follow up on easements and permitting. ThermalTech send load calcs to GCWW for use in their model.
02/27/25 – BW already made call on easements but believes the Engineer Office probably wants a Right of Way enlarge so the utilities can get back to maintain utility in the future. The routing of the line from the tap to down the road may change to meet GCWW needs for taps. TTC to check back with Doug on additional updates.
03/25/25 – Kleingers submitted an updated set of review drawings this week for review.
04/23/25 – Project in for review. Some emails are going around for coordination right now.
05/28/25 – Biweekly design meetings are now being held on Friday afternoons. ThermalTech hosting the meetings on Teams. Current work includes final approvals form GCWW, communication with Colerain Fire Dept about hydrant locations and finalizing HC Engineers Office comments. The Right of Way for the work around the bridge is in HC hands. Kleingers review drawings are up to date and distributed.
06/25/25 – Kleingers sent review drawings to the team yesterday. TTC to review and work on branch application. GCWW said the first shipment of piping will be delivered Friday.
07/11/25 – Design meeting to review County engineer comments
07/18/25 – Design meeting to review comments with GCWW. Kleingers to update and send new drawings for GCWW review to everyone.
07/30/25 – Next meeting is August 1 to comment on revised drawing sets and proposed budget. Bert sent easement requirements to Kleingers for their help with.
08/01/25 – Design Mtg #8 was held. The schedule was coordinated with the latest timeline. Kleingers will pick up latest markups and update the BOM on the dwgs for CWW. We are sending final review set to every for review the week of August 18. The easement work is underway.
08/04/25 – Kleingers sent latest drawings and materials list for final approvals.
08/22/25 – Final review project manual and drawings submitted to Bert Watts for approval. Budget and cost estimate finalized and coordinated with Bert. Comments sent to Kleingers by TTC for updates into final bid package. KEG working on easement with HCEO. Mylars sent to City for approval. New budget around $1.14M and we will publish at one million.
09/24/25 – Final review with City, GCWW and HamCo held on 9/12. We must wait until city/county agreement is signed and funds approved for bidding then TEI can publish the project.
10/29/25 – Kleingers has paid the OEPA bill and sent the City receipt. The project is nearly ready to bid but we await the City/County agreement to move forward with bidding. All the documents are ready to go minus final review and assembly.
12/12/25 – City/County agreement went to Board for Approval on 12/11, assuming that is approved bidding for RSC City Water Line will be in January.
01/21/26 – Received comments back from Bert Watts indicating that the City and County would have final comments back to DEG by Feb 6. Issuance pushed back to Feb 11 and bid date extended.
02/18/26 – Project Issued for Bid to County Purchasing.
02/25/26 – Prebid scheduled for March 4 on site. Bid opening schedule for April 1.
03/25/26 – The project is out for bid. Addendum 1 & Addendum 2 have been issued. Bids open April 1.
04/22/26 – Bids extended to April 22. Bids were opened and read. Four awardable bids.
04/24/26 – The low bidder has pulled his bid because they did not include the full paving requirements.
04/27/26 – The pre-award meeting is scheduled with the next low bidder QCM on Friday at 1:00 PM.
05/27/26 – QCM was recommended for the job. Their contract is in for review with the prosecutor office.
06/25/26 – Contract sent to QCM and signed. DEG met with QCM on SOV and schedule on 6/24. QCM to send SOV in for review and they are okay with schedule extension and August 1 start. They would like to have a pre-const ASAP.
07/30/26 – Early Pre Const and Pre Const meeting held, notes distributed. Next meeting August 4. QCM acquired ROW permit, survey complete, and had begun marking and cutting pavement.
08/26/26 – Const Mtg #1 & #2 held on site. QCM making progress to about 1200 LF of piping installed. FH 13 installed. 50 sticks of piping missing but we’ve tracked it down to a missing shipment. US Pipe working to provide missing lot to the project site for use. Payapp #1 received and approved.
09/23/26 – Payapp #2 approved and submitted. Next Const Mtg is next Tuesday at 8AM not 9AM. QCM working on CO cost for hydrant and culvert, we will have something by the end of the week. Things are going well.
10/19/26 – Project team met on site to review landslide condition at Station 4 where the water line goes down hill to creek. It was decided to bring Terracon out to review existing road conditions.
10/22/26 – Project team met Terracon on site to review existing conditions. Facilities, GCWW, Terracon, QCM, DEG and Kleingers discussed alternate routes and proposed solutions. GCWW is leaning toward keeping the line where design and shoring up the hillside and sharing that cost with HCEO. Facilities and HCEO has afternoon meeting to discuss next steps. Afternoon meeting reviewed original design and field conditions with HCEO, Facilities and DEG. Kleingers not at afternoon meeting. It was decided to do more investigation, look for previous soil boring and to reconvene with another HCEO and Facility meeting on 10/30/26 for updates.
10/26/26 – HCEO working on reviewing existing field conditions at and around original water line path so we can keep water line in original spot. Terracon submitted boring report to Facilities from 1970’s for this area. This report was shared with the project team. Follow up meeting on Friday.

RSC – City Water Main Extension Read More »

Scroll to Top