2020 AUBURN – BUILDING ASSESSMENT

05/03/07 – Hard copy report is finished and being delivered to Mark Donnelly.

04/26/07 – TTC told Mark that he would incorporate Don Benbow’s mark up and update the website and give him 6 new hard copies.

04/18/07 – The only comments that we have received are from Don Benbow. We will update the report for the items we are willing to concede and update and send down final copies to Mark Donnelly if he is okay with this approach.

04/13/07 – Issues in disagreement are being worked out.

04/04/07 – Matre forwarded some comments from Don Benbow. TE may incorporate his suggestions into the report. We however disagree with some of them.

03/30/07 – Email copy has been delivered to Mark Donnelly for markup. TEI will provide 6 hard copies upon receipt of HamCo comments.

03/23/07 – Awaiting notification to provide hard copy of report.

03/20/07 – TTC to input report on Wednesday. Report has been input to Archibus. Review set to be hand delivered on Thursday.

03/14/07 – NR created project journal and filled in back data from previous meetings. Report completed, information to be inputted into Archibus on 03/12/07. Hard copy will be delivered during the week of 03/12/07.

2020 AUBURN – BUILDING ASSESSMENT Read More »

2020 Boiler Replacement

01/24/11 – All punchlist and closeout documents have been sent to Bert for this project. Receptacle was moved by Ginter on water softener.

10/1/10 – All work is complete. Seco has not turned in final closeout paperwork yet.

09/22/10 – Peck has scheduled change order work to start at the end of September. ThermalTech has provided answers to the PHB questions on the Change Order work.

08/13/10 – Peck submittals are approved on water heater and all other change order work. Seco change order was sent out for signing. Seco payapps sent to Bert for payment. Siemens payapps sent to Bert for payment.

07/23/10 – Peck change orders are approved. Folck is working on Seco closeout documents and change order forms. Peck is to schedule change order work starting next week. Bert is trying to get PO for water softener.

06/02/10 – Siemens has provided pricing for OM-1 Actuator Option to convert 2-position valves to modulating. Isolation valves will need to be modulating to avoid damaging system shock.

05/28/10 – Boiler installation has been approved by IBI. There are a few minor issues which Seco will complete next week. PH+B has provided pricing to install blank off orifice plates to convert (3) 3″ flanged 3 way bypass valves to 2-way valves for AHU-1,2,3. Blank off plates are 1/16″ thick with a 1/4″ hole in the center for relief and will be installed between the existing valve gaskets and flanges. CB BLR-3 and BLR-4 have been successfully fired and will continue commissioning by Siemens next week.

05/26/10 – Boiler installation has been approved by the State/City and is ready for startup with CB Thursday and Friday (5/27-5/28).

05/24/10 – We had a construction meeting today for the project. All mechanical and electrical work has been completed. Siemens will be on-site all week to install control wiring and begin controls startup / commissioning. Boiler inspections are scheduled for Wednesday (5/26 – State/City) and Thursday (5/27 – Electrical). Boiler startup with CB is scheduled for Thursday and Friday (5/27-5/28).

05/21/10 – HWS/HWR and NG piping have been completed. Condensate drain line and relief valves will be installed Monday (5/24). Combustion air intake has been modified to eliminate 45 degree elbow around conduit rack. All electrical work has been completed including VFD’s, pump, and boiler feeds. Current transformer has been fixed temporarily until new transformer is installed on Monday (5/24). Control panel has been installed and conduit for control wiring was run to boilers and pumps. CC will be on-site all next week (5/24-5/28) to install control wiring, thermal wells, and begin programming with Chris Neff.

05/18/10 – Combustion air and exhaust have been installed for Boiler #3 & #4. (1) 45 degree elbow was used on intake air to avoid conduit rack. TTE recommends (2) 90 degree elbows vs (1) 45 degree elbow for a more appealing installation. To avoid compromising the security bars and make installation more simple, combustion air intake was not installed thru existing louvers. Boiler piping has been started and will be completed by Monday (5/24). Balancing valves or triple duty valves will not be used for this installation. Copper was considered for condensate drain lines to avoid damage by foot traffic, but is not an option due to possible erosion from acidic condensate. If problems occur in the future, condensate drain lines could be changed to sch 80 pvc or stainless steel. Electrician has moved (2) of (4) VFD’s near pumps and will complete installation Wednesday (5/19). Siemens will be on-site Thursday (5/20) for controls.

05/14/10 – Project schedule was updated and meeting notes were sent out from construction meeting on Monday (5/10). All demo has been completed for boiler #2. New Boiler #3 & #4 are currently in the assembly process and will be completed on Monday (5/17). Included boiler legs have been shortened 5″ to accommodate overhead clearance requirements. Boiler #3 & #4 have been positioned on existing concrete pad as shown on TTE drawings. Included boiler exhaust was installed opposite of drawings by factory and will be changed to match TTE drawings. Boiler piping will now be routed between boilers as approved by TTE. HWS valve has been relocated near existing HWS tie-in. TTE considering the addition of balancing valves or triple duty valves for Boiler #3 & #4. Boiler combustion air, exhaust, and piping will be installed next week (5/17-5/21). Electricians will be moving VFD’s near pumps on Tuesday (5/18) to satisfy line of site concerns. Replacement transformer is scheduled to arrive Wednesday (5/19).

05/10/10 – We had a construction meeting today for the project. Peck will begin demolition on Tuesday. Controls and Electricians will be reported next week to start their next phase of work. TTE will work on schedule and meeting notes this week.

05/07/10 – We setup a const mtg for next week on Monday to kick off the demolition on this job and to coordinate the construction issues. The permit has been approved by IBI and City. The real work begins.

04/29/10 – We continue to work on schedule with Peck. PHB came on Wednesday to begin coredrilling for the new vents. The city has the permit held up on 3 issues that TEI sent responses down for reconciliation. The electricians and Siemens are working on a disconnect issue with the VFD’s. Boiler is scheduled to be demolished on May 10 which has been approved by Don Benbow.

03/24/10 – Siemens payapp has been received but the schedule of values is not acceptable. TTC will contact Siemens. Peck payapp has been approved.

03/23/10 – All submittals have been received. All submittals have been returned. We clarified an issue with the boiler vent piping. It can be single wall with personnel protection on this job. A controls meeting is scheduled next week to work on sequences with 2020 and the Siemens. Gary Davies will attend for TEI.

02/22/10 – No word on Siemens. TEI created permit drawings sets for the contractors, as soon as they are stamped and signed, we will give to contractors. Small modifications to venting per the 02/12 visit.

02/12/10 – Met with Peck on site and reviewed project with Foreman. Contact all contractors for submittals. Neff said he could call Siemens for me to find out where their subs are.

01/19/10 – The preconstruction meeting was held on site. TEI has approved the boiler submittals but wants better paperwork. Siemens did not attend the precosnt meeting. PHB and Seco were in attendance and are working on submittals as TEI works on permit drawings for the project.

12/31/09 – Contracts are signed but the BOCC have to approve them before we start. Siemens state term contract is ready. Peck asked for and received an extension on the project completion date. Ballinger informed us through Peck that boiler prices will increase in 2010 if we don’t order in 2009. That is a problem since the contract won’t be approved because of winter hours for the BOCC.

10/19/09 – Bid came in for the project. Peck appears to be the lowest bidder. I confirmed the prices with Bernie. His labor looks low but they are willing to do the project for the price. I know have to look at the LCC for the boilers and see which is best and look at lead times on the equipment.

09/18/09 – Final bid documents were sent to Purchasing and Queen City. The Bid Opening is October 19th. The Prebid is Oct 1. Chris Neff called and wants to go over some drawing details. The controls contract will be given to Siemens under a state term contract. TEi turned over the pdf’s to Siemens but we have not heard any comments from the CC yet. Gary is in the office this week so we need to organize the final details.

08/25/09 – Control schemes are finished. SOSS is approved. TEI is working on design. We need to go back and do more fieldwork for verification and start the design on paper. We are bidding 3 alternates for boilers: Clearfire, Fulton, Sync.

07/28/09 – TTC & TZ visited the site and did the preliminary field work. TTC created and sent Tony an SOSS for the project. TTC will hand deliver the SOSS to Bert at the County Partnering Meeting.

2020 Boiler Replacement Read More »

2020 – Boiler Replacement Phase 2

08/13/10 – We are waiting on an approved SOSS to proceed.

09/24/10 – Project was bid out as scheduled. Bid opening scheduled for Oct 14.

10/25/10 – Contract for Peck has been sent to Tony for approval. Tony said he was going to pay for Boiler #1 repair this year and install the new boilers in Spring 2011.

01/24/11 – Contracts are in approval stages. Waiting for pre const mtg. Labor will start after heating season, March 2011.

02/22/10 – Pre Const Mtg Complete. Mtg notes being sent to contractors. PHB has submitted boiler paperwork for approval. The original rain caps have been removed on the boiler stacks to prevent ice puddling below the stacks. PHB is looking at installing thimble caps on all new vents. New venting and project schedule must be approved.

03/30/11 – Peck is working on boiler order and delivery. Boiler submittals and electrical submittals have been returned to Peck. We are currently trying to work out a change order on the control valves, actuators and flow meter. The project will begin in May-June 2011. We should be finished by the time summer is over.

05/12/11 – Peck is working on new background checks. All change orders have been sent through. Boilers are ordered.

06/07/11 – Boilers are at PHB and the flues should be there in a few weeks. PHB still needs to get background checks back from the State before they proceed.

06/20/11 – PHB is ready to start some sheet metal demo in the boiler room next week, also finalizing the project schedule for this job.

Item #2 – There are a couple of issues with the control equipment that we need to discuss. The acuator and valve by Keystone apparently is out of stock. They have offered a replacement that we can get, it is slightly bigger than the one we specified. The problem is TTC can’t find this model on their website. Asked Chris who they contacted locally for prices and model #’s.

Item #3 – TTC asked if Siemens or someone else preferred make the paddles wheel flow meter needed. Bernie was looking for a local manufacturer that sells the Badger flow meter, but was not aware of any yet. Did Siemens offer the one we get easily?

07/07/11 – Peck is on site performing demo. Chris has been sharing controls and wiring with the Peck for purchase through Seco.

07/21/11 – Pipefitters are complete with their work. Sheet metal guys are waiting for a fitting for the flues, and will continue as soon as they get the rest of their materials. SECO Electric will be on site Monday 7/25. Start up is scheduled for August 12th, that will give enough time to get everything complete and the boilers inspected. ThermalTech has to provide a punchlist and discuss controls with Chris Neff.

08/05/11 – TTC sent out an email punchlist to Peck from a site visit last week. Bernie said they can get this done.

08/08/11 – Peck submitted payapp #1 but the change order paperwork is not signed yet. TEI asked them to modify their payapp so they can bill more quickly on this project.

08/25/11 – All work is complete except for metal pans on louvers. Boiler alarms not part of new boilers, Bill is working on a separate change order for that. Ready to closeout. Chris is writing sequences now.

09/28/11 – Pay App #1 was resubmitted by PH&B. Approved by TTC 3 copies were sent to Tony Matre on this date.

09/30/11 – We resolved Payapp #1 issues and asked PHB for closeout documents. Tony paid the $102,600 invoice already so we voided the later invoice and asked for a #2 for closeout. The change order was signed on May 13.

10/24/11 – Payapp 2 (labeled 3) arrive and was paid. Payapp 3 (retainer arrived and was held for closeout docs). TTC advised PHB the closeout documents are due before final payment can be made.

12/23/11 – This project will be archived for 2012.

02/22/12 – Chris reports all boilers are working great but there is still some programming left for him to change or update. This project is ready to be archived. All closeout and pay applications have been sent to Tony.

2020 – Boiler Replacement Phase 2 Read More »

Elevator Maintenance Bid

01/10/06 – TTC completed the escalator contract per Kerry’s comments and merged with previous comments. TA will hand delivery 4 copies to PBS today at 1:30 p.m.

01/09/06 – TTC delivered PBS elevator to PBS and bid tabs for their use.

01/06/06 – TTC delivered 230/800 contracts to Tony at the 237 WHT pre const mtg.

01/04/06 – Kerry returned electronic copy marked up. TTC to check over and approve.

12/21/05 – TTC returned electronic copy to Kerry for revisions.

12/12/05 – Contract revisions arrived from Kerry Dowling. TTC to make changes and send out ASAP.

12/09/05 – Kone called today to inquire about new contracts and cancelling old contracts for buildings they did not win under the new bid. Terry told them that new contracts should be forthcoming for official use by end of next week.

11/21/05 – TTC answered questions from the County about contracts. Everything appears to be in order.

11/17/05 – All contracts have been given to County for approval. TTC noted that there is no real need to have a supplementary conditions with the project manual as that is all outlined in the maintenance contract and we don’t use AIA contracts with this type of bid.

11/16/05 – TTC finished the elevator contracts for 230, 800 & PBS and sent them to Joe and Tony for distribution. This time, we coordinated issues like termination clauses, contract amounts with the combined bid savings and decided to split the savings 50/50 between the PBS and Facilities.

11/03/05 – After an initial scare that Addendum 01 did not get posted, Gina realized that the bid doesn’t open until 11/08 and therefore Addendum 01 is posted to demandstar and already has been sent from Ohio Blue.

11/01/05 – TTC is writing the Add01 for escalator project. This job should open next Tuesday. The SOSS has been signed for the escalator change order part of the job.

10/25/05 – Abell/Irvine called today to say that their office has been on Colerain Avenue since 1986. They have got their questionnaire answered and turned in with their bid. TTC ask Purchasing to fax a copy of it over to ThermalTech for review. TTC told everyone that the bid spec stated up to 5 buildings with 5 years experience. Tony called and discussed with TTC the new elevator contracts.

10/24/05 – Bids were opened. Fujitec did not bid the job. Kone didn’t their bid bond, Schindler withdrew their bid after TK’s opening bid, ThyssenKrupp and Abel/Lincoln turned in appropriate bids. TTC contacted both vendors for qualifications. TK provided a fax with all the documentation today. I have not heard from A-L but their number turned out to be long distance so I don’t consider that a good thing.

10/18/05 – The escalator bids immediately went back out on the street because no bid against Kone. Joe and Terry set the new bid estimate based on past numbers for the work in an attempt to make sure Kone didn’t try to overbid as they may be the only one entering bids on this project.

10/14/05 – The final addendum was issued to the contractors that dealt with questions from the prebid and mostly insurance and indemnity. TTC incorporated answers from the HamCo prosecutors office and risk managers for those issues. Also there is concern that one of the vendors does not have a full time office in the City as required by the bid. They also have not met the 5 project requirement of the specifications. This will have to be followed up on in the interview process.

10/03/05 – This Wednesday is the prebid meeting. I will meet Tony and Mike at 230 at 10:30 a.m.

09/21/05 – Project Manual completed and sent out for public bid. Bid opening scheduled for Oct 19th. Prebid mtgs scheduled on Oct 5th per everyone’s attendance request. Project budget estimated at $650,000.

09/20/05 – TTC completed the bid manual and sent out for review. All comments came back, TTC incorporated them into the manual and sent back to Maureen for advertising dates and SBA %. TE will turn over to County on Wednesday for bidding.

08/31/05 – Tony emailed today to say that TE is to keep the original insurance requirements from the original bid.

08/30/05 – Finalizing the bid process. Insurance requirements for Kone are final question before setting up public bid forum. Waiting on word back from Todd Dalton at Kone and AKM.

07/18/05 – Meeting went great. TTC has some work to cleanup old bid. AKM to inform TTC about 2020 building. Kone had some verbiage changes to contract. TTC has to modify bid form for combination bids.

07/12/05 – TTC setup a meeting with Tony and the elevator vendor for Friday.

07/05/05 – Project manual built by Sam. TTC has to get new information from Kone on new testing requirements. TTC talked to Sam Kinman today at PBS while on a walkthrough at PBS and was told that October’s escalator work is going to be an additional $30k on top of the standard contract. TTC will talk to Kone about new scope and testing for this bid and project manual.

Elevator Maintenance Bid Read More »

ADAS – Due Diligence MEP Study

11/03/05 – TTC contacted THP for coordination and kickoff on this project. We will wait till they contact us to start working directly with Wes Miller at the site. According to Mike Stiles, the building could certainly use an electrical upgrade that could be upwards of $1mil in cost.

10/25/05 – TTC and Wes Miller setup a walk through today for Sam and Mike to gather info for the SOSS for this project.

10/24/05 – TTC contacted Wes Miller, THP and Diana Supe about finalizing the SOSS for this project. It appears to be much larger than originally thought. KLH has already visited the site and did a walk through with the Facility Director Wes Miller. TTC will re-contact and set up a field trip for TE to build the SOSS by Wednesday.

ADAS – Due Diligence MEP Study Read More »

Energy Manager Project

01/16/07 – TTC compiled new format energy report and sent to Tony & Ralph. After December bills come in, TEI will present year end Energy report for Tony and Ralph.

06/01/06 – TTC sent Governors Award Application out for review. Markups will be incorporated and sent out UPS on June 2, 2006 to ODOD.

05/22/06 – TTC and Tony discussed the Governor’s Award for Energy that is due on June 02, 2006.

05/18/06 – Talked to Compass Energy about being an authorized buying agent for Hamilton County. There are so many things I like about this approach. I typed up and email to Tony to outline his benefits. We are awaiting approval to move forward.

05/05/06 – Strategic is very interested in bidding County work but mostly PBS. TTC sent the indemnity clause to them that County always requires and they want a conference call on 05/16/06 to discuss Q&A.

04/05/06 – After a second conference call, Tony has requested a write up from TTC outlining the possible cost and savings for bidding our dereg electric. TTC shall get this complete in a week.

03/23/06 – TEI sent Tony & Ralph the CCAO Report for 2005 updated with all the latest numbers. TEI sent Tony & Ralph the 2005 Monthly Report through December with the final CCAO numbers included. Next on TTC’s agenda is to update the yearly master and then the 2006 report for CCAO gas cost.

03/20/06 – Terry requested the Nov/Dec CCAO bills again as the latest packet doesn’t have them. TTC also contacted the CCAO for the information and talked to Amanda and she said she would fax them down to TTC but as of 3:40 p.m. they have not arrived. TEI cannot reconcile 2005 gas without this information.

03/15/06 – Talked to Joe Ewing today about Electric Deregulation Bid for county. We setup a conference call next week to discuss possibilities. TTC reconciled the 2006 Cinergy Rate schedule with an actual JC bill for February. This is a very big accomplishment towards reconciling the bills each and every month.

