Hamilton County Facilities

RSC – Regional Safety Complex Phase 2

PM: Rycca, Murphy, Toombs
09/25/25 – Design schedule has been updated such that final CD documents to be completed and bid in November 2025. Design documents are about 60% complete at this time.
10/29/25 – 90% Drawings, specifications, and cost estimates sent to Owner this week.
12/12/25 – Phase 2 drawings are in for owner comments. Bert said that he would get those back later this week. We are shooting for bidding first of January.
01/25/26 – MEP drawings and specification sent to Champlin Issued for Bid. They are stamped and signed. The targeted bid date is 02/02/26, Champlin reviewing all final documents in the set now. DEG is trying to onboard an AV and IT specialist for this job. We have not received his PO yet, Bright Technologies.
1/28/26 – THP submitted Bid & Permit set 1/21/26. will go out 2/3. Construction is expected to start in April.
02/26/26 – Budget has been approved and sent to Robert Bell for approval. Waiting on Cincy approvals to go out to bid. We are shooting for mid March issuance.
03/26/26 – Project is out to bid. Pre-bid scheduled for 4/2.
04/30/26 – Bid opening pushed back to 5/21. Sniper tower scope was pulled out as an alternate.
05/28/26 – Graybach was apparent low bidder. Bid vet to be scheduled in near future.
07/30/26 – A305’s requested from bidders. Waiting on direction from County. Not sure we have received them yet.
08/28/26 – Graybach awarded the project.
09/22/26 – THP – CA on going, reviewing RFI’s/Submittals.
10/29/26 – Permits submitted and almost ready. Dave commented that general waiting on fire inspector. Driveway permit is expiring next month. Plumbing submittals received and returned. Mechanical submittals received and returned.

Scroll to Top