Hamilton County Facilities

TPC

Todd Portune Center

TPC 9th Floor JFS and CoC Renovation

County: PM Rycca Thacker – Champlin PM: Sam Hofmann

02/26/26 – SOSS received for JFS portion of work. Design team verified existing conditions. SD plans and estimate in progress.
03/26/26 – SD plans and estimate in progress.
04/30/26 – SD plans and Estimate to be submitted to County next week.
05/28/26 – SD plan and estimate submitted to county for JFS work. CoC work is put on hold until further notice.
06/25/26 – No Update.
07/30/26 – No Update.
08/28/26 – CoC approved. SD plan and estimate to be uploaded to Archibus.
09/24/26 – Re-kick off to be scheduled.
10/29/26 – No Update.

TPC 9th Floor JFS and CoC Renovation Read More »

TPC – Mechanical Room Door Replacement

PM: Jesse Estes, Sam Hofmann

08/28/25 – Field visit to confirm scope.
09/25/25 – Review set submitted to county. Project will be going out to bid next week.
10/30/25 – Project in Bid phase. Bids open 12/1.
12/11/25 – Triton is low bidder. Project is in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No update.
04/30/26 – Submittals are coming in. County to schedule mobilization.
05/28/26 – Tentative start date of 7/6/2026.
06/25/26 – No Update.
07/30/26 – Tentative start has been pushed back to 9/8.
08/28/26 – No update
09/24/26 – Project has not started yet.
10/29/26 – 16 doors and frames have started. Project ongoing.

TPC – Mechanical Room Door Replacement Read More »

TPC – BOCC Security Upgrades

PM: Matt Butz, Eryn Thamann, Mike Barth
06/26/25 – Fee estimates from Elevar/DEG were provided based on the Sheriff’s risk assessment document. ROM construction estimates were also provided.
07/31/25 – No update. The County commented that all has been submitted, waiting on comments.
08/28/25 – No update.
09/25/25 – No update.
12/11/25 – No update.
01/29/26 – No update.
02/26/26 – No update.
03/26/26 – No update.
04/30/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – No update.
10/29/26 – Submitted SOSS for egress study.

TPC – BOCC Security Upgrades Read More »

TPC – 3rd Floor Auditor Breakroom

PM: Megan, Sam Hofmann, Terry Cannon
05/29/25 – Added as new project.
06/25/25 – Checking dates for meeting.
07/24/25 – Design meeting conducted on site.
08/26/25 – Design continues, updated floor plans received from Champlin today.
09/24/25 – Prices and owner review documents submitted to Champlin. County to review budget and scope to determine if they have enough money to bid as is.
10/30/25 – Scope and Budget confirmed. Project will be issued for bid today.
12/11/25 – Triton is low bidder. Project is in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No Update.
04/30/26 – Submittals are in process. County to schedule mobilization.
05/28/26 – Triton mobilized on 5/6. Construction and Bi-weekly meetings ongoing.
06/25/26 – Demo complete. Framing complete. Roughin inspections ongoing.
07/30/26 – Construction ongoing.
08/28/26 – Project nearing completion. Punch scheduled for next week.
09/24/26 – Punch walkthrough completed. Closeouts in progress.
10/29/26 – Backpunch complete. Closeouts received and being reviewed

TPC – 3rd Floor Auditor Breakroom Read More »

TPC – NFPA Fire Door Upgrades

PM: Sam Hofmann, Jesse Estes

02/27/25 – SOSS returned. Kick off to be scheduled in near future.
03/27/25 – Drawings have been started. Kick off to be scheduled.
04/24/25 – Drawings in progress. To coordinate with Elevar on format.
05/29/25 – No update.
06/26/25 – Field visit to walk through all buildings to be scheduled.
07/31/25 – Field visit complete. Drawings to be finalized.
08/28/25 – Final review meeting to be scheduled.
09/25/25 – Door Hardware Consultant to visit doors on site to provide feedback and cost.
10/30/25 – Assa Abloy is working on specs and estimate.
12/11/25 – Assa abloy is finalizing scope.
01/28/26 – Finalizing cost estimate and base bid scope
02/26/26 – Completing bid set and project manual.
03/26/26 – No Update.
04/30/26 – No Update.
08/28/26 – County is cleaning paint off labels and will report back which locations will still need to be replaced.
09/24/26 – Confirmation required on labels able to be cleaned.

TPC – NFPA Fire Door Upgrades Read More »

TPC – Atrium Glass Replacement

PM: John Nester, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Field verification complete. work in progress.
06/27/24 – CDs in progress.
07/25/24 – No Update.
08/29/24 – Project will be issued for bid in next couple of weeks. Send to JN for review including the base bid and three alternates (bullet glass).
09/26/24 – Project is out to bid. Pre-bid scheduled for 9/30.
10/31/24 – No bids received. Project is back out today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future.
2/27/25 – Contracts finalized. Kick off to be scheduled.
03/27/25 – Kickoff held. Submittals to be submitted.
04/24/25 – Submittals in progress.
05/29/25 – Pricing for frosted glazing received. We need to decide if spandrel glazing is remaining in the project.
06/26/25 – Change order cost to remove spandrel glazing and add frosted glazing to project received. Jesse to confirm.
07/31/25 – Changes confirmed. Scope will potentially be added to make use of deduct funds.
08/28/25 – Provided confirmation of scope change and permission to start. An offical cange order will be settled at the end of the project after any additional scope is added.
09/25/25 – No update
10/30/25 – Work is complete. Scaffolding removal and final cleaning to take place next week.
12/11/25 – Scaffolding removed and punch items addressed. Closeouts in review.
01/28/26 – County to provide scope for additional change order work.
02/26/26 – Field visit to determine additional work attended by Sam and Rycca. Bulletin #1 to be posted shortly.
03/26/26 – Bulletin #1 sent to Alpha to include glazing replacements on floors 5-10 and window cleaning of first floor windows.
04/30/26 – Alpha provided pricing. Waiting on clarification on pricing.
05/28/26 – No update.
06/25/26 – Change order approved. Schedule to be sent after submittals are approved.
07/30/26 – No firm delivery date yet.
08/28/26 – Tentative delivery date of 9/14
10/29/26 – Glazing installed. Windows washed this weekend.

TPC – Atrium Glass Replacement Read More »