02/27/06 – TTC has to sign up for energy conference in Columbus. TTC and AKM discussed today on phone. TTC will drive up on Wed morning.

02/16/06 – TTC delivered the final report to Tony Matre and Ralph for use a couple of weeks ago but made one final change to the pie chart today. TTC is now working on deregulated electric and updating the individual building charts for a meeting with the bldg managers.

12/28/05 – TTC entered all the 2005 Gas data and got it input into the main spreadsheet for the County. TTC also began answering the CEC questionnaire.

12/09/05 – TTC discovered a billing anomaly in the CCAO billing for FT rate. It is a question that TTC can’t explain. The CH burnertip price is about $2 higher than the rest of the buildings for the same gas (it is all FT from the CCAO). Tony and Terry called the CCAO about the situation and left a message for assistance.

12/02/05 – TTC received the Energy Report packet today from the County that we will use as a template for LCC and this year’s report.

09/27/05 – Tony called and Terry sent our all 2004 Utility Data to Tony for his use. We sent a PDF and and excel file.

09/21/05 – First pass at Energy Star application yielded a grade of 33 for the 230 building. Passing is 75. TTC reviewed all data that Sam put into website. We believe that although we have additional data for additional months, this only hurts the ES score. Sam is removing extra months. The new score was in the mid 40’s. TTC manual calculated the buildings kbuth/sf to be 64.5 which is still lower than required for an Energy Star rating. TE is learning as we go on the application process for this website.

09/20/05 – Sam is currently entering 2004 data for 230 East Ninth.

09/16/05 – Set up user account at Energy Star for Hamilton County. We will be entering data for 230 East 9th Street for qualifications.

07/20/05 – TTC and Tom Kennedy met with Tony Matre and Mike Florimonte to discuss a proactive approach to getting the 230 East Ninth building LEED-EB certified. TE is to put together a business plan to make this work for the County

07/20/05 – TTC received the Alliance To Save Energy rejection letter for our March 2005 submission on the IT rate at the Courthouse. TTC forwarded the letter to Tony Matre.

07/19/05 – TTC finished the electric utility reports up through June 2005 and distributed to the County. TTC will work on reconciling the gas utilities next.

07/13/05 – Tony sent the CCAO summary to TTC for inclusion in to the energy files.

06/03/05 – TTC submitted the 2005 Governor’s Award to the State of Ohio. PDF. TTC submitted all 2004 energy data to Ralph for reporting.

05/26/05 – Downtown Six Pack Cinergy bills should started to arrive today at ThermalTech. There is no need to continue to copy Cinergy bills for EM work. I know will receive all the bills I need to do the monthly tracking. This should save Pat and Donna some work each week. If by chance I am missing one or two, I can request those manually.

05/20/05 – TTC has spent the better part of 3 days re-writing the TE software to accept all the new Cinergy Market Generation Riders so that I can correctly calculate and reconcile the energy bills for 2005. I estimate 2 more days of work before they are approved for use.

05/10/05 – TTC picked up Energy Authorization letter and will request data from Bill Fleisnner.

04/27/05 – TTC requested a County release for new energy data and to be authorized for the e-clips program to see Cinergy bills online, plus receive duplicate bills for the main 6-pack of buildings. The County should provide this letter.

03/31/05 – TTC sent in “Stars in Energy Alliance Application” PDF

03/25/05 – TTC startup monthly charts showing electric and gas, usage and cost and plotted on column graphs. TTC synchronized data with Tony’s local disk.

02/25/05 – TTC completed all the 2004 Energy Pulse Data Input. Graphs printed for 6 pack buildings. I am started to reconcile data vs. pulse data. A lot of energy bills are missing from 2004 and I have to contact Cinergy to get the actual bills for comparison. That request should be made on Tuesday.

02/18/05 – TTC attended the 9th Annual Ohio Energy Conference in Columbus and tabulated the 2004 237 WHT Energy Data.

02/11/05 – TTC will be working from TE and attending the Ohio Energy Conference next week for 2 days.

02/10/05 – TE registered TTC for the Ohio Energy Conference today. See you in Columbus next week.

02/08/05 – TTC collected more bills and is having Laurie at TE re-organize the bills by year, building, then service for easier updating..

02/04/05 – TTC got 230 E9th electric input for 2004. Looks like building has started using more energy and more 24/7 hours. TTC pointed out on graph to AKM.

02/02/05 – All 2004 bills have been tabulated. TTC and AKM set a schedule of having Energy Star program applied for by May 2005, having LEED-EB applied for by May 2005 and having Deregulated Electric bid on street by May 01, 2005. Cinergy has provided ALL 2004 interval electric data in an email today.

01/28/05 – TTC organized bills collected from 2004 for water, gas and electric.

01/2 1/05 – TTC organized bills collected from 2004 for water, gas and electric.

01/14/05 – TTC created water spreadsheet for 237 WHT. There are unexplained phenomena that need further investigation.

01/07/05 – TTC requested data from all current registered Cinergy Suppliers for Deregulated Electricity for County Bidding Purposes.

Energy Manager Project Read More »

XPEDX – DUE DILIGENCE STUDY

05/21/07 – The team presented the both phases of the Due Diligence study and the BOE move in programming and cost to Jeff Alluto, Diana Supe, Kevin Maue and John Michel and Bill Stautberg today. We went over existing conditions and possible future costs if the BOE takes occupancy of the building. Phasing plans and cost were turned over to the owner for this report. MEP wise the building is in good shape and will work for this and future needs.

05/14/07 – TE has DK on site for mechanical HVAC testing. TEI visited the site last week to get more FPC, EC and PC information. Report is due for review this Friday with MD and partners.

04/27/07 – TE awaiting signed SOSS.

04/18/07 – TE got prices from one contractor to perform Due Diligence on the AHU’s units at the site for $1900. We have a couple of request still pending.

04/17/07 – TTC & TA visited the site with CRA and THP and County Officials to take pictures, look at equipment and assess the requirements to prepare the Due Diligence Report.

XPEDX – DUE DILIGENCE STUDY Read More »

BLACKOUT/VULNERABILITY STUDY

04/27/07 – The final report is going to be delivered to Hamilton County Facilities Department today, April 27, 2007.

04/20/07 – TE received word from Hamilton County Facilities and are currently working on the final report.

04/13/07 – TE awaiting word from Hamilton County Facilities to proceed with final report.

04/03/07 – TA turned over draft copy report to Mark Donnelly by hand for review.

03/30/07 – Project progressing as expected.

03/23/07 – Hillcrest and Patrol Hdqtrs are complete. 800 Broadway is scheduled for next week.

03/20/07 – Patrol Hdqtrs fieldwork is complete. Hillcrest is scheduled in the next couple of weeks. Whole project is scheduled to be completed by end of March 07

03/14/07 – Patrol Headquarters, 800 Broadway and Hillcrest Campus have been added to the list of buildings to be evaluated. Field work for Patrol Headquarters and 800 Broadway has been performed. Hillcrest will be completed next week.

02/28/07 – 5 out of 6 original buildings have the report completed and turned over the Hamilton County Facilities Department.

02/19/07 – TEI will wrap up this project. 3 buildings are left to complete. CH, CAB, River City, Coroner’s Office are complete.

02/02/07 – The write up is very nearly complete on this project. TA is hoping to finish today.

11/03/06 – Write up is progressing

09/29/06 – Field trip is scheduled for week of 10/02/06

09/22/06 – Field trip is scheduled for the week of 9/25

09/15/06 – 5 out of 6 buildings are complete. Working on 6th next week.

BLACKOUT/VULNERABILITY STUDY Read More »

2010 COST ESTIMATES

07/24/09 – The cost estimates were finished on Wed 07/22 but Bert found several that needed more work or were empty. We finished these today. TTC reviewed every project new and old for completeness. The LEED portion was difficult and I an not 100% sure the data will be totally usable by HamCo fo its 2010 needs but it is the first step towards getting greener buildings. The projects are complete. CRA will be printing manuals for the next 5 days.

06/23/09 – TTC reviewed the Rebuild America and ECM Screening Tool with Tim and issued the original cost and scope documents to the team for updating our scope items for the cost estimate project. I have found several projects that are duplicates and especially have some questions about the Hillcrest site where they appear to be repeated twice and maybe three times. Terry will call Bert to discuss.

06/19/09 – The SOSS is approved and we have begun visiting the buildings. Terry and Mike have been to the 250 WHT building. The remaining projects are being coordinate by several TE employees for field trips next week. For this project we will have Terry, Tim, Andy and Mike Folck performing mechanical estimates. Mike, Danny and George will be performing the electrical estimates. Today we had our internal TEI kickoff meeting and internal Archibus training for input.

2010 COST ESTIMATES Read More »

BOARD OF ELECTIONS Third Floor Renovation

10/16/08 – Bert reports the BOE is very happy and has given Facilities a kudos for the work.

08/22/08 – Permit is in County hands for IBI. Bert said city permit was also received.

08/08/08 – According to City Permit Tracker Website this project is APPROVED.

08/01/08 – TEI has submitted three drawings to IBI for permit for this project.

09/05/08 – Permit approved in August. TEI submitted final payment for permits so final inspection can be scheduled.

BOARD OF ELECTIONS Third Floor Renovation Read More »

FIRE ALARM & FIRE SUPPRESSION MAINTENANCE BIDS

02/02/10 – Cintas submitted paperwork for a change order cost to the JC work for 2010 based on building count inaccuracies. TEI may review? No word on Tony on what he needs.

12/31/09 – The only development aside from all contract being approved is that JCI will not agree to the contract published with the project. The Admin bldg is going to have to be inspected outside the scope of this project. TTC recommended Hamco take out a change order on SA Communale contract and get them to do the building for 2009. A separate agreement will have to be reached with one of our vendors to get the 2009 testing complete. Tony is working on final contracts.

09/11/09 – TTC sent final contracts to Tony for delivering to Kerry for review. We have 5 contracts on this job and everything is under budget. SA Communale got most of the buildings, Cintas, JCI and Simplex each got one of the buildings.

08/25/09 – Addendums 1-5 have been sent out and extended the bid to Sept 4. One company protested the bid and forced Addendum 5 and we published the actual service contract with the last addendum for their use.

07/29/09 – We have collected almost all of the building summary sheets for the project back from the building managers. TTC & DPC are working on the new spec, combined bid forms, etc for the large Addendum.

07/15/09 – Addendum 01 went out to bidders and extended the bid opening date to August 19th.

06/23/09 – Today was the first prebid meeting and it was less than stellar. The addendum on this project will be quite large and we have to get better equipment counts in all the buildings. The printouts that were provided do not have all the equipment the contractors want to see for an accurate bid. We will most likely extend the bid opening by one month, detail the scope of work better, combine the bids, rework the building summary sheets, take combined bids for better pricing, add an alternate for the five year required testing and add an alternate for the County workers to self perform all the weekly and monthly testing.

FIRE ALARM & FIRE SUPPRESSION MAINTENANCE BIDS Read More »

ELECTRICAL DEREGULATION 2009

01/28/10 – Talk to PBS & Tony. All paperwork should be in. There are some lingering questions about contract signee’s and interval meters at several locations. As these get solved to the satisfaction of DERS these accounts will be brought on line too.

12/31/09 – Contracts are being signed. Interval meters request have been sent out. TTC forwarded the emails to hamco directors for signature and suggested everyone accept option 2 where the cost $446 each of the interval meter be rolled into the monthly bills for 24 months. Bill Fleissner is our contact at DEO for this. There was significant conversation between Matre and Cannon about us believe the entire cost was under $1000 for interval meters. DERS indicated 11 accounts required them. TTC rebuffed that by providing interval data on 9 of those accounts. DEO came back with another 19 that required it because peak demands were over 100kw not 1000kw as TTC believed. In the end written documentation is clear that the threshold is 100kw. PBS has already signed and faxed their approval to DEO. Final contracts and insurance have been worked out between Kerry, Tim and DERS. TEI provided backup savings calcs for the groups approving DERS savings estimates at significantly lower numbers (DERS numbers include cost savings and cost avoidance savings as one lump number).

10/20/09 – We have about five vendors registered and we have extended the contract question phase. We are opening the project on Nov 19. We have no contract questions yet on this project.

09/22/09 – Tony and Terry discussed insurance requirements with Tim Grabenstein for this contract. TTC sent the final copy for review to Tim. TEi asked for comments back by Friday.

09/21/09 – Contract comments came back from Tony and Kerry. Jim and Terry merged them into a final contract. We received the ITB-92-09 for this project. TEi will issue the final documents for public distribution on Oct 1. Contract questions and comments will be due Oct 15th. Bids are due in November.

08/19/09 – We completed our meeting with the Prosecutor’s office RSM will write a preliminary contract. TEI will write the end. 6 certified suppliers will be invited. Ralph will present to the commissioners for their review. Ralph, Tony, Kerry and myself have agreed to the plan.

07/20/09 – TTC sent Tony a revised SOSS for bidding out electrical services for the County. Ralph also asked about the Voltage Guard hardware which TTC and NV replied that TEI was very weary of this technology. We are doing more investigation.

06/23/09 – The report is approved and we have presented the results to the Commissioners. There are a few projects for energy savings that we should pursue in this year.

ELECTRICAL DEREGULATION 2009 Read More »

Archibus Drawing Updates

6/18/10-Met with Jack Randle of In4 and Michelle Ray of Hamilton County Facilities Department to discuss In4 scope of work verses Architectural Partnership scope of work. First Floor of Alms and Doepke mentioned. Michelle to investigate status.

6/21/10- Received email from Bert Watts with attachment documenting building drawing red-marks for correction.

6/22/10- Verified with Bert Watts the First Floor of Alms and Doepke is to be added to list of drawing corrections.

6/23/10- Submitted SOSS to Bert Watts at monthly Partner Meeting.

6/29/10- Approved SOSS delivered to GBBN.

7/02/10- Drawing updates completed and reported to Bert Watts.

Archibus Drawing Updates Read More »

2011 Project Request Estimating

4/26/10- Bert Watts discussed Estimating Project at Monthly Partner Meeting

5/8/10- Bert Watts email with attachments listing Partner and Project Manager Project List received.

5/12/10- GBBN received estimates for services from Mike Strine at Pinnacle Engineering for Asbestos Abatement Services.

5/13/10- GBBN submitted SOSS to Bert Watts.

6/23/10- Met with Walt Heckel of THP to coordinate all projects involving “All Partners”.

6/23/10- Conference call with Susan Barrett of IPM to discuss Communications Building Projects estimated earlier by IPM.

6/24/10- GBBN submits proposal requests to vendors for printing and assembly of project binders.

7/01/10- GBBN met with Bud Wells at Parkhaus Garage to discuss vegetative roof project request

7/02/10- IPM/GBBN visited Communications Center to discuss two project requests.

7/03/10- GBBN visited 2020 Auburn to discuss and document two project requests.

7/18/10- QCR delivers final binder tab revisions to GBBN to allow for final binder assembly.

7/19/10- Deliver project request binders (9 sets) to Bert Watts at the Courthouse.

7/20/10- Record set of Binders delivered to MEP Partner TEI.

7/22/10- Bert Watts delivers revisions to Binder Summaries for GBBN to insert into sets for partners.

7/23/10- Record set of Binders delivered to structural Partner THP.

7/27/10- Bert indicated the binders are to be slightly realigned from GBBN’s submission. Bert will take the 9th set of binders and realign them for GBBN’s reference. GBBN’s current office copy set of binders will be delivered to IPM for their records.

7/29/10- GBBN to received 9th set of binders from Bert Watts at the monthly partnering meeting.

2011 Project Request Estimating Read More »

Workforce Investment Board Vestibule Renovations

Current Comments (5/26/2010)

Project complete. Working on closeout documentation. CRA completing work.

Past Comments

Masonry repair work in progress.

Vestibule removed and new vestibule under construction.

New piers anticipated next week.(2/24/10)
Contractor completed demolition of vestibule.(2/24/10)
Sink Hole investigation:
Dug test well to footings and no fill below footing.
Pumped 5 yards of flash fill into void.
Plan to complete second test well on adjacent wall.
All phases of work approved.
THP subconsultant to CR Architects.

Workforce Investment Board Vestibule Renovations Read More »

2012 Project Cost Estimates

06/27/11 – Project 1208 was updated. Barth already had the cost separated as Bert wanted.

06/24/11 – Project estimates are complete. We are currently putting final touches of the estimates for this year.

05/24/11 -started field work on most estimates. Several have been input. Added one based on field work.

04/27/11 – We will be kickoff off this project next Monday and doing the work in May 2011.

2012 Project Cost Estimates Read More »

Emergency Generator PM Bid

06/29/11 – Tony reported today that the contract is approved.

05/03/11 – ThermalTech turned over final paperwork to Blaine for contract writing.

04/27/11 – Engineer’s office is writing a one year contract, Comm Center asked me to looked at three year bids and Tony asked me to write a contract for five years for the Facility buildings.

03/30/11 – Bids are due Thursday at 11am. TTC will attend. Three Addendums have been sent out on this job. We are taking prices on base bid, alternate and unit prices.

02/25/11 – Project is out for bidding. Prebid Mar 11, Bid Opening Mar 24. Note: TTC has to fix bid form for more clarity on bid day.

02/22/10 – Tony and Mike have approved the project manual and TEI will be sending to Jill Williams for bidding on Friday Feb 25.

Emergency Generator PM Bid Read More »

ENERGY MANAGER 2011

08/25/11 – Ameresco work is in final stages for contract negotiations. More controls meetings are schedule. Ameresco is presenting final report early Sept.

07/29/11 – 10 color copies of the final report have been mailed to Ralph per his request. The 2010 Report is complete.

07/07/11 – Energy Star bills have been entered for 230, Admin, and 800 Broadway. Field trips were scheduled for 230 and Admin, but have to be moved back to July 26 to coordinate with Florimonte vacation.

06/24/11 – Ralph said that he is sending Jeff’s questions over for final changes.

05/04/11 – Deliver 2 hard copies to Tony & Ralph today. Ralph said that if Jeff Aluotto approves this report, we can print these in color and be done. Also for 2011 report, he would like Hillcrest added, 237 WHT removed and the water data expanded.

04/26/11 – Delivered the final report to Ralph for 2010 including water from 2009 and 2010 completed for all major buildings. In 2011 we will add water for the remaining buildings and try to back date that information to 2007. We are trying to update the Energy Watchdog website before the final import at the end of May. It is nice to report that we saved over $1,000,000 in 2010 on our 3 major energy conservation measures.

03/30/11 – TTC finished inputting water bills. Thursday Amy will integrate into the report. Friday, Terry will finish the report.

03/14/11 – Duke has confirmed that ThermalTech has correctly included all the Administration Bldg electric into the Energy Star website. With this information, we are going to move forward with Estar approval.

03/01/11 – TTC has to add the deregulated electricity calcs to the report.

02/22/11 – TTC gave Ralph and Tony their final copy to review. Comments are back and TTC will finalize to give to Ralph for review by EOB on Friday.

01/24/11 – Folck has entered all bills that have been received. Terry and Amy are starting the Energy Report this week. Hopefully to be completed early February.

09/29/10 – All bills ThermalTech receives have been input into Watchdog. Next week have to do the bills kept at the CH.

07/28/10 – We are working on the new HamCo RFP with a couple of ESCO. RFP’s are due Aug 16.

05/26/10 – We received the 237 bills. Folck will input them. We will then generate the April bill.

05/06/10 – We modified Energy Watchdog to allow us to start entering electric commodity for Hamilton County ins 2010. Folck will enter all bills to date starting this afternoon.

04/26/10 – We delivered 10 copies of the final report to Ralph last Thursday. We delivered an updated electronic copy with the years of each project added to the Appendix today per Ralph’s request. We will continue to update bills in Energy Watchdog.

03/22/10 – Ralph and Tony have returned the Energy Report with comments. TTC will compile the final report. All previous reports uploaded to web.

03/05/10 – ThermalTech sent the final report to Ralph and Tony for commenting. TEi will compile the final report when comments are returned.

02/24/10 – Attended the 14th Annual Ohio Energy Conference with Tony & Ralph. Got the Energy Report about 50% complete. We are adding new buildings this year which means fixing the baseline model from 1997 and forward. It is harder than expected and taking longer.

02/22/10 – We have collected all utility data for 2009 and input into our worksheets

02/04/10 – Energy Watchdog data is input for 2009 for all buildings except for missing CCAO bills for Courthouse. We are working on the 2009 report and trying to finalize all the bills.

01/28/10 – Terry and Amy will be updating the report in Feb 2010. Andy is putting in the Watchdog data and Energy Star data this week.

12/31/09 – More bills are being input. The energy watchdog website should be up to date by mid January.

09/22/09 – Some bills are missing. TTC contacted Tony about Coroner’s gas bills. Jackson called about Coroner’s office water usage. TTC emailed the 2010 cost estimate report and explained the cost and program to reduce water usage.

08/19/09 – We completed our meeting with the Prosecutor’s office RSM will write a preliminary contract. TEI will write the end. 6 certified suppliers will be invited. Ralph will present to the commissioners for their review. Ralph, Tony, Kerry and myself have agreed to the plan.

07/20/09 – TTC sent Tony a revised SOSS for bidding out electrical services for the County. Ralph also asked about the Voltage Guard hardware which TTC and NV replied that TEI was very weary of this technology. We are doing more investigation.

06/23/09 – The report is approved and we have presented the results to the Commissioners. There are a few projects for energy savings that we should pursue in this year.

05/22/09 – The final report was turned over to the commissioners and we attended the commissioner meeting on 05/18. Mike Folck is updating all the water bills from 2009 and 2009. All data has been entered into Energy Watchdog through April 2008. We are not updating our monthly sheets until next year.

04/05/09 – The report is ready for TTC to review. I will get this done this week. I emailed Ralph & Tony about working with Ameresco on the 2009 energy projects.

01/26/09 – TTC & MAF finished the ECM Summary table and sent to Ralph Linne & Tony Matre. Ralph forwarded it to Jeff Aluotto for use. We are awaiting and update on how to write the SOSS for the work.

ENERGY MANAGER 2011 Read More »

2012 Project Estimates

Current Comments (9/28/2011)
Past Comments

Project complete.

THP added 250 William Howard Taft assessment into Archibus.

June 6 THP updated Archibus entries for 1431 and 1432.

Project estimates completed and loading into Archibus June 3, 2011.

THP reviewing project estimates, deadline for data entry into Archibus is June 3.

May 5, 2011 SOSS approved.

THP developing SOSS.

March 31, 2011 requested SOSS to complete 2012 project estimates.

2012 Project Estimates Read More »

2012 Project Request Estimating

03/31/11- Kick-off Meeting with Bert Watts during regular monthly Partnering Meeting. Tabulation Lists to be issued to all partners.

04/28/11- SOSS delivered to Bert Watts at monthly partnering meeting.

05/16/11- Met with Scott Lemond of ARC to discuss printing schedule and deliverables.

05/12/11- GBBN and IPM visited with Greg Smorey of the County Engineer’s Office to discuss the CAB 8th Floor Phase 2 Renovations.

05/18/11- Met with Greg Smorey of the County Engineers Office to review scope of project request for the Phase 2 renovation of the 8th floor not renovated in Phase 1.

05/31/11- Meeting with Greg Gelhaussen of the County Engineer’s Office at Ripple Road Engineer’s Garage.

06/14/11- All project Request Estimating is closed and completed.

06/23/11- Bert Watts email indicating three Project Requests have been eliminated.

06/27/11- Bert Watts email indicating one additional Project Request has been eliminated.

06/30/11- Deadline for all consultants to complete any requested revisions to Project Requests.

07/05/11- Delivery of electronic files and lists of projects to ARC printing

07/27/11- Binders received from ARC printing. Bert Watts accepts delivery from GBBN

07/29/11- GBBN delivers and installs corrected spline and cover slipsheets.

08/05/11- GBBN delivers partner sets of binders to THP and IPM.

08/25/11- GBBN delivers partner set of binders to TEI and CD’s of 2011 and 2012 to all partners.

2012 Project Request Estimating Read More »

2011 General Services – GBBN

01/14/11-SOSS submitted.

01/21/11- Bert Watts forwarded the new Contractor Safety and Health Specification section that is to be included in all future HCFD project manuals.

01/24/11-SOSS signed by BOCC and issued to GBBN along with Purchase Order.

01/25/11- Modified Standard Bidding Documents to indicate Christian Sigman as Interim County Administrator.

01/27/10-Attended HCFD Partnership monthly partner meeting.

01/27/11- GBBN forwarded to the other Partners the revised Master Specification Table of Contents and Legal Wrap showing the inclusion of the new Contractor Safety and Health specification section.

02/04/11- The meeting with Amy Hoh to kick-off a new project to modify the existing office partitions was cancelled.

02/14/11-Kick-off meeting with Sean Winfield of CAGIS to initiate an estimate to enlarge the CAB 10th Floor Conference Room.

02/15/11- Bert Watts agreed to perform the CAGIS work under this contract in lieu of a SOSS.

02/18/11- Drawings and estimate for CAGIS project sent to Bert Watts.

02/24/11- Attended the regularly schedule Partnering meeting at the Courthouse.

03/12/11- Met with Bert Watts to review the as-built conditions at Parkhaus Retail spaces. GBBN took measurements and photographs of space

03/15/11- GBBN sent as-builts to Bert Watts for review. Additional MEP input to be performed by GBBN due to lack of involvem,ent by ThermalTech.

03/25/11- Meeting with GBBN, ThermalTech and Duke Energy to discuss potential energy savings and partnering programs.

03/31/11- Attended the regularly schedule Partnering meeting at the Courthouse.

04/28/11- Attended the regularly schedule Partnering meeting at the Courthouse.

05/11/11- Interior Project Management performed background checks at the Justice Center. GBBN delivers results to Diana Supe.

05/12/11- GBBN staff performed background checks at Justice Center. GBBN delivered results to Diana Supe.

05/26/11- Attended the regularly schedule Partnering meeting at the Courthouse.

06/23/11- Corrections for new County Administrator made to standard front-end specifications.

06/30/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated after Partnering Meeting.

07/06/11- Meeting with ThermalTech to review Courthouse Courtroom Ceilings for redesign of the soffits and ceilings with Tony Matre.

07/29/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated before Partnering Meeting.

08/25/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated before Partnering Meeting.

09/29/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated before Partnering Meeting.

2011 General Services – GBBN Read More »

2013 Project Cost Estimates

06/06/12 THP submitted SOSS.

06/07/12 SOSS Executed.

06/29/12 THP updated Archibus with project estimates for 1469 and 1471. THP, TTE, and GBBN working on estimate for Revit modeling (1467).

09/17/12 – TTC checked in with Partners to ensure that website is updated with final cost for Bert and it was agreed that we had all of our consultant time entered to do the ThermalTech provided 3D modeling presented at Partner meeting in July with THP and GBBN support for building frame structures done at base level.

09/06/12- GBBN meets with Tremco Roofing on site to finalize the remaining roofs that require restoration or replacement. This is a result of the Project Request Estimate that was cancelled due to inaccurate roof designations for estimating.

2013 Project Cost Estimates Read More »

2012 General Services – GBBN

12/14/12 – SOSS submitted.

12/23/1 1- Signed SOSS returned by Bert Watts to GBBN.

01/26/12 -Attended HCFD Partnership monthly partner meeting.

02/23/12 – Attended HCFD Partnership monthly partner meeting.

03/29/12 – Attended HCFD Partnership monthly partner meeting.

04/26/12 – Attended HCFD Partnership monthly partner meeting.

05/16/12 – Bert Watts requests GBBN investigate CAB 6th Floor security upgrade project.

05/17/12 – BOCC CAB-6th Floor Security Modification estimate presented to Bert Watts.

05/31/12 – Attended HCFD Partnership monthly partner meeting.

05/23/12 – Bert Watts forwards the list and schedule for the 2012 CIP projects.

05/29/12 – Bert Watts sends letter of Critical Project SOSS requests.

05/16/12 – Bert Watts requests GBBN investigate CAB 6th Floor security upgrade project.

06/28/12 – GBBN attends monthly partnering meeting.

07/26/12 – GBBN attends monthly partnering meeting.

08/30/12 -GBBN attends monthly partnering meeting and performs website updates.

09/23/12- Bill Scholl of 2020 contacts GBBN about flooring replacement information. GBBN suggests contacting Spectra Flooring for State Term options.

09/27/12- GBBN attends monthly partnering meeting.

2012 General Services – GBBN Read More »

2012 General Services – THP

LEED Partner: THP
Current Status: SOSS
SOSS: F32
Contract Date:N/A

Status: N/A

As-built:

Status:

03/29/12 THP completed initial review the book case load assessment on the 9th floor in the Administration building. Initial assessment was inconclusive; either drawings are needed or testing is required.

THP Staff submitted information to Sheriff on January 30, 2012. Sheriff’s office noted background check can take six to eight weeks.

SOSS submitted; waiting on approval.

04/25/12 – THP working Administrative building load assessment field work to be scheduled with anticipated answer by mid-May. Drawings do not exist, so THP is complete a field survey and tests.

4/30/12 THP provided summary letter of Administrative Building load assessment to Bert Watts.

5/23/12 County provided Capital project list with proposed schedules. THP agreed with the proposed schedule.

5/29/12 County requested SOSS for the following projects: Memorial Hall, 800 BW Roof, and 250 WHT windows and concrete repair. SOSS due June 1, 2012.

2012 General Services – THP Read More »

2012 General Services – TEI

09/17/12 -Joann Cramer sent a new PW packet without the Terrorist statement included. TTC will udpate and distribute.

09/26/12 – SOSS-F056 Approved. TTC received, reviewed, updated and sent out the revised Prevailing Wage packet for Hamilton County Purchasing. Several edits were made by TTC. TTC updated the website for the new design with all buildings in facilities, black bar titles and updated projects for use and unloacked all building files for others to work on.

2012 General Services – TEI Read More »

Master Space Plan

Partner: GBBN

Status: Inactive

Status:

04/12/10- An email from Bert Watts requested a Kick-off meeting with Bud Wells in Courthouse B-90. First Phase of three to be performed in2010 requiring SOSS submittal.

04/15/10- Kick-off Meeting held with Bud Wells and Bert Watts. Handouts included Survey Form, Project Activity Timeline, Charter for Space Utilization Study and Buildings to be incorporated into study.

04/27/10- Clarification emails from Bud Wells and Bert Watts answered questions related to SOSS.

04/28/10- SOSS to be submitted to Bert Watts at Monthly Partnering Meeting.

05/21/10- Signed and Approved SOSS returned. Email from Bert Watts indicates schedule is to commence 6/24/10- Archibus Drawings to be updated are sent to GBBN from Bert Watts. Progress is on hold until In4 completes all Archibus polyline revisions and Michelle Ray completes all reviews.

08/04/10- Attended kick-off meeting to change this SOSS to another masterplan for the 237 Internalization study.

Master Space Plan Read More »

Master Plan Internalization Study

Partner: GBBN

Status: Inactive

Status:

08/04/10- Attended Kick-off meeting with Ralph Linne and Diana Supe.

08/18/10- Internal Kick-off meeting with Keven Speece, Thomas Rottinghuas, Jack Herbet Ralph Linne and Diana Supe along with Craig Landers and KEvn Maue of DDS.

08/30/10- Meeting with Ralph Linne and Diana Supe to discuss changes to the scope of this project. Project will now contain five options for relocation.

08/31/10- Met with Tony Matre and Bill Scholl at 237 WHT to walk the entire building and field verify the existing drawings.

09/01/10- Meeting with Jeff Alutto, Ralph Linne and Diana Supe to discuss all the various options, including those generated by GBBN, and decision affecting data to be considered.

09/01/10- Meeting with Craig Landers and Kevin Maue of DDS to discuss programming issues and schemes for possible relocation to 237 WHT for their existing employees in lease facitlities.

09/09/10- Meeting with Jeff Alutto, Ralph Linne and Diana Supe to discuss variations in options to be considered including possible tenants into 237 WHT.

09/17/10- GBBN met with Ralph Linne and Diana Supe to restructure the options to be investigated for the study. A report was requested to summarize the options and all data to be considered for the approval of the options to be developed further.

10/25/10- Kick-off Meeting with Ralph Linne and Diana Supe. SOSS requested for additional Options for Jeff Alutto to review for Masterplanning Studies.

11/03/10- Meeting with Jeff Alutto, Ralph Linne and Diana Supe to review report and options documented in Partner study.

Master Plan Internalization Study Read More »

2013 GENERAL SERVICES THP

12/24/13 – SOSS Requested

01/03/13 – SOSS Submitted to County.

01/07/13 – SOSS Executed.

03/20/13 – THP met with County to review beam condition in the basement of the Administration building. Based on the initial visit an additional assessment needs to occur to determine the effect of the active deterioration on the beam. The assessment will determine the need to stabilize or repair the beam.

06/04/13 – Coroner building is reporting long term leaks in the basement under the entry slab. Bert requested THP contact Mike Jackson and determine the possible leak/scope.

06/14/13 – Coroner building – THP reviewed entry after short term heavy rain. Evidence of long term water infiltration was evident, but entry did not leak. Reported findings to County with to recommendations: water test or wait for soaking rain to determine water leak. County directed THP to wait for a soaking rain; then publish a letter of findings.
10/31/13 – THP waiting for active water infiltration in the Coroner Building to evaluate scope of work.

01/30/14 – THP plans to archive project.

2013 GENERAL SERVICES THP Read More »

2013 GENERAL SERVICES GBBN

01/16/13 – SOSS submitted.

01/23/13 – Signed SOSS returned by Bert Watts to GBBN.

12/24/12 – THP – GBBN issues permit drawings; THP documents included.

01/23/13 – GBBN confirms to Millay & Company there is to be no Mechanical Permit initiated by the Owner due to no work required unless required by the Building Department.

01/31/13 – Attended HCFD Partnership monthly partner meeting. GBBN delivers signed General Services Contract to Bert Watts.

02/28/13 – Attended HCFD Partnership monthly partner meeting. GBBN delivers CD to THP and IPM for 2013 Estimating binder.

04/25/13 – GBBN attends monthly HCFD monthly partner meeting.

05/30/13 – GBBN attends monthly Partnering Meeting.

05/30/13 – We discussed the SBE packet for new bids. If we are 0% we do not have to include the actual packet in the bid specification to save paper.

05/30/13- County requests GBBN submit payment on Alms and Doepke Building Pinnacle Engineering Invoice on the General Services SOSS,

06/26/13 – GBBN performs Website updates.

06/27/13 – GBBN attends monthly Partnering Meeting.

07/25/13 – Monthly Partnering Meeting is suspended.

08/29/13 – GBBN attends monthly Partnering Meeting.

2013 GENERAL SERVICES GBBN Read More »

2013 GENERAL SERVICES THERMALTECH

Contact: Terry Cannon

Status: Active

Status:

11/19/12 – SOSS submitted.

11/29/12 – SOSS Approved.

12/12/12 – TTC updated front end documents to remove Terrorist documents.

02/01/13 – TTC updated front end bid documents to remove change President to Chris Monzel.

02/12/13 – TTC & SJ updated front end documents to add the non English speaking language to the Supplemental Conditions.

02/15/13 – TTC updated font end documents to remove the SBE paperwork and language.

03/14/13 – 800 Broadway Vacuum Pumps – TTC recommends doing the following after tracking down some factory information and meeting with Process Construction: 1. Temperatures coming back in the condensate piping are high indication leak-by at the traps: Recommendation-do a full trap survey and repair dysfunctional traps. 2. Temperature in “hurling” chamber start low when system is off and then rise to 190F. The aquastat on the hurling chamber is set at 190F so this tank will quench and drain continuously when the temperature is above 190F. We changed the MUW to this unit from softener water to standard city water because it is typically drained upon use. There is no need to use soft water for this mark up. This work was already completed today when I was there. 3. The condensate pumps are on a mechanical alternator and take turns pumping condensate in the lower chamber to the DA tank for boiler feed water make-up. 4. The vacuum pumps however are lead/backup. VP-1 is always the first pump on when the system vacuum gets close to 0″HG. It provides up to 4″ HG of vacuum, if this pump cannot provide vacuum, it automatically turns on the second pump and both VP-1, VP-2 run together to provide 4″HG. The vacuum limits are between 4″ to 8″HG. 5. Please leave all four HOA switches in the Auto position at all times. 6. With this knowledge, I believe I can report the Vacuum Pump Package on the left in the boiler room is working properly. 7. The vacuum package on the right appears to have a pump seal leaking and should be repaired prior to putting back into service. 8. Please repair the building steam traps to reduce the inlet temperatures from the traps to approximately 180F. Process stated that the vacuum system must be used when the building has low loads but you may find that under high loads (32F or lower) the steam system has enough pressure to push the condensate through the system and you can turn them off the vacuum pumps-that is for your users to decide if that can be done without leaving so much condensate in the building systems.

03/26/13 – Updated Website. Sent out some new formatting rules for users.

2013 GENERAL SERVICES THERMALTECH Read More »

ROYAL GLEN PUMPING STATION Pump Station

Lead Partner: ThermalTech

Current Status: Construction

Status:

10/05/12 – IBI approved 98% inspection today. MB at TEI called Steve Twehues of Duke and requested power get restored ASAP. Steve to contact IBI, get release letter, and schedule restoration of power with Steve Wessels (likely early next week). Project can then be closed out.
10/31/12 – IBI released approval. Duke energy powered the pump up, but there is no meter at this time. Duke energy is insisting that the exiting PT’s are relocated up approximately 2-3 feet on pole, they feel that this is a safety issue once the platforms are installed, they will be too close to be within reach. TTE and trades argued that this area is only accessed by “qualified personnel”, and Duke CPC agreed, but metering division is requiring that they are moved, stating that kids are thrift and can climb fences and that this is a safety issue.

08/28/13 – TE met with Steve Wessels and FD Lawrence. FDL pulled report on soft start, and determined that the soft start was starting/stopping every time that the pump ran. TE sent wiring diagram to Steve Wessels to wire a stop float and a start float.

01/24/14 – Back punchlist complete. This project is complete.

ROYAL GLEN PUMPING STATION Pump Station Read More »

2014 COST ESTIMATES

Partner: All Partners

Status: SOSS

Status:

04/25/13 – Bert reported that we are still probably doing estimates for next year but it may be later this year than most. They will handle resubmitted projects and the partners will get the new projects.

05/30/13 – BW reported that they are getting close to releasing the list to the partners but RWL has to review several items. This list may be bigger than usual if we get to do the entire list this year. This may include some work on the 20 year project.

07/08/13 – GBBN receives the “Capital Roof Plan” showing the historical replacement data and estimated pricing of the six downtown campus buildings from Tremco Roofing.

07/11/13 – GBBN submits SOSS to County for approval.

07/30/13 – GBBN receives approved SOSS from County.

07/23/13 – GBBN meets with Darnell Edwards to review elevator replacement estimating scope.

07/25/13 – GBBN meets with Joe Merkt to visit the Justice Center Roof for the roofing replacement estimate.

07/26/13 – GBBN meets with Mike Florimonte to visit the CAB and 230 WHT Law Center Roofs for the roof replacement estimates.

08/08/13 – GBBN meets with Aluminum Resources to discuss the Window Replacement estimates for the six downtown campus buildings.

08/09/13 – City of Cincinnati Elevator Inspection Department responds with Elevator Code Requirements applicable to the 800 Broadway Elevator Equipment Replacement.

08/10/13 – Kone Elevators responds with Estimating data to GBBN for the 800 Broadway Elevator Equipment Replacement. Existing equipment is Montgomery-Kone.

08/13/13 – GBBN meets with Maria Karvelas to discuss the 230 WHT Pre-Trial Estimating Scope.

08/15/13 – GBBN sends preliminary plans to Maria Karvelas for review.

08/16/13 – Maria Karvelas indicates preliminary drawings for the Pre-Trial estimate meet the requirements.

08/21/13 – GBBN receives pricing back from Seeger Glass for the replacement of the Justice Center High Security Windows.

08/26/13 – GBBN completes all estimating into Archibus.

08/28/13 – TEI reviewed combined estimates and made minor changes.

09/03/13 – GBBN contacts ARC to notify of impending printing requirements within the next two to three weeks.

07/08/13 – County provided list of project estimates for 2014.

07/17/13 – THP submitted SOSS for review.

08/08/13 – County approved SOSS.

08/27/13 – THP completed structural estimates and entry into Archibus.

2014 COST ESTIMATES Read More »

BOARD OF ELECTIONS ADA Ramp Entrance

Lead Partner: GBBN

Current Status: Construction

Status:

12/07/12 – THP 824 ADA upgrade project requested from the County. THP to provide structural services for entry ramp. Building Owner forwards existing PDF files of building floor plans.

12/08/12 – GBBN- issued SOSS to Hamilton County.

12/10/12 – GBBN, THP and TEI kick-off meeting and building tour.

12/12/12 – Existing hard copies of original building drawings received from Owner. ARC creates electronic copies for GBBN who distributes to TEI and THP.

12/13/12 – GBBN receives signed SOSS from Hamilton County.

12/14/12 – THP – THP issued SOSS to Hamilton County.

12/17/12 – GBBN meets with Building Owner and Contractor to discuss scope and walk existing building.

12/18/12 – THP – County executed THP SOSS. Building Contractor sends Otis Elevator ADA upgrade estimate to GBBN.

12/18/12 – GBBN sends ADA handicap access ramp layout to TEI and THP. CUH added by TEI and steel structure added by THP.

12/19/12 – Meeting with BOE staff that changes scope of work to include Lobby lift not ramp, no 2nd or 3rd floor restroom renovations and modified 3rd Floor renovations. Drawings generated by GBBN and circulated to BOE/ Facilities and Building Owner/Contactor.

12/19/12 – THP entry scope modified to allow for lift in lobby vs. constructing a room with a ramp adjacent to the entry.

12/20/12 – Ralph Linne notifies GBBN to proceed with generation of construction documents based on Building Owner original scope drawings.

12/21/12 – Small changes request to new scope drawings on the3rf Floor Office Area. Changes made by GBBN and sent to BOE. BOE signed off on new scope drawings.

12/28/12 – Final pricing and scope drawings sent to Millay & Company by GBBN.

01/02/13 – GBBN forwards new card reader lockset to BOE for approval.

01/04/13 – Ralph Linne notifies GBBN to proceed with amended scope from original SOSS per BOE Staff requests. GBBN sends approval to commence to TEI/THP. GBBN calls City Transportation and Planning to ask about handicap parking space in front of building. Left voice mail. No return call ever received.

01/07/13 – GBBN and TEI perform reflected ceiling field verification.

01/08/13 – GBBN meets with Midwest Accessibility Products to discuss details on lift installation and code approval.

01/12/13 – Ralph Linne confirms Prevailing Wage Rates required in specifications for contractor work on this project.

01/14/13 – Millay & Company confirms storefront replacement to be from existing horizontal door header and down. Existing transoms to remain.

01/15/13 – TEI sends stamped and sealed drawings to GBBN for permitting.

01/16/13 – THP sends stamped and sealed drawings to GBBN for permitting.

01/16/13 – GBBN notifies Millay& Company that stamped drawings, electronic CD and permit application available for pick-up at GBBN offices. Millay & Company requests electronic drawing files sent for review. GBBN complies.

01/21/13 – Millay & Company pick-up drawings from GBBN offices.

02/20/13 – Milay & Company sends a copy of the City of Cincinnati Permit Center building application response letter to GBBN. Most issues deal with existing building conditions.

02/22/13 – GBBN contacts Norwood Hardware about response letter issue on access control

02/25/13 – TEI reports findings concerning existing outside air repairs by building owner and test results from TEI research on existing units.

03/13/13 – Millay & Company receives letter from The City of Cincinnati Permit Center. Two items require further information for building permit approval.

03/14/13 – GBBN issues directive to BOE and Building Owner about front door over-swinging existing steps as code violation that must be addressed.

03/25/13 – GBBN receives return call from Plans Examiner with additional information concerning front door potential solution.

03/26/13 – The Building Owner and BOE agree upon GBBN Scheme B solution for addressing front entrance existing code violation solution.

04/12/13 – GBBN submits City of Cincinnati Permit Center requested Response letter and drawing corrections.

04/19/13 – City of Cincinnati Plans Examiner requests Mechanical Permit drawing for submission for earlier Mechanical Permit.

04/23/13 – TEI delivers stamped and signed Mechanical Drawing to GBBN for submittal to the City Permit Center.

08/22/13 – GBBN and THP attend meeting with Millay and Company to discuss structural coordination of steel support steel under the existing Lobby for lift elevator installation.

BOARD OF ELECTIONS ADA Ramp Entrance Read More »

2015 20-YEAR PROJECT ESTIMATES THERMALTECH

Lead Partner: TTE

Current Status: SOSS

Status:

09/17/14 – SOSS submitted.

09/26/14 – Prep work started for these estimates. Waiting on Administrator approvals.

10/29/14 – THP completed initial field work and estimates. THP entering data into Archibus.

12/12/14 – BW called with an SOSS update. This project is approved for work at a new SOSS. TTC marked approved and gave Becky the PO for future billing. Coroners office 20 Year cost to be added to scope.

01/19/15 – All 20 year estimates are complete. TTE coordinate with THP and GBBN for roof estimate at Coroners Office to complete the entire list.

01/21/15 – GBBN reported that Coroner’s Roof Estimate was complete.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

2015 20-YEAR PROJECT ESTIMATES THERMALTECH Read More »

2015 PROJECT ESTIMATES THP

Lead Partner: GBBN

Current Status: SOSS Approved

Status:

07/22/14 – THP issued SOSS.

08/04/14 – County requested SOSS for 20 year project estimates.

08/05/14 – GBBN issued initial SOSS for County review.

08/21/14- GBBN submits revised SOSS with 20-Year projects removed from the Annual Estimating

08/22/14 – County approved Revised SOSS.

09/03/14 – County approved SOSS.

09/23/14 – THP published Archibus estimates.

10/29/14 – THP completed initial field work and estimates. THP entering data into Archibus.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

2015 PROJECT ESTIMATES THP Read More »

2015 PROJECT ESTIMATES THERMALTECH

Lead Partner: TEI

Current Status: SOSS Approved

Status:

09/26/14 – Many estimates completed. Fieldwork underway. Project due 10/5/14.

10/05/14 – Most projects complete. Some stragglers and large projects remain to be estimated.

10/23/14 – ThermalTech down to Courthouse Server project remaining to be estimated. TTC to finish this week.

12/13/14 – TTC to review final project status and coordinate with GBBN. I believe all projects are complete and estimates are in.

01/19/15 – 2 leftover projects were completed by ThermalTech in Jan 2015. All projects are now truly complete.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

2015 PROJECT ESTIMATES THERMALTECH Read More »

2015 PROJECT ESTIMATES GBBN (20-Year and 2015)

Lead Partner: GBBN

Current Status: SOSS- F107

Status:

0717/14 – Bert Watts sends email to partner with initial listing of projects.

07/18/14 – GBBN inquires about 20/30 year projects, cost of living increases and approaches for delivery of these estimates. Bert Watts responds to GBBN.

07/21/14 – Bert Watts responds to questions via email and deliverable date.

07/22/14 – THP initials email and spreadsheet for discussion on lead partner roles in shared project estimates. GBBN responds back to THP.

07/29/14 – GBBN informs ARC Reprographics of probable schedule for deliverables of printing and binder assembly.

10/07/14- GBBN visits Burlington Garage and completes roof replacement estimate.

10/09/14- GBBN completes all 20-year Capital Improvement Estimates.

10/17/14- GBBN coordinates with Bert Watts on scope for the Technology Estimates at the Courthouse and Justice Center.

10/23/14- GBBN completes all 2015 Project Estimates including LEED Silver Estimates.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

03/22/15 – GBBN picks up empty binders from Facilities department for pickup by ARC Reprographics.

03/24/15 – ARC Reprographics picks up empty binders from GBBN for assembling final volumes of Project Request Estimating Volume Sets.

2015 PROJECT ESTIMATES GBBN (20-Year and 2015) Read More »

ADA Building Assessments

Partner: GBBN

Status: Active

Status:

05/04/11 – Bert Watts notified GBBN of prospective project via email.

05/19/11 – GBBN attended the SWOBOA seminar in new ADA requirements.

06/16/11 – Bert Watts indicated this Project Request should be broken into eight (8) separate SOSS’s based on each of the separate buildings. See the SOSS’s F045 through F052 below.

02/12/12 – Otis Elevator declines to assist GBBN in Elevator Assessment due to liability reasons. Suggests local consultant for assistance.

08/21/12 – GBBN completes last ADA Assessment Report for the Courthouse.

08/28/12 – GBBN begins estimating portion of Assessment Reports.

08/24/13 – GBBN completes estimating impacts of ADA Assessment findings on each building.

02/26/14 – Assessment report has now been fully reviewed and finalized. The cost estimate component is now in the preliminary stage of completion.

ADA Building Assessments Read More »

BURLINGTON RD GARAGE Damaged Wall Panel Replacement

Lead Partner: GBBN

Current Status: Close-out

Status:
10/14/14 – GBBN contacts Metallic Building Company about information on original pre-engineered building fabrication. Voice Mail is left.

10/18/14 – Project manual cover from original building construction sent to Metallic Building Company

02/24/15 – County requested a full letter report and authorized additional field work.

10/24/14 – GBBN contacts Metallic Building Company about information on original pre-engineered building fabrication. Voice Mail is left.

11/18/14 – GBBN contacts Metallic Building Company about information on original pre-engineered building color samples

11/25/14 – County Engineers reported existing overhead door stuck and has been closed temporarily not to be used until repairs completed.

12/15/14 – Metallic Building Company delivers quote for replacement part list to GBBN.

12/26/14 – GBBN authors and delivers SOSS to Bert Watts.

02/25/15 – Bert Watts emails approved SOSS and Purchase Order to commence work.

03/13/15 – GBBN attends Owner Review Meeting to review bid package documents.

03/13/15 – GBBN issues informational requests to five (5) selected bidders for project.

03/17/15 – GBBN sends invitations to Bid to all five (5) selected bidders. Electronic copies of documents included in email.

03/24/15 – GBBN holds Pre-Bid Meeting at Offices of County Engineers’ Burlington Road Garage. Hard copies of bid drawings and specifications handed out to potential bidders and owner.

03/25/15 – John Nester forwards scope quote from Overhead Door Company for overhead door repairs.

04/02/15 – Bids received and bid tabulation compiled for Facilities Department. GBBN commences interviews with those bidders submitting bids.

04/03/15 – GBBN forwards Recommendation Letter to Facilities for lowest and responsible bidder.

04/03/15 – Hamilton County approves recommendation and instructs GBBN to author contract to Century Construction Inc.

04/03/15 – GBBN hand delivers hard copies of AIA contract to Facilities Department.

04/07/15 – Century Construction delivers signed copy of Safety Receipt Form to Facilities Department.

04/10/15 – GBBN receives color samples chips from Century requiring approval.

04/13/15 – GBBN visits building and approves color samples from manufacturer and sends approved submittals to Century.

04/21/15 – GBBN receives Schedule of Values from Century, via Facilities Department.

04/29/15 – Pre-Construction Meeting held at site. Signed and executed contract hand delivered to Century from the Facilities Department. This date established as the contract commencement date.

05/15/15 – Century reports all construction work is completed. Facilities performs site inspection and punch list. One item, caulking bead at overhead door jamb is required.

05/19/15 – Facilities performs site inspection back punch list. The one item, caulking bead, has been installed as requested.

05/20/15 – GBBN signs first/final Application for Payment.

05/26/15 – GBBN sends email to Century requesting all close-out documents be processed and executed.

06/03/15 – Change Order #1 for additional signage scope, authored by GBBN and sent to Century for signatures.

06/15/15 – GBBN receives close out documents from Century Construction.

06/16/15 – GBBN receives executed Change Order #1.

06/16/15 – GBBN receives Application for Payment #0002 from Century but without Change Order #1 included. Century to revise and sent to GBBN once project change order work is completed.

07/20/15 – GBBN receives Application for Payment #0002 with Chan ge Order #1 included. GBBN signs and delivers to Facilities Department.

07/20/15 – Century Construction announces the change order signage has been installed on the building facade. John Nester confirms the work has been completed to the User Group’s satisfaction.

BURLINGTON RD GARAGE Damaged Wall Panel Replacement Read More »

2015 Electric Deregulation Bid

12/11/14 – Bert requested new SOSS this week for several end of year projects including A&D General Service, BW General Service, and 2015 Dereg Services.

03/31/15 – TTC requested updated account numbers for the Elec Dereg project from all clients for the 2015 bid.

04/01/15 – Greg Gelhausen replied to my account number request and wants to add one account to the bid. TTE said no problem.

04/14/15 – ITB 010-15 has been assigned to this project.

04/15/15 – TTE requested billing data from Duke on all accounts included in this bid.

04/20/15 – David Hisser returned all billing data to TTE for Calendar Year 2014.

05/25/15 – First Draft should be ready this week for Ralph and Tony to review and approve.

06/24/15 – Project is out for bid. Addendum 1 has been sent out. Addendum 2 is being prepared. We have 4 bidders registered.

07/16/15 – Dynegy contract approved for all four departments. Service starts in Jan 2016.

08/26/15 – Dynegy offered all Hamilton County employees a Preferred Discount plan on home electricity through 2015 or 2017.

2015 Electric Deregulation Bid Read More »

2016 Project Request Estimating ALL

05/16/15 – County requested SOSS from Partners.

05/18/15 – Bert Watts forwards email with “List of Projects by Partner” to all partners.

05/26/15 – GBBN hand delivers SOSS to Bert Watts.

05/29/15 – THP anticipates issuing SOSS.

06/02/15 – THP issued SOSS

06/05/15 – County executed SOSS for THP

06/24/15 – ThermalTech is complete with all but 3 estimates which are to be worked on tomorrow. Bert added #1824 for 800 Broadway Emergency Generator to TEI scope today. THP completed estimates and data entry into Archibus.

06/25/15 – GBBN completed with all but four estimates. ADA/Title II/III Projects Request Estimates are ongoing. Bert said that all projects must be done by 6/25 so he can make the early July deadline for the County.

07/20/15 – Facilities Department sends binder summary documents to GBBN for printing. GBBN informs ARC of the impending printing schedule.

08/26/15 – A call to ARC Reprographics confirmed the binder printing and assembly is nearly complete. ARC expects to deliver the binders to GBBN on Monday August 31st right on schedule.

08/31/15 – ARC Reprographics delivers all binders and existing documents to GBBN Offices.

09/01/15 – GBBN delivers Hamilton County copies of binders to Facilities Department.

2016 Project Request Estimating ALL Read More »

Fire Alarm & Sprinkler Testing

Partner: ThermalTech

Status: Active

Status:

06/24/15 – Project is out for bid. Addendum 1 has been sent out. Addendum 2 is being prepared. We have 4 bidders registered.

07/29/15 – Two day prebids complete. Add01 is issued. Add02 will be issued tomorrow. Bid opening on schedule for August 27.

08/27/15 – Bid opening scheduled for today. 2 Addendums issued total on this project.

09/23/15 – Tony selected SA Comunale form base bid initial term as the recommended bidder for this project. ThermalTech to author the contract for Facilities.

10/28/15 – Contracts approved. Project can be archived.

Fire Alarm & Sprinkler Testing Read More »

2017 Project Cost Estimates

All Partners

Status:

04/18/15 – Bert sent out estimate list for SOSS pricing. Facilities sends list of Project Request Estimating “Project by Partner” list to GBBN.

04/22/16 – Facilities sends email clarifying number of “standard” binders and “summary” binders along with CD’s to be delivered. Also clarification to other estimates are provided.

04/25/16 – IPM sends proposal for hours to be incurred for interiors scope of estimating.

04/25/16 – Facilities requests two separate SOSS, one for the estimating and one for the binder assembly and reimbursable expenses.

04/26/16 – GBBN hand delivers both SOSS to Facilities.

04/26/16 – Facilities requests that GBBN/IPM contact Facilities first for initial estimate contact on each Project Request and for any RFI.

05/25/16 – TEI proceeding nicely on cost estimates. We are hoping to be complete by 5/27/16 with all engineering estimates.

06/01/16 – TEI complete with 2017 estimates. We updated a few and added one after discussing with Bert Watts.

06/10/16 – GBBN completes all estimates.

06/20/16 – Facilities approves GBBN to begin estimate printing for final binder assembly.

06/28/16 – GBBN completes electronic project request estimate printing and notifies ARC for pick-up of all materials for binder assembly.

2017 Project Cost Estimates Read More »

2017 PROJECT REQUEST ESTIMATING PROJECT Estimating and Binder Assembly

Lead Partner: THP

Current Status: SOSS

Status:

04/18/16 – County requested GBBN complete project estimates for new 2017 work.

04/28/16 – GBBN provided an SOSS for review.

05/17/16 – County approved SOSS.

05/25/16 – GBBN reports to Facilities that it has completed estimates and entered them into Archibus for all assigned projects.

06/01/16 – Project estimates completed printing to pdf. Progress reported to Facilities.

06/14/16 – Facilities sends completed Binder Summary sheets to GBBN.

06/20/16 – GBBN completes packaging of al materials for ARC pick-up. ARC instructed to send deliveryman. Facilities confirms final numbers of binders and CD to be processed.

06/22//16 – ARC makes pick-up of all materials.

07/05/16 – ARC requests one pdf file be reprocessed and emailed. GBBN processes and emails back.

07/27/16 – GBBN sends request for status to ARC concerning printing and binder assembly.

07/28/16 – ARC responds the binders should be delivered between August 1 and the 4th.

08/01/16 – ARC delivers the binders and materials to GBBN. GBBN delivers one set of each binder to Facilities for review. Modified end binders required but approval given to GBBN to deliver all remaining binders.

08/02/16 – All final assembled binders and CD’s delivered to Facilities. CD delivered to IPM and TEI.

08/25/16 – GBBN delivers CD to THP at Partnering Meeting.

09/23/16 – GBBN receives final ARC invoice for printing services.

2017 PROJECT REQUEST ESTIMATING PROJECT Estimating and Binder Assembly Read More »

2017 STRUCTURAL PROJECTS Estimates

Lead Partner: THP

Current Status: SOSS

Status:

04/14/16 – County requested THP complete an investigation of slab settlement and cracking observed in the building.

04/18/16 – County requested THP complete project estimates for new 2017 work.

04/27/16 – THP provided an SOSS for review.

05/17/16 – County approved SOSS.

05/25/16 – THP has completed estimates and entered them into Archibus for all assigned projects except 17-FAC-2020-1847 and 17-FAC-5035-1848. Also confirmed Archibus entries for 17-REC-0138-1633 (entered by GBBN, LEED estimate currently $0.00 – not entered) and 17-FAC-1021-1845 (entered by THP and Thermal Tech).

05/27/16 – THP’s goal for having remaining two projects estimated and entered.

06/01/16 – Project estimates complete.

2017 STRUCTURAL PROJECTS Estimates Read More »

Emer Generator PM Bid

02/24/16 – Tony called and said that this project and PO are approved. Bid in March, Award in April, current contract runs out in May.

03/30/16 – Barth has made progress on the specifications they are about 90% complete. We are ready to get dates and an ITB and for Owner review.

04/26/16 – Project manual is ready. Date of Issuance will be 4/28/16. Bid Opening 5/26/16.

04/27/16 – Bid package sent to purchasing on 04/26/16. Pending bidding process.

05/25/16 – Bids open tomorrow. Two Addendums on project so far. All seems to be going well.

06/17/16 – Bids opened and there were anomalies. Tony to get information to ThermalTech as to which bidder each of the user groups has selected (Facilities, Cell Towers, Engineers).

06/27/16 – TTC to write a contract for Cummins for the Facility project. OK to share this contract with other departments if they need this. I told Tony this would be done last week, I will try to finish today.

07/18/16 – Tony is discussing with Kerry and is trying to stick with Cummins for the this contract. Kerry questioned the Alternate no bids by Cummins as legitimated on this job.

07/22/16 – Kerry and JoAnn and Tony are discussing rebidding this project due to Cummins not submitted Alternate bids for years 4 & 5.

07/25/16 – Talked to Tony and Gina today about the Alternate items in the Egen bid and we are going to rebid this project and we have change front ends to the standard county non-prevailing wage front end document and change Alternates to Optional Years. New ITB is 059-16.

07/28/16 – Talked to Tony and we are going to rebid all departments. I discussed a small SOSS to just pay for the the hours of this bid. We have a new ITB but no bid schedule yet.

08/03/16 – Tony said he approved my SOSS-A for rebidding this work. TTC to proceed.

08/25/16 – Egen PM Rebid sent out for bidding.

09/02/16 – No substantial questions on rebid yet. Bid opening scheduled for 9/8/16.

09/08/16 – Bid opening is today. Results to follow.

09/23/16 – IC won the second bid but didn’t include any battery replacement in year three. After several emails and reviews with Purchasing and the Prosecutors department, they are going to let their bid stand if they provide the battery replacements in year three.

10/25/16 – Post bid and Pre-Award meeting was held last Friday. Everything seems to be in order and TEI will write the contract for IAC today.

11/10/16 – All three revised contracts sent to Tony today for use on the Rebid work. IAC is the new vendor.

Emer Generator PM Bid Read More »

ELECTRICAL SWITCHGEAR PM SPECS

Lead Partner: TEI

Current Status: Approved

Status:

07/22/15 – TEI develop preventative maintenance specifications for Electrical switchgear in the following buildings. Alms and Doepke, Courthouse, 800 Broadway, 230 East Ninth Street, 250 William Howard Taft, and the County Administration Buildings.

10/28/15 – TEI working on specifications and coordinating with John Nester. TEI developed a scope matrix to review with John Nester, and also has written PM procedures. John Nester to confirm with HamCo PM procedures that the specs and the procedures are all encompassing.

12/07/15 – TEI sends John Nester preliminary specifications, questionnaire, and scope matrix for review and discussion.

04/27/16 – ThermalTech and John Nester meet to review specs. Information required from each building on “Mission Critical” equipment in building that can not see an outage. John Nester and Mike Barth are scheduled to attend next Building Managers Meeting on May 4th to facilitate the acquisition of information. Upon receipt of data from all buildings, specifications will be completed.

05/25/16 – Data from building managers due to John Nester at the June 1 building Managers meeting. Upon receipt of the data from all of the buildings, specifications can proceed.

06/27/16 – Data from building managers not all submitted to John Nester to date. ThermalTech provided JN a list of building that data still missing for. JN following up with Bldg Mgrs.

07/27/16 – ThermalTech met with John Nester just before MB Vacation. JN and MB concluded that specific data from building managers will not be obtained, and that the specifications need to be written in such a manner that we will give the overall concepts at each building, and we will size the emergency egens accordingly, but then state that building specifics will be worked out on a building by building basis.

10/27/16 – Comments back from John Gilbert this week, now ThermalTech can assist in getting the quotes together for the switchgear cleaning in the upcoming year. John Nester will lead this for HamCo.

01/27/17 – Specs are complete, project is ready to archive. Project can be be at any time, no dates were specific in the bid documents.

ELECTRICAL SWITCHGEAR PM SPECS Read More »

Burlington Garage Storage Shed Expansion

Lead Partner: GBBN

Current Status: SOSS

Status:

08/17/16 – Facilities confirms GBBN has no As-Built scope for this project on the SOSS.

08/18/16 – GBBN discusses <30% existing structure addition requirement for full existing building structural analysis. GBBN reports findings to Facilities. 08/22/16 - GBBN gets SOSS scope from TEI for Electrical scope of work. Hard copies delivered in the mail. 08/23/16 - GBBN consults with THP to discuss structural SOSS and permitting requirements for the project. 08/24/16 - GBBN forwards contact information from original contractor of Pole Barn Shed for investigation into alternative delivery method.

Burlington Garage Storage Shed Expansion Read More »

GALBRAITH SERVICE GARAGE LINTEL INVESTIGATION

Lead Partner: THP

Current Status: SOSS

Status:

03/16/16 – County requested THP investigate a deteriorating lintel at the service garage.

03/18/16 – THP visited the site to review field conditions.

03/31/16 – THP provided an SOSS for review.

07/08/16 – County approved SOSS.

07/28/16 – THP to schedule field work and complete field work in August.

08/22/16 – Field Assessment trip completed.

09/28/16 – THP anticipates final report being released 10/15/16.

GALBRAITH SERVICE GARAGE LINTEL INVESTIGATION Read More »

Energy Star Validations

09/02/16 – Buildings should be ready for certification after August bills are entered in late September. ThermalTech to draft SOSS for each building for approval.

10/14/16 – All fieldwork is complete for the certifications.

10/18/16 – TTC has reviewed all the SEP and found most to be compliant. The Courthouse requires some changes prior to submitting to the EPA. TTC contacted Tony Matre to discuss and make changes.

10/19/16 – TTC to meet Dave Johnson on site to reocver steam usage data for Courthouse Energy Star.

10/21/16 – These buildings have, 230,250,800,Admin, A&D have been uploaded to Energy Star. The Courthouse is not ready for SEP yet until we work out some occupancy issues that TEI is flagging as potential issues.

10/25/16 – TTC created a new SEP for the Courthouse with the updated numbers agreed upon between Tony and Terry. TEI will take to Ralph for signing on Thursday and hopefully upload to Estar on Friday.

11/10/16 – All six buildings have been submitted. Five buildings have been approved. We are waiting on the Courthouse approval at this time.

Energy Star Validations Read More »

BOARD OF ELECTIONS – RELOCATION SERVICES ESTIMATING

Lead Partner: GBBN

Current Status: Active- Project Closeout

01/22/16 – County requested availability for kick-off meeting with Board of Elections.

01/27/16 – Meeting date established for Kick-off Meeting at 824 Broadway Building. Kick-off meeting held at BOE Offices.

01/28/16 – IPM and GBBN visit existing Warehouse for site investigation and photographing of existing conditions.

02/04/16 – GBBN receives approved SOSS from Facilities.

02/09/16 – Facilities directs GBBN/IPM to use estimate number 1835 in Archibus for the estimating efforts.

02/10/16 – GBBN/IPM receives first space planning design from Owner’s Reality Agent.

02/23/16 – IPM visits proposed building site with BOE for the site investigation for the purpose of estimating the move services.

02/24/16 – GBBN and Facilities agree on concept for estimating electrical disconnect services to be placed into the estimate.

02/24/16 – IPM begins estimating input for the move services.

03/02/16 – IPM/GBBN confirm with Facilities that the Move Services will require a public bid if over $49,000.

03/03/16 – TEI communicates information about the Data Room/Network relocation component of the relocation services. Facilities responds to inquiry about inert gas/fire suppression systems.

03/07/16 – Facilities responds to additional requests for information about phone switch and data/I-T questions.

03/10/16 – TEI provides Network/Data/I-T relocation estimating data and cost figures.

03/11/16 – GBBN and IPM finalize estimating in Archibus with the exception of phone/I-T relocation pending input from BOE.

03/23/16 – GBBN/Facilities/HamCo Telecommunications/BOE meet to discuss I-T/Network/Phone relocation component of move services estimating. Telecom to provide estimate to BOE for running new data wiring at new facility. BOE to inquire with CBTS and Building Owner related to Inert Gas Extinguishing and Phone provisions in lease and services agreements for Telecommunications.

04/19/16 – BOE instructs Facilities that revisions to new facility space planning are not completed, by other Architectural firm, so data outlet location drawing have not been completed, for sending to Hamilton County Telecommunications Department for completion of their Opinion of Probable Costs for the data/telecommunications component, for insertion into GBBN overall Opinion of Probable Cost.

05/19/16 – GBBN attends Kick-off Meeting with RFP Team.

05/20/16 – Facilities requests SOSS from GBBN for the Moving Services Scope of Work.

05/24/16 – IPM meets with Sally Krisel to discuss scope and overall project delivery dates.

05/26/16 – GBBN submits SOSS to Facilities at monthly Partnering Meeting.

06/02/16 – GBBN and IPM attend BOE RFP Construction update meeting.

06/07/16 – GBBN and IPM attend BOE Design Services Kick-off Meeting.

06/08/16 – IPM completes BOE on site existing furniture/equipment field verification.

06/16/16 – GBBN and IPM attend BOE RFP Construction update meeting. IPM releases final furniture and equipment layouts to BOE for final approval.

06/30/16 – GBBN and IPM attend BOE RFP Construction update meeting.

07/14/16 – GBBN and IPM attend BOE RFP Construction update meeting.

07/21/16 – GBBN and IPM meet with BOE to review Moving Services Bid Package with BOE Directors.

07/28/16 – Next scheduled BOE RFP Construction update meeting with Developer, Building Team, BOE and Facilities.

08/15/16 – BOE Move Services ITB #061-16 Issuance of Bidding Documents.

08/23/16 – BOE Move Services ITB #061-16 Pre-Bid Meeting held. 824 Broadway was toured first, followed by 3600 Red Bank Road Warehouse and concluded at the 4700 Smith Road Facility.

08/30/16 – Final Day for Bidding Questions. GBBN receives one set of questions from Purchasing Department for Addenda.

09/01/16 – GBBN issues Addenda #1 to Purchasing and ARC.

09/08/16 – GBBN attends bid Opening for BOE. Two bids received and Purchasing releases copies of both bids to GBBN.

09/15/16 – GBBN and IPM meet with Planes Moving and Storage Inc to discuss bid, scope and validity of bid documents. Planes agrees to honor bid and agrees in principal to enter into contract with Hamilton County for this project.

09/19/16 – GBBN authors a Meeting Minute summary for Facilities with GBBN and IPM recommending Planes be awarded the contract.

09/26/16 – GBBN and Facilities discuss status of Meeting Minutes, recommendation and contract authoring. Subject of accepting Alternate Bid to be determined with conversations with the Board of Elections.

10/03/16 – GBBN authors AIA contract for Planes Moving and Storage. Delivers to Facilities.

10/05/16 – GBBN and IPM tour construction site to field verify critical furniture installation dimensions. Critical dimensions are found to be acceptable.

10/15/16 – Wessells Moving and Storage emails GBBN about the return of their Certified Check. GBBN emails Facilities about it immediately.

10/17/16 – Wessells calls GBBN to personally inquire about the return of the Certified Check. GBBN calls Facilities to inquire but no answers are available. GBBN calls Purchasing to obtain more information and obtains answer. GBBN calls Wessells back to inform them the bid recommendation has not been officially accepted by the County therefore check can not be returned until that time by Purchasing.

01/17/17 – IPM reports roof leak in new Warehouse area will delay move of elections equipment to new facility. Building Owner to have roof repaired.

02/22/17 – IPM reports to GBBN that move is progressing very well and move should be completed soon. BOE is very happy with progress by Planes Moving.

03/16/17 – GBBN authors and delivers Additional Services SOSS for IPM services due to delays related to roof leaks and delayed move-in of the Warehouse Elections Equipment.

03/17/17 – Planes issues request for additional services to be allocated from the Allowance built-in to the contract. GBBN requests that Planes re-issue request with additional cost break down including material and labor.

03/22/17 – Planes revised request received. Facilities approves request and authorizes GBBN to author Change Order #1 reflecting revised request.

03/23/17 – GBBN issues Change Order #1, with Architects signature, to Planes via mail.

03/27/17 – GBBN authors and mails Change Order #1 Revisions as requested by BOE.

04/20/17 – GBBN informs Planes that AIA Documents are required to submit any Application for Payments to the County per the Project Manual.

04/26/17 – GBBN coordinates completion of AIA Documents with Planes.

BOARD OF ELECTIONS – RELOCATION SERVICES ESTIMATING Read More »

Board of Elections- Training Center Renovation Study

Partner Lead: GBBN

Current Status: SOSS submitted

08/08/17 – Hamilton County requested Kick-off Meeting at BOE SOSS.

08/22/17 – GBBN and TEI meet with Facilities and BOE to discuss project, measure, photograph and field verify the existing space. Hamilton County requested SOSS.

08/25/17 – GBBN authors and provides Hamilton County with a SOSS.

08/26/17 – GBBN contacts Architect from RFP project to inquire about MEP drawing files from RFP Project. Architect responds sending along contact information for CM. CM is contacted and and sends files to GBBN.

08/26/17 – GBBN receives field verification dimensions from TEI for existing sanitary drain cleanout locations.

09/12/17 – Facilities communicates Project Request Estimate number to GBBN.

09/13/17 – GBBN communicates with Property Manager and CM related to RTU and Plumbing information.

09/14/17 – GBBN researches codes and Plumbing Fixture Unit requirements.

09/15/17 – GBBN finalizes the concept floor plan and circulates to Design Team. TEI finalizes HVAC concept approach with Facilities.

09/19/17 – Property Manager forwards information on Mechanical and Plumbing Contractors that worked on last renovation.

09/20/17 – TEI confirms contact with Mechanical Contractor.

09/22/17 – GBBN finishes Architectural and General Construction input into Archibus Project Request Estimate.

09/25/17 – TEI confirms contact with Plumbing Contractor and confirms concrete was placed in abandoned underground plumbing lines. Estimates are complete by ThermalTech for this project.

10/06/17 – BOE confirms to GBBN that tables used for trainees may be only 3 feet wide.

10/09/17 – BOE requests changes to the table and Training Room configurations. The Lobby is decreased in size and extra space dedicated to both Training Rooms.

10/10/17 – GBBN sends updated drawing to BOE for review.

10/11/17 – BOE confirms to GBBN which modified option has been selected for use. Decision on how to eventually pursue real project, if approved, is still pending discussions with Building Owner.

11/29/17 – GBBN and TEI attend Client project kickoff meeting on 11/29/17. Discuss schedule, budget, and design parameters.

Board of Elections- Training Center Renovation Study Read More »

PBS – Sound System Repair Project

03/21/06 – TEI asked for an engineering change order which covers extra time spent by ThermalTech during the construction phase and occupancy permit time on this project. Joe said he signed it and went on to his boss Eric Stuckey. This project is officially complete.

02/13/06 – TTC finally approved the closeout documents, final pay applications # 6 & 7 and as-built drawings for this project. The only thing left is TE request for additional payment.

12/02/05 – TE requested a revised final payapp reflecting $6200 change order that was approved for the north end zone speakers. All final paperwork and as-builts have been received from Durrell in hard copy and CD. TTC made a copy of this information and is sending all originals to Joe Feldkamp for his use included 3 binders of O&M’s required by spec. TE will have have a hard copy of the 1/2 sized dwgs, just the CD.

11/30/05 – Chris Schaeffer called to inform Terry that the County reached settlement with Ed Simon and his lawyer’s and that a court appearance would not be needed.

11/28/05 – Upon final check the sound system is working, the new speakers are installed and working and the final paperwork has all arrived including the as-builts for this building. TTC has to write an engineering change order for ThermalTech’s Extra Time and WJHW Extra Time on this project and submit it for payment for the year 2005.

11/14/05 – Durrell and TJ’s total change order totaled $6200 ($5600 + $600). Joe Feldkamp approved. TTC confirmed with both contractors. Chris Horrell and Scott have scheduled Durrell’s visit for this Wed 1/16/05. Work to be completed by Thursday. TE shall send out the hard copy paperwork to all vendors.

11/10/05 – TTC was contacted by Chris Schaeffer about a possible court appearance in December over the bidding of this project. TTC discussed County bidding procedures and current ORC requirements for bidding and how the Sound Engineer, Audio Contractor and Electrical Contractor was selected for this project.

09/12/05 – Pay Application #4 is being resent to TE. TTC will approve and send to County for payment. TJ delivered payapp to TE today.

09/08/05 – TTC emailed contractors about closeout for project and punchlist. Sound was excellent last Friday when TTC went to the Colts-Bengals preseason game. TTC sat in section 315 and was impressed with quality of sound and clearness of PA announcer.

08/09/05 – Durrell reported that, Tom and I went over these items and will have most knocked out this week prior to this weekends game. What will be left will have to do with getting QSC down to make the cosmetic changes to the amplifier control system to make it that much more user friendly and correctly control the amplifiers that are being displayed.

08/08/05 – TTC coordinated the final change order amounts with TJ Williams and will modify the change orders for final signing today. Both change orders are complete. TTC will deliver them by hand to PBS tomorrow and try to get Bill Meyer to stop down and sign them. Punchlist was compiled and emailed out to contractors (hyperlink below).

08/01/05 – WJHW and Durrell completed the punchlisting work. Ron Baker is going to send the punchlist to TTC for distribution. TTC talked to Scott Simpson about items that he needed added from his end and left a message for Joe about his items. The consensus appears to be that everything is very nearly complete and everyone is very happy. Hopefully this will lead to a quick closure and a working sound system ready for the season in a very short time period.

07/19/05 – We have reached resolution on the PBS Sound Change Orders. Amy will approve change order #1 8855.00 for the countertops and change order #2: 2,060.74 for restocking fees from TJ. TE will write the new change orders for these amounts and send them to TJ for signatures and then onto JF for signatures by the County. WJHW and Durrell have scheduled the Engineering Commissioning for this project on 07/27 thru 07/29. TTC will be out of town on Wednesday but will assist on Thurs/Fri as needed. Punchlist should be fine as Durrell and Scott Simpson have been working hand in hand during the project. TE and WJHW will supervise and TE will try to set up and Const Mtg on Friday for a final update on progress before we start the as-built drawings for this job. Durrell reported by email on 07/18/05:

Last week Durrell got all the speakers working (with only two exceptions) and wired to the correct amplifiers. The West amp room is complete, all racks laced and cleaned, all amplifiers working. The East we ran out of time Friday, but we have all amplifiers working with the correct speakers, we need to spend one day lacing up and minor cleaning.

We found one 2″ driver not working on the East side that will have to be accessed and one crossover on a full range speaker on top of the north end zone – each will require one day’s work.

The west club area is finished and working and the east is about two hours away (got held up due to a wedding party).

The control room is up and working. We had a MediaMatrix card fail (used backup for tuning) and Scott Simpson has to provide us with info where to mount the two computer screens and the Volume meter, both minor installs. The console and all the other equipment is in a functioning correctly including the software upgrades. We want to rebuild the control block that exist for the control screens for QSControl – some coordination will need to exist between Scott Simpson, Tom Moores and we would like Ron Baker’s input – when the commissioning is done.

Durrell will schedule two days prior to WJHW’s coming to PBS for their commissioning to be sure all of these minor items are finished. We are waiting on Ron Baker for that date (date has been set see above)

07/08/05 – Eric Stuckey, Joe Feldkamp, Diana Craynon and Bill Meyer called today to inform me that the change order has be stopped and no work will be done on it and it is most likely canceled until later. We informed TJ Williams and TTC is supposed to cancel Monday’s field trip to work on it.

07/05/05 – TTC emailed Eric Stuckey the final Change Order #01 cost including the cabling and the countertop for approval. PDF. TTC met Chris Schaeffer, Scott Simpson, Steve Durr, Sam Kinman and Ed Simon and his associates downtown today to supervise a field visit and walk through with the County for the County lawsuit.

06/27/05 – TTC sent out CD’s to HamCo for law suit.

06/23/05 – TJ Williams sent the revised ACO out today. PDF. Terry and Joe asked for TJ to redo the change order to reelect the credit that the County will be receiving in place of the speaker parts that won’t be installed. TTC and JF will then talked to Amy about writing a change order to finish the project off with the cabling upgrade. The Const Mtg verified that many, many of the issues with the speakers were resolved by fixing wiring and termination points. ThermalTech believes that by knowing this it is a fair inference that the 3000 foot cable splices are probably not infallible.

06/22/05 – Const Mtg #02 was held. Durrell reported that all base work is complete except for software upgrade on MM. Durrell offered to do all the CO work except for the cabling for the $50,000 allowance. TTC agreed that this work be a fair barter. We decided to accept the countertop change order from jb schmitt. We will pursue a change order to get the cabling issue taken care of this year and Joe and TTC will talk to Amy about it after TJ provides an update T&M price NTE for the work.

06/16/05 – TTC visited the site earlier in the week with JB Schmitt and they turned in a quote today for the new countertop work at PBS. TTC forwarded the quote to the team for a decision. Countertop = $5695.00 and New Window = $3160.00.

06/06/05 – Durrell sent an email request Topper be added to all correspondences on this project. TE forward to Joe Feldkamp for approval. PDF.

05/31/05 – TE tried to reach WJHW for a conference call to discuss moving forward with additional bidding on Change Orders for this project. CO# 2 and CO# 4 are significant and may have to be bid out separately. TJ Williams called today to see about CO approvals. TTC sent the Allowance email to Bill Meyer. TTC should have sent last week when it was approved but somehow that didn’t happen. TE and WJHW still need to talk to Joe about Club Level work and scope.

05/24/05 – TE issued a recommendation letter to PBS about Change Orders for this project. TE spoke to Durrell and told them they must proceed with scheduling on the assumption that the Change Orders # 2 and # 4 are not approved. The County will issue a formal approval as soon as it can. This may lead to scheduling conflicts later near substantial completion but bidding and change order policies must be adhered to for this project. PDF

05/17/05 – Consultants and JF are in consultation about approving change order request. TE has requested direction from their sub WJHW on what is essential and what is not. First TJ payapp is approved and sent to JF.

05/11/05 – TJ submitted 5 change orders today to the project. PDF TE setup a construction meeting for Thursday at 1:30 p.m. to discuss project progress. TJ contracts are signed and in security for contractor to pick up.

04/27/05 – Contract has been approved by the Commissioners. TTC advised the contractors that the contract and PO would soon be in their hands. TE and WJHW will have subs complete by the end of the week.

04/26/05 – WJHW has submittals for AV work on the job. TE has reviewed the submittals fro EC compliance and found no errors so we will approve them with “No Exceptions Noted” to that end, we have told TJ the same. TJ inquired about contract approval and TE told them Wed at Board meeting, we should know. Please advise us when you hear information about Contract.

04/22/05 – TE received submittals for TJ yesterday. TE is checking for EC items. TE shipped one to WJHW for AV items. TE has delivered all dwgs and specs to TJ for permit application. JF reported that contract is in front of board for approval on 04/27/05. Everyone is still working at their own risk to date. Durrell has sound system working in bowl for weekend draft picks. County Prosecutor asked for some video footage of splice problems in the amp rooms. PBS reported that some have been fixed but other still remain to be documented and that Durrell may know best which ones to document. JF and TTC communicated about this pre-work in email PDF.

04/19/05 – TE sent out an email stating the Durrell may be doing some additional work in the Club levels that is above the scope of work outlined in the contract. Monies for this work shall be determined later.

04/18/05 – TJ sent their employee list into the County for this project. PDF. JF reported that contracts have been submitted and the project is up for Board approval on 04/27/05.

04/12/05 – TE had TJ resign new contracts forms and delivered to Kerry Dowling for approval. Kerry said that she would sign these on 04/11/05 and TE would have City Dash pick up the newly signed contracts and have them delivered back to Joe Feldkamp for submission to the County Commissioners for approval. TE sent 3 sets of dwgs to Dallas for WJHW to sign for TJ to turn into IBI for permit sets. TE and JF told TJ at the pre construct mtg on 04/11/05 that all work done by Durrell and TJ before receiving the contract and the PO is “at your own risk” type work.

02/23/05 – TE delivered contact to Joe Feldkamp. TTC and JF discussed contractor over phone and coordinated paperwork due to prosecutor. JF will submit contract for prosecutor review. TE will hold on notification to contractors until all paperwork is finalized. TTC would like to see 2 week turnaround in contract to keep scheduled intact.

02/22/05 – TE has received all required bid paperwork and finalized the Contract. Contract, Drawings, Spec Books and Drawings will be sent to Joe Feldkamp today.

02/16/05 – County and PBS indicated to proceed with Base Bid and Alternate 2 for this project.

02/16/05 – TTC and WJHW discussed the Alternates from the bids and are basically recommending that the County accept Alternate # 2 at this time and wait on Alternate # 1 because of the unknown variables included with updating the system. TE recommends fixing all the existing problems first before adding a new layer of master control that my contribute new and undiscovered problem of us to troubleshoot in the field plus upgrading to the BIAMP system will add additional dollars to the existing SOSS as this is a scope change for engineering (WJHW is working on an adder price). We will write the contract with Alternate #2 for the time being.

02/08/05 – Bids opened. TJ Williams appears to be the low bidder. TE has contacted contractor for additional paperwork and will begin contract work immediately. County needs to provide a signed bid evaluation form with Alternate recommendations for contract.

01/25/05 – Addendum 3 distributed. Durrell asked a new question for Addendum 4. The bid was extended to February 3, 2005.

01/21/05 – TE coordinated with WJHW and County to extend bid date one week and to send out Addendum 03 on Monday with updated information for bidding and alternate. Purchasing Department instructed TE to contact ICB Audio via email about non-inclusion into the accepted bidder’s list for this project.

01/20/05 – TE distributed Addendum 01 on 01/11/05 and Addendum 02 on 01/20/05. Addendum 03 should come out on 01/21/05. TE has written a rejection letter and given it to Purchasing to give to ICB as they do not meet the Professional Stadium Experience Requirement on this project. The SoundCom qualifications have been sent to WJHW for review and we are currently waiting on SoundCom to confirm a couple of questions about which office will serve this project but they most likely will be approved for bidding as they do meet the quals. TTC asked if the bid should be extended since SoundCom is being added. TE is awaiting the County’s decision. The second prebid was attended by about 8 contractors. Muzak declined to bid and left the prebid after we stated that OEM equipment must be used for repair.

01/19/05 – Prebid is finished. Addendum # 01 wads distributed. Addendum # 02 is going out tonight. Addendum # 03 is scheduled out tomorrow. ICB will not be an approved vendor. TE has to provide a letter to Purchasing for the use, modify and send.

01/14/05 – Joe Feldkamp called to inform TE that because the prosecutor wants a firm number for cost to provide as-built drawings that we can change the bid for to add an alternate to have the AV contractor provide a complete set of as-builts encompassing the entire scope of work at the stadium. TE shall modify the bid form accordingly.

12/24/24 – TE invited Audio Specialist Contractors. Project Manual is on the street, on schedule. Prebid set for January 5th. WJHW will be in town for the prebid. Everything appears to be set for bidding att his time.

11/04/04 – TE found and sent the AV drawings to WJHW today. Final design is still scheduled for final delivery on 12/08/04.

10/25/04 – WJHW sent an informal report from the field trip last week. PDF

10/19/04 – TE, WJHW, PBS and HamCo had a meeting and set the following schedule for this project (see below)

10/19/04 – TE and WJHW met onsite with the owners and ironed out the scope of the project, schedule of the project and the expectations of the project. WJHW will begin design and target first week of December for final engineering documents. TE will release minutes in a follow up email. Contract will be bid to a local EC with a Audio Specialist assigned as a sub.

10/15/04 – TE will meet WJHW onsite on Tuesday for kickoff meeting. WJHW will be onsite late Monday afternoon. They have coordinated their time with Scott Simpson.

ThermalTech solicited consultant bids and wants to team with WHJW from Texas for this project.

Conference call on August 17 between Eric Brown, Bob Bedinghaus, Joe Feldkamp and Terry Cannon with WHJW was held to discuss itemized consultant cost and scope of consultant work on this project.

TE is awaiting a signed SOSS from the County.

The County is awaiting a one page report from WHJW outlining the added benefits of using WHJW on top of the Durrell report.

Project scheduled to be signed in August 04, Designed in Sept – Oct 04, Bid Nov 04, Awarded in Dec 04, Construction Jan 05.

PBS – Sound System Repair Project Read More »

PBS – Occupancy Redistribution Project

03/20/06 – Joe approved TEI’s cost on the ECO for Sound project. This project is officially complete and ready to be archived.

11/30/05 – After speaking with City Permit office they confirmed that TE did pay for these permits. TTC called Randy this morning and told him that these permits were paid for on 10/18/05. TTC is awaiting a call back to clear this up.

11/25/05 – Randy Campion called to inform TE that there is a remaining balance on these permits. TTC called the city to see what that cost was because TE has already paid for the new permits with a check. Once this is cleared up Randy will send new Certificates of Occupancy.

10/18/05 – All revisions have been accepted and approved by the City. New permits costs = $354.00. New occupancies have been set to 1021 (East Club) and 986 (West Club). According to Randy Campion once the permit is paid for, which TTC did today, the permit will close and information will be sent to Fire Dept. They will issue a new occupancy for private club events. to PBS.

09/28/05 – The City received all the information from Cole & Russell but need it properly inserted into the permit dwg sets. TTC will stop at the permit office and manually do this on Friday or earlier if possible.

09/20/05 – After the City sent the letter emailed by TTC to PBS yesterday requesting additional egress information, TTC talked to Cole & Russell about this information. C&R believes that they already have all that information collected from the sliding door project and will call Carl Graeber and discuss directly with him. They can get all that information to the City on Friday or early next week. TTC will check back with city and C&R about progress at that time. We believe the city will accept this and process the permit app immediately thereafter for final inspection.

09/08/05 – TTC contacted city. Permit should be reviewed by 09/13/05. TTC will check back at that time.

08/25/05 – The permit is still being reviewed by the City. TTC will continue to check on status.

0815/05 – TTC met Randy Campion at the PBS site on Monday, Randy approved the 821 and 851 increased occupant load and will sign the CO paperwork and send it to PBS. After the meeting, PBS said that the 30% OA was not a problem so that they want even higher occupant loads. TTC turned in another set of prints with the higher numbers of 986 and 1021. The city made us turn in for all new permits: 2005P06669 and 2005P06670.

07/18/05 – City called with Approved Permit numbers today. Permit was split up into 2 permits 2005P05544 AND 2005PO5589 ($284). TTC will pick-up permit on Tuesday morning. Inspector, Randy Campion has to come to the site to approve and give us a new CO for the space. This will be coordinate with HamCo & PBS in the next couple of weeks.

06/30/05 – TTC got GD to sign occupancy permit drawings in regards to HVAC OA requirements. TTC submitted for permit. Permit # 2005P05544. TTC informed all parties that permit can be checked at www.cincinnati-oh-gov at anytime. Amit was also promoted to Project Manager, so we are unclear if he will review this permit.

06/16/05 – Eric called today and TTC reported that Amit had returned one of his phone calls stating that he was seriously behind in permit reviews. With that knowledge, TTC stated that we should just go ahead and subject a revised CO application and talk to him them as opposed to conferencing in with him early.

06/06/05 – TTC sent an email outlining TE’s field findings to Joe, Sam and Eric. TE need direction from PBS to proceed on next level or work.

06/03/05 – Sam Boehringer of TE collected field data to update actual occupancies of the space.

05/25/05 – Eric Brown setup a meeting with the CFD department about occupancy requirements of the club level space.

PBS – Occupancy Redistribution Project Read More »

PBS – Deep Well Pump Replacement

03/23/06 – TTC spoke to John Wagner of Moody’s today and here is where the problem is: the actual repairs cost $15,573 not $6573, the 6573 +the 9000 already paid = the total cost of repairs on this job. This means that they are still giving you back $4427 on the job. John outlined this in a letter in September which I am having faxed to me. With this information, I will redo the paperwork and send it up to John for use on completing this project. I have to write a new change order, allowance usage and final pay application to make all the numbers work out right.

03/20/06 – TEI received final paperwork on this project today from Moody’s. This will be forwarded to Joe for payment on this project. TEI to begin phase II service contract immediately.

02/16/06 – Moody contacted TEI to request AIA forms. TTC sent them out in US mail for their use. They should complete these, notarize them and get them back for closeout.

02/06/06 – After an inquiry by Sam Kinman, TTC found the payapps sent to ThermalTech for approval. They were approved by Sam on 11/21/05. The problem is that they are not on AIA invoices which means there is no where for TTC approve. Assuming they are approved by TTC on these forms, the Contractor still has not turned in standard county documents for project closeout. TTC will forward a copy to Moody’s and ask for return of these documents. TTC completed a full packet of information required and mailed to Moody’s today via US Mail. TTC will follow up with a phone call today as well.

11/30/05 – Sam Kinman reported today in an email back to TTC that the deep well pump replacement job is complete. Since TE wasn’t used very much during construction, TTC assumes the punchlist is fine and no additional work needs to be done. TTC will archive the project from the database and closeout the project number. TE has never received a payment to approve, nor the final County paperwork to approve for that payment, nor manage any of the allowance monies. All this will need to be done before the project is closed out in the County’s books.

08/08/05 – TTC contacted the County about status of the Deep Well Pump Contracts. The previous entry does not state that the contracts were sent to PBS.

07/18/05 – Bid were opened. Moody was apparent low bidder at about $29,400. $20,000 in Alternates can be taken (ALT #1 and ALT #3). TE has contract written for $49,400 and will give 4 original copies to PBS for approval with Board. Bid PDF

07/05/05 – TTC worked on July 4 to get Addendum 2 complete and sent it out for distribution. PDF

06/27/05 – TE worked on Add01 and it will go out to the Contractors on 06/28/05. PDF

06/13/05 – TE sent out Project Manual for bidding. PDF

06/06/05 – Comments received from Sam and John Wagner of Moody in Dayton. TTC will update Project Manual and prepare for bidding ASAP. PBS talked about including a 3-year service contract on top of the bid. TE has done these in the past and can add this scope to the project if so directed by the County for bidding. This would be an engineering scope change to this project but it makes very good sense to include it now (12 hours x $80 = $960) and that includes the contract modifications for the Alternate bid to take optional years.

06/01/05 – Comment received from Joe and Eric. Nothing from Sam yet.

05/30/05 – TTC sent a project manual out for review over the weekend to PBS and County. Once comments are received, TE will distribute to public for bidding. All dates must still be coordinated with HamCo Purchasing.

05/26/05 – TTC contacted Moody’s for some specific questions about parts replacement. The Project Manual is built for front end. TTC needs to add dwgs and mechanical section. Bid Form needs to be modified for this job.

05/17/05 – The team had serious discussions about project schedule today. PBS re-iterated their concern about flooding. TE provided a timetable for construction that appeared not to be acceptable to PBS. TE had discussions with JF about project and will try to speed up project manual creation significantly to lessen risk. It is TE’s belief that County Purchasing has already decreed that this project does not meet Emergency Status.

PBS – Deep Well Pump Replacement Read More »

PBS – Pro Shop Metering Project

03/29/06 – TTC reviewed the billed KW and KWH to the PBS Pro Shop and the numbers looked good. The pro shop is using less than 1% of the total power consumed at the building.

KW KWH
February

50.91 21,863
January

34.91 28,950
December

79.91 25,448
November

59.28 16,077
October

72.30 14,661
September

63.67 16,528
August

53.30 4,166
02/01/06 – TTC check on the meters and to review monthly billings at the site. The meters appear to be reading in the Megawatts which seems really high at first glance. TTC to reconcile with actual building data.

11/16/05 – TA visited the site today. Reviewed punchlist and determined that Bond Electric has not completed the issues described on the punchlist. TE called Bond to tell that them that can’t get paid until these items and the final paperwork is complete.

11/15/05 – As-Built drawings for this job were turned over to Wayne Trent of HamCo Facilities today.

06/17/05 – Const Mtg was held at PBS. Sam did not attend. Equipment is not on site yet but Bond is ready to get to work as soon as it arrives.

02/28/05 – Purchasing called to inform TE that Bond does NOT have a performance bond or check submitted for this project. We should not let them begin work without this paperwork in place. TA to confer with Jack Boland today and emphasize the need for this check immediately.

02/10/05 – Contracts and Bid Results are in County’s hands. TE awaiting further direction on this project.

11/17/04 – Bid Results

10/12/04 – Project is out for bidding.

Addendum#1 distributed.

Addendum#2 distributed.

Addendum#3 distributed

PBS – Pro Shop Metering Project Read More »

PBS – Deep Well Pump Service Contract

02/02/07 – After many contract revisions, phone calls and problems, the Prosecutor finally allowed preventative only maintenance contract that Kerry wrote and gave back to everyone to use. Other repairs and emergency repairs must be bid our as prevailing wages. TEI does not and will not every agree with this approach. We took prices for many other services to save the County money but those were not accepted as part of this job by Hamco Prosecutors office.

01/10/07 – TTC got Kerry’s new email address and forwarded the revised contract to her for any final changes that she would like to make. Kerry confirmed that the packet was received at her office.

01/08/07 – TTC hand delivered the final contract with Kerry’s marks to security for Jenny and Joe to pick up and resubmit to the Prosecutor’s Office.

12/26/06 – TTC will finalize the deep well pump contract this week.

03/29/06 – TEI has not heard from Daktronics with a registered service repair list yet so I called and got Greg’s email and sent him the request again.

03/21/06 – TEI finished the SOSS and will drop it off at the HamCo Facility Department on Wednesday for this project.

PBS – Deep Well Pump Service Contract Read More »

PBS – Energy Study

03/20/07 – Project ready to archive.

11/30/05 – TTC and GD have to meet internally to review the 10/11/05 findings and energy usage. GD believes there can be savings found in schedules and space control but we will need “buy in” from facility department to implement. TTC has to setup meeting with GD to review other items but County end of year crunch on projects has dampened progress. All work will be done by end of year.

10/11/05 – TTC and GD met on site and reviewed the whole facility with Sam, Joe, Eric and the financial manager.

05/10/05 – Kickoff meeting for project with JF, TTC.

PBS – Energy Study Read More »

PBS – Video Wall Replacement Project

12/19/07 – Nor Comm has provided the AIA closeout paperwork, warranty letter and payapps. TTC signed and City Dashed it to Joe Feldkamp. This project is complete.

09/03/07 – TTC has received and approved the O&M’s. TTC is hand delivering the box of O&M’s and final payapp to PBS tomorrow at 9am at the Deep Well Pump prebid.

08/28/07 – TTC contacted Nor-Com again about final payment via email with a Read Receipt.

08/20/07 – Nor-Com contacted Joe today about final payment. TTC emailed Joe back station what happened to Payapp #2 as listed below. To date, we have not received any additional paperwork.

07/02/07 – TTC has contacted Howard Milkis and Nor-Com several times for closeout on this project. No response to TEI. TTC will try to contact the office directly today and find out how we are going to close out this project.

05/14/07 – PBS did not use TEI service much at all on site during this project. TEI has been in contact with Joe and Scott numerous times during construction as things were going well. TEI contacted owner today for punchlist and closeout items for Nor Comm. As far as TEI knows, this project is complete.

03/30/07 – TE received submittals for review and promised to work on them this week. Nor-Com has a schedule forthcoming.

03/16/07 – Scott and Joe held a kickoff meeting. TTC to follow up and publish some const mtg notes this week. A second Const Mtg is to be scheduled. PBS would like TV in before draft day.

02/13/07 – All contracts and information is in the Prosecutors office for review. Comments have been added and the contract should be approved very soon. TEI provided a copy of the bid results to Kerry Dowling per her request last week. Joe Feldkamp is following up with the Prosecutor Office.

01/30/07 – TEI finished the revised contract and returned it to PBS for use on this project. Now TEI is waiting for approval and signatures to move into a pre construction meeting.

01/10/07 – TTC hand delivered the contract based on the Base Bid cost to Joe for submission to the Prosecutor’s office. TTC included a $2500 allowance in the project after the bids were opened.

12/26/06 – TTC will finalize the deep well pump contract this week.

PBS – Video Wall Replacement Project Read More »

PBS Video Switcher

10/26/09 – Final paperwork is received. TTC approved and mailed to Joe.

09/22/09 – Project is complete. We have approved payapp #2. Once all the closeout paperwork has been received and training is complete. We can close out this project.

08/25/09 – One payapp has been approved. Punchlist has started. Training continues.

07/29/09 – Project has been bid and awarded to Rosco. Work is proceeding and Chris Williams will be able to check in on progress on August 4th when he visits Cincinnati for the Brewers game.

06/23/09 – This project is in contract approval stage at HamCo.

PBS Video Switcher Read More »

PBS Z-Ramp Replacement

09/14/09 – Additional documentation has been sent to Kerry for contract approval.

08/25/09 – Joe needs additional bid information for the project. United needs to provide final bid paperwork to Joe.

0729/09 – Project has been bid. Prices were tabulated and sent to bidders. Final contract was $16,300 and included $500 in allowance monies. TEI has written the contract and given to the County for signing.

06/23/09 – This project is out for small project bidding.

PBS Z-Ramp Replacement Read More »

JC – AHU Access Platform (N&S Gyms)

Partner Lead: THP

11/17/16 – Hamilton County requested SOSS.

01/09/17 – THP provided SOSS.

01/20/17 – Hamilton County approved SOSS.

02/22/17 – JC Platforms THP to meet with building operators in the afternoon for first design meeting.

03/10/17 – THP provided review drawings to the County.

04/19/17 – THP, Facilities staff, and Sheriff staff met to discuss final bid documents and construction/security requirements.

04/27/17 – Bid documents schedule to be published week of May 1st.

05/02/17 – Bid documents published.

05/08/17 – Prebid meeting occurred.

05/19/17 – No bid questions received for JC platforms.

05/22/17 – Addendum 01 for JC platforms (pre-bid mtg minutes only) issued.

05/25/17 – Bid opening schedule for June 1.

06/01/17 – JC bid opening. SSRG is low bidder at $66,170.00.

06/06/17 – THP recommends SSRG to county for JC platform job.

06/26/17 – JC Platforms waiting on SSRG to send in revised forms for contract completion with the county.

07/25/17 – J Nester requests additional contract information from SSRG. SSRG Answered yesterday. Waiting for county to finalize contract.

08/25/17 – SSRG to provide schedule. SSRG plans to visit the site to verify dimensions and complete beam scanning. The project team plans to have the pre-construction meeting with building personnel at time of visit.

09/21/17 – Pre-Construction Meeting onsite.

09/22/17 – Stamped set sent to SSRG for permit.

09/25/17 – Special inspections report sent to SSRG for permitting.

09/28/17 – Terracon scheduled (by SSRG) to scan beams for tendons.

09/26/17 – Steel shop drawings submitted. THP in coordination with fabricator.

10/18/17 – Permit drawing changes sent to HGC. Waiting on news of permit status

10/19/17 – Second round of steel shop drawings submitted and comments returned.

10/20/17 – THP Discussed shop drawings with HGC. Attempted to reach Neiheisel on behalf of HGC. No answer.

11/22/17 – HGC completed installation of frames and demobilized. THP visit the site and published field report.

11/29/17 – THP plans to review final installation with HGC.

JC – AHU Access Platform (N&S Gyms) Read More »

JC – 3rd Floor Handwashing Sink

12/29/16 – TTC sent options into County on this sink, location and plumbing. We are awaiting additional direction from owner.
01/26/17 – Bert said that estimate was sent to Kevin Horn for approval on this job to become a project. This could get started next month.
03/09/17 – No updates, on hold for now.
04//26/16 – No updates to project.
06/19/17 – SOSS approved and TEI to meeting with County on kicking off this project.
07/24/17- Drawings are issued for Review tomorrow. TEI requested Permit cost form QCM.
08/30/17 – QCM has submitted permit drawings for the sink. We are awaiting the permit # to share with the County.
09/25/17 – ThermalTech has picked up permit drawings and permit and sent to John Nester for owner use. A hard copy set of dwgs was delivered to the owner last week with equipment selections. TEI stands ready to assist as needed during construction.
10/24/17 – Permit is issued and work should be underway. TEI stated that HCDF can purchase an equal sink from a local vendor for this work and that should be fine.
11/28/17 – County has started the project. DK has been contacted for coredrilling.
11/30/17 – Work has begun on this work and the pilot holes have been drilled.
02/22/18 – Project complete and ready to archive.

JC – 3rd Floor Handwashing Sink Read More »

JC – 3rd Floor Recovery Unit Study

07/25/17 – GBBN meets with Facilities, and the Sheriff’s Department, to discuss scope and walk through spaces to be considered for this project. The 3rd Floor North, 3rd Floor South and the Courthouse 7th Floor East are to be considered as potential locations for the Recovery Unit in the Study.
08/11/17 – THP issued SOSS for structural and building envelope support services for review of new windows in recovery unit study.
08/12/17 – GBBN authors and delivers SOSS to Facilities.
08/28/17 – Approved SOSS delivered to GBBN.
09/22/17 – GBBN and Facilities meet with Sheriff’s Department to discuss Study in greater detail. GBBN issues Meeting Meetings and sends to Facilities. Facilities confirms accuracy of Meeting Minutes and approves them for circulation to TEI. THP contacts GBBN to confirm THP was original structural engineer for the JCC project and has original drawing set.
09/25/17 – GBBN send meeting notes and follow up plumbing and HVAC design inquiries to ThermalTech.
09/25/17 – THP communicates knowledge of existing building structure and floor slab construction to GBBN. GBBN circulates structural and proposed restroom block concept design to TEI.
09/25/17 – GBBN sent and email to THP concerning JCC structural conditions and possible modifications requested by the County. THP responded the same day.

10/19/17 – GBBN finishes Architectural estimating input into Archibus Project Request module.

10/26/17 – GBBN and Facilities to meet with Sheriff’s Committee to review plan layout options.

10/31/17 – GBBN attends walk-through meeting with Sheriff’s Committee. Existing spaces in JCC Third Floor and Courthouse JAX spaces on 6th floor are reviewed and photographed.

11/10/17 – Archibus Project Requests input is completed by TEI and GBBN for both options.

JC – 3rd Floor Recovery Unit Study Read More »

COURTHOUSE Roof Y and Z Leak Investigation

Partner Lead: THP


05/05/17 – Hamilton County requested SOSS to investigate roof leaks on the Y and Z roofs along the west elevation.

05/25/17 – THP developing SOSS.

06/08/17 – THP issued SOSS for review.

06/26/17 – County approved SOSS.

07/27/17 – THP plans to schedule work second week of August.

08/25/17 – THP visited site to do visual survey of roofs Y & Z, and interior of 6t and 7th floor spaces below roofs.

08/25/17 – THP visited site to do visual survey of roofs Y & Z, and interior of 6th and 7th floor spaces below roofs.

09/28/17 – Based on weather forecast, THP planning on conducting thermal scans October 3rd.

10/03/17 – THP documented roofs Y & Z using infrared camera.

10/06/17 – THP met Underground Detective to inspect all drains at roofs Y & Z.

10/25/17 – Roof cuts scheduled, weather permitting.

10/26/17 – THP visited site to perform investigative roof cuts.

11/28/17 – THP finalized draft of report summarizing findings and recommendations.

COURTHOUSE Roof Y and Z Leak Investigation Read More »

COURTHOUSE Roof 10 Repair

Partner Lead: THP

06/11/15 – County requested SOSS.

06/13/15 – THP and County visited the roof.

06/25/24 – THP anticipates issuing the SOSS.

07/17/15 – County Facilities, THP, TTE and Chambers Control met to discuss phasing the project and completing the work.

07/30/15 – Due to the different scope of work, THP split Court House roof project into Roof 10 (repair/replacement) and Roof T (warranty extension) for tracking purposes.

08/01/15 – THP anticipates issuing an SOSS to the County.

08/03/15 – THP issued SOSS to County.

08/07/15 – County approved SOSS.

08/26/15 – Project update: THP developing design documents.

09/24/15 – Project update: THP developing design documents.

10/29/15 – THP completed roof scan, roof cuts and field measurement. Design development documents anticipated to be released 11/2/15.

12/09/15 – THP working on bid documents with update roof configuration from field findings.

01/28/16 – THP working on bid documents

02/25/16 – THP confirmed plumbing routing and delivered update plumbing drawings for review by the County.

03/21/16 – Prebid meeting conducted.

03/28/16 – Addendum no.1 issued.

03/31/16 – Last day for contractors to submit questions.

04/04/16 – Last addendum will be issued.

04/12/16 – Two bids were submitted with both Contractors within the project budget. Imbus Roofing was the apparent low bidder.

04/13/16 – THP completed a cursory reviewed of Imbus’ bid and recommend the County accept all alternates.

04/14/16 – THP issued draft AIA contract for County review.

05/20/16 – County issued PO and Contract to Imbus Roofing.

05/26/16 – Imbus working through background checks and project planning.

07/22/16 – THP contacted Imbus regarding submittals. Ed with Imbus stated he would gather submittals and send to THP.

08/05/16 – Preconstruction meeting completed.

08/25/16 – Imbus in the process of mobilizing.

09/28/16 – Imbus has roof 10 completely removed and the temporary roof installed. Have had some leakage issues, but otherwise turning water. THP provided pipe post support detail to Imbus for pricing. Imbus initially submitted $524 per pipe and revised to $400 per pipe installed. County authorized to proceed with fabrication and installation. Imbus started tear-off and temporary roof installation last night on roof 6. American Façade plans to begin sealant work on cornice adjacent to roof 10 and along north and south walls of law library tomorrow. Imbus and THP meeting tomorrow to review pipe penetration near RTU in southwest corner of roof 10.

01/26/17 – Project update: Roof 10 – complete , Roof 6 – complete except downspout installation, Roof 5 – last phase of layup this week. Flashings, cap flashings, and terminations still to do. Stainless steel trough at Roof 10, painting roof hatch at Roof 5, and HVAC duct replacement at Roof 5 still left as well. Change order for securing electric lines on outside of parapet at Roof 5 being developed. This work is outside our scope, but Imbus subcontractor has provided cost for work. Imbus plans to turn parking in courtyard back to county this week. Hoist and scaffolding was to come down over the weekend. Bert asked THP to look at stained glass windows and protection from winter ice or snow.

02/22/17 – Roof 5, 6, and 10 generally installed. Imbus working on final detailing and flashing conditions

03/23/17 – Project update: Roof membrane installation complete. Imbus has several items to finish prior to reaching substantial completion.

03/23/17 Roof 6 and 10 need punch list developed.

03/23/17 Roof 5 has the following efforts to complete: Reconnect HVAC units, including running new conduit/power on parapet wall. Duct work (elbows) need replaced. Terminations and flashings need to be complete below the duct work. New posts need to be cleaned and painted. New posts need sealant to prevent water from being harbored on top of the cap plate. Prepare and paint the roof hatch. Repair junction boxes. Complete the termination of roof membrane at stained glass window. Repair the CMU block at steel stair landing tie-in at wall. Finish target at roof drain on north side of Roof 5. Fix the walk mats that are not lying flat. Change order work – replace displaced electrical conduits. Finish counterflashing installation.

04/27/17 – Imbus finalizing punch list. Work anticipated to be finished week of May 1st.

05/18/17 – THP issued final punch list.

05/25/17 – Imbus working on punch list.

07/26/17 – THP to complete review of final punch list.

08/28/17 – Final punch list repairs were reported to be completed Friday 8/25. THP to complete final review 8/31.

09/27/17 – THP to complete final review of final punch list.

10/20/17 – THP publish updated punch list.

10/24/17 – Imbus and County walked the roof to review the punch list.

11/30/17- Imbus completed all punch list items. County is waiting on final prevailing wage from contractor.

COURTHOUSE Roof 10 Repair Read More »

PBS – Deep Well Pump Service Contract

02/02/07 – After many contract revisions, phone calls and problems, the Prosecutor finally allowed preventative only maintenance contract that Kerry wrote and gave back to everyone to use. Other repairs and emergency repairs must be bid our as prevailing wages. TEI does not and will not every agree with this approach. We took prices for many other services to save the County money but those were not accepted as part of this job by Hamco Prosecutors office.

01/10/07 – TTC got Kerry’s new email address and forwarded the revised contract to her for any final changes that she would like to make. Kerry confirmed that the packet was received at her office.

01/08/07 – TTC hand delivered the final contract with Kerry’s marks to security for Jenny and Joe to pick up and resubmit to the Prosecutor’s Office.

12/26/06 – TTC will finalize the deep well pump contract this week.

03/29/06 – TEI has not heard from Daktronics with a registered service repair list yet so I called and got Greg’s email and sent him the request again.

03/21/06 – TEI finished the SOSS and will drop it off at the HamCo Facility Department on Wednesday for this project.

PBS – Deep Well Pump Service Contract Read More »

PBS Video Switcher

10/26/09 – Final paperwork is received. TTC approved and mailed to Joe.

09/22/09 – Project is complete. We have approved payapp #2. Once all the closeout paperwork has been received and training is complete. We can close out this project.

08/25/09 – One payapp has been approved. Punchlist has started. Training continues.

07/29/09 – Project has been bid and awarded to Rosco. Work is proceeding and Chris Williams will be able to check in on progress on August 4th when he visits Cincinnati for the Brewers game.

06/23/09 – This project is in contract approval stage at HamCo.

PBS Video Switcher Read More »

PBS Z-Ramp Replacement

09/14/09 – Additional documentation has been sent to Kerry for contract approval.

08/25/09 – Joe needs additional bid information for the project. United needs to provide final bid paperwork to Joe.

0729/09 – Project has been bid. Prices were tabulated and sent to bidders. Final contract was $16,300 and included $500 in allowance monies. TEI has written the contract and given to the County for signing.

06/23/09 – This project is out for small project bidding.

PBS Z-Ramp Replacement Read More »

Parkhaus Garage Assessment

September 7, 2011 THP sent assessment report to County

THP anticipates completing the report by August 5.

July 25, 2011 THP completed all field survey.

Assessment placed on hold until Ram completes stair tower work.

THP anticipates field work in next two weeks and report to be complete by June 30.

April 26, 2011 SOSS approved.

County reviewing SOSS.

April 18, 2011 THP provided requested SOSS to complete garage assessment for the Parkha

Parkhaus Garage Assessment Read More »

Northside MR/DD Masonry Review

THP closed out project.

October 29, 2010 THP provided a summary letter of masonry work.

THP anticipates publishing a letter to GBBN documenting field condition on October 29, 2010.

October 14, 2010 THP notified GBBN that lintel repairs were not recommend and THP will follow-up with a letter documenting the field visit.

September 29, 2010 the County, GBBN and THP met to review the lintel condition of the west wall of the Northside MR/DD facility.

Northside MR/DD Masonry Review Read More »

DDS-Beckman Adult Center Change of Use Remediation Project

5/17/10- GBBN received final Structural Analysis for Beckman Change of Use Code Review.

5/25/10- Arcodect delivered final Code Review for implementation into Permit Set of Construction Documents.

5/26/10- Final Permit Set of Construction Documents printed, signed and stamped. Set to be hand delivered to TEI at the Partnering Meeting for issuance to the Hamilton County Planning Department.

6/4/10- Issuance of ITB#047-10 by Hamilton County Purchasing Department.

6/14/10- Attend Pre-bid Meeting at Beckman Adult Center.

6/15/10- Issuance of Addenda #1 with Pre-bid meeting minutes.

6/23/10- Bid question sent directly to GBBN. Bidder instructed to send question to Purchasing per the bidding documents.

7/1/10- Building Department Response Letter received from TEI with two items concerning occupany separations. Building Department requesting drawing showing Use Group separations, net/gross areas and occupancy locations on floor plan.

7/02/10- Responses for Building Department Response Letter received from Wayne Meyer at Arcodect.

7/19/10- Newly created Occupancy Summary Drawings for Building Department Response Letter delivered to TEI.

9/15/10- Construction meeting was held.

9/27/10- TEI announced the Plans Examination was completed and approved for Building Permit by Hamilton County.

1/27/11- TEI and Kevin Maue confirmed the permit is now closed on this project. The Certificate of Occupancy and the Colerain Township Fire Department Letter of Release have been obtained.

1/27/11- Kevin Maue indicated at the Partnering meeting this project can be archived.

DDS-Beckman Adult Center Change of Use Remediation Project Read More »

DDS-Beckman Adult Center Change of Use Code Investigation

3/19/10-Met with Jim Bowman, Colerain Fire Department, and Kevin Maue at Beckman Adult Center for walk-through on current renovation project.

3/20/10-Kevin Maue requested SOSS be submitted. This is first of two SOSS’s for this overall project.

3/21/10-Preliminary Code Investigation performed and submitted to Kevin Maue by email.

3/23/01-Fee proposal from Arcodect (code consultant) received. GBBN spoke to Cindy Rutherford, Hamilton County Building Department to discuss Change of Use requirements and submissions.

3/31/10-Schedule of submissions to Hamilton County Building Department submitted by email to Kevin Maue.

4/1/10-SOSS to be revised and re-submitted showing THP as a structural consultant to GBBN for any seismic implications per directions of Kevin Maue at Partnering Meeting.

4/7/10- GBBN met with Kevin maue, Terry Cannon (TEI) and Tom Frimming of Communale Fire Protection to review proposed AFSS implementation.

4/14/10- Signed SOSS without Ralph Linne’s signature and approval delivered by Kevin Maue to GBBN.

4/27/10- Signed SOSS with Ralph Linne’s signature and approval delivered by Bert Watts via email to GBBN.

4/27/10- Bryan Korb of GBBN assigned to project. Bryan to meet with Wayne Meyer code consultant at Beckman on Thursday and Friday for site investigation

4/29/10- GBBN to meet with owner, Colerain Fire Department, and Hamilton County Building Department to review building and change of use scope.

5/12/10- Kevin Maue announced ThermalTech Engineering would be the lead design professional on this project and GBBN would be the consultant. GBBN established estimated hours for completion to TEI for SOSS.

DDS-Beckman Adult Center Change of Use Code Investigation Read More »

DDS Signage Refacing

10/01/09 – Kevin Maue of MR/DD contacted GBBN about the pending name change as mandated by the State of Ohio. Sign letters on 1520 Madison to be removed as part of ceremony and will be handled as a purchase order. The signage refacing of all other sites will be on a SOSS through the Partnership contract.

10/05/09- ASI Modulex was approved to handle the purchase order work for 1520 Madison based on a submitted quote to MR/DD.

10/07/09-Existing electronic drawings sent to ASI for signage permit with City of Cincinnati.

10/23/09- Shop drawings for 1520 Madison approved for layout and lettering style.

10/30/09- Signage Refacing RFP sent to four selected bidders.

11/24/09- Adams Signs was selected for Signage Refacing and P.O. 536683 released.

12/08/09-1520 Madison sign permit approved. ASI
to order building sign letters.

1/04/10-Adams Signs re-submittal shop drawings approved.

2/19/10-Adams Signs has completed all installations. Kemper Meadow Road sign has bleed through of old signage.

2/22/10-Email sent to Rick Cain of Adams Signs about corrective measures at Kemper Meadow Road location.

2/25/10-Received signed SOSS from Bert Watts at monthly partnering meeting.

3/15/10-Resent email to Rick Cain with photos of Kemper Meadow. Rick claimed the corrections would be completed soon.

4/3/10- Email sent to Rick Cain of Adams Signs about corrective measures at Kemper Meadow Road location.

4/10/10- Rick Cain called to indicate Adams Signs very busy but will try and expedite completion of remediation measures to Meadow Road location.

5/19/10- Kevin Maue sent an email to Adams Signs indicating Application for Payment non-payment until corrective work is accomplished at Meadow Road location.

6/18/10- Notified Adams Signs to submit warranty information to comply with close-out documentation.

6/23/10- Sent Invoice from Adams Signs to Kevin Maue.

6/24/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

6/29/10- Rick Cain called to indicated work is commencing to author standard warranty details.

7/28/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

7/30/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

8/24/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

9/27/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

10/25/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

11/25/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

12/14/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment. Rick Cains email was returned as undeliverable.

DDS Signage Refacing Read More »

MRDD – THOMAS KIDD CLASSROOM ADDITION

02/14/08 – Punch list submitted.

02/13/08 – CRA sent additional service signed 2/13/08 to Bert

02/13/08 – TEI attended the const mtg today for MRDD. EDI is almost complete. Additional concrete will be installed around the new air handlers.

12/07/07 – CRA job meeting held on 12/05/07

11/14/07 – CRA received and approved shop drawings and substitution request for automatic door operators.

11/10/07 – The construction has commenced.

11/01/07 – Pre-construction meeting was held. See Meeting Minutes below.

10/26/07 – GC/EC submitted revised insurance certificate. GC/EC contracts have been approved approved. HVAC contract is still pending.

09/28/07 – Awaiting GC/EC to submit revised insurance certificate for final executed Contract.

08/16/07 – Contracts submitted 07/31, CRA received comments, re-issued 08/16.

08/02/07 – C+RA and TE submitted the Building Permit Application to the Village of Evendale Building Department.

06/25/07 – Addendum issued. Bids are due 07/02/07.

06/15/07 – A pre-bid meeting was held on location yesterday, June 14, 2007. This project is set to open for bid on June 26, 2007.

06/08/07 – This project has been sent to Cole & Russell for review. TE is awaiting comments back.

04/27/04 – Final review meeting is scheduled for next week.

04/20/07 – Updated drawings are being sent out today, April 20 2007.

04/13/07 – Project is progressing as expected.

04/06/07 – Preliminary set of drawings were sent to Architect today, April 6, 2007. Awaiting review comments.

03/30/07 – Final field work has been assessed. TE working on design.

03/23/07 – Project is progressing as expected.

03/20/07 – Kickoff meeting complete. Check CRA for updates.

MRDD – THOMAS KIDD CLASSROOM ADDITION Read More »

MRDD – JACKSON CENTER RENOVATION

02/15/08 – Add service CR-077a for $6,755.00 signed by MRDD on 2/12/08, forwarded to Bert Watts.

01/16/08 – Mtg held re additional service request my MRDD.

01/17/08 – Meeting held at site for scope definition. TJ and MAH attended. A few deletions and additions from original scope. ZZ ran meeting and will produce meeting notes. TJ and MAH will produce notes and forward to ZZ.

12/20/07 – Add service requested by MT

12/07/07 – CRA Told by MT that project will be from 2008 budget.

10/10/07 – Received signed SOSS.

09/06/07 – SOSS submitted.

05/18/07 – Kickoff meeting was held.

MRDD – JACKSON CENTER RENOVATION Read More »

MRDD – Franks Center Renovations

03/31/08 – Bids due 4/11/08

03/31/08 – Pre-bid meeting

03/21/08 – Addendum 1 issued

03/08/08 – Issued for bid

02/15/08 – CRA Add Service CR-084a $6,999.00 signed by MRDD on 2/12/08, forwarded to Bert Watts.

01/11/08 – SOCC CR-084a modified per WM email 1/11/08

12/20/07 – CRA add service requested by MT 12/20/07

11/09/07 – SD review meeting was held at Franks Adult Center. CRA presented Schematic Design drawings and color and finishes samples.

11/02/07 – Next review meeting is scheduled for 11/08/07 at Franks Adult Center at 3pm.

10/24/07 – Meeting was held at Franks Adult Center to discuss the scope of the project and verify existing conditions.

09/24/07 – CRA received signed and approved SOSS.

08/30/07 – CRA submitted the SOSS.

MRDD – Franks Center Renovations Read More »

MRDD – 1520 MADISON RD RENOVATION

08/29/08 – Triton is still working on warranty issues. Boiler control boards. Humidity issues. RCP problems.

02/25/08 – Triton and JCI have been working to remedy the remaining warranty issues on this project which include boiler flame outs, VAV box control, min airflows through VAV boxes, winter heating. TEI has to look at cold restrooms in the 1956 building for Kevin Maue.

12/17/07 – JCI and Triton had to go back to the site today to continue to work on DDC issues since the RTU-2 is still not running properly. Triton put the unit in had on Friday at 40%. TEI does not have an update on Monday from the troubleshooting field trip.

12/14/07 – TTC was on site today with JCI and Carrier going over warranty issues on the job including the LON talk interface between RTU-2 and DDC. Scott fixed the misnomers on the RTU-1 unit in the points list. Scott fixed the economizer program so RTU-1 would actually run in economizer mode when conditions were right (there was a programming glitch in the system) and he addressed the setback temperatures which are correct as programmed. Training will be schedule the second week of January 2008 with MRDD. There was a cold call in the lobby today from Wayne Mckee and Triton and JCI was dispatched to investigate the problems with the space. The hot water is 156F so there should be plenty of hot water available for the system.

12/04/07 – CDFP is scheduled the FM200 training directly with the MRDD folks and they will keep TTC in the loop. CDFP sent a change order in today for additional services on this project that TTC forwarded to ZZ for approval on this project for the extra sprinkler work, additional fan test.

11/28/07 – Jim Lape emailed to ask about closeout on this job. TEI stated that TJ should be 100% complete on this project. Triton is also done but we don’t have final closeout documents from them on this job. TTC is trying to get Grady to give us all closeout docs for this job.

10/17/07 – TTC visited the site and produced some more items for JCI and Triton to take care of on this job. He emailed pics and instructions to the contractors for completion. Everyone is working on completing all the work this week. Triton says the final balance reports are complete. TTC said today that he would adjust the manual high limit controllers to 210F and let the factory 190F shut the boilers down on auto reset. TTC also said he would caulk up the hole in the concrete hatch patch while he was on site. TTC will also check the installation of the electric heaters in the stairwell today while he is on site.

10/08/07 – TTC answered Jim Lape’s email about door control hardware. On drawing E400 #12 & #13 state that TJ will wire up the devices furnished & installed by the GC.

10/01/07 – TTC was on site last week performing commissioning. The control system was not ready to be back checked by TEI. JCI had not performed the functional test and TTC did not have the CX sheets. Nevertheless the system is running and with another week of actual work, it will be fine. TTC requested trend reports for verification of working systems.

09/19/07 – TTC approved JMW change order for roof drain and sent email to Jim, Zach and Kevin to that effect. TTC reviewed Triton invoice and asked for change order modifications before actual billing to the County. Change Orders were not reflected on actual payapp but they were on the schedule of values.

09/17/07 – Discussed Change Orders # 09,10,11 with Tim and Kevin Maue. I approved them as submitted. The steel issue is still are large issue that doesn’t appear close to resolution. TTC responded by email about controlling the pressure of the system by setting the static residual to 5 psig and letting the building set the pressure from there. If we have to change the relief valves to 65 psig from there, we can. The static of the building on the basement pumps should be 26.64 psig (50 ft bldg ht / .4328 ft h20/ psi + 5 psig to keep air out).

09/12/07 – Triton is on site checking the existing VAV boxes for repairs. They found one bad damper and believe 6 of the 7 boxes that are not operating properly. We are concerned that we have paid for some of this work already at the beginning of the job, but we will pay for the repairs to the dampers now and fix the electric heaters.

09/04/07 – JCI has given training but the controls are not complete and they still need some work. Boiler are not operational at this time and Denny Lammers is still need to program the internals of the boilers so JCI can communicate and give them their firings rates and monitor alarms. TTC dropped off TJ Williams hard copy as-builts drawings for the project that need to be included into the O&M’s that Kevin already has in his office.

08/23/07 – TEI printed out 2 more originals for Change Order #1, signed them, and sent them to T.J. Williams with instruction to sign them and forward them to HCFD.

08/17/07 – TEI received as-built drawings from TJ. Williams today. TEI will update the electronic drawings with the information and forward them back to CRA early next week. TTC delivered the O&M’s for EC, PC and FPC to Jim Lape at his office today.

08/16/07 – TTC and Cintas performed and passed the final server room fire alarm test on Wednesday. TTC has the paperwork in the folder and will include in the O&M. Triton said that the handrail was ordered and will be put back by Pat Murphy.

08/06/07 – TJ will do the security camera and emergency lighting change order work at T&M not to exceed but they will not come down in price. TTC sent this info to Jim Lape and approved on his end. TEI needs direction from the owner. TTC contacted MRDD about installing gaskets behind wall plates in server room.

08/02/07 – TTC talked to Kevin today about TJ outstanding issues at the MRDD. Security Camera change order and Emergency Lighting change order. JMW has O&M’s into TEI and they all closeout paperwork into Kevin Maue. TEI received TJ Williams closeout paperwork on this project as well. NV had TTC give to it to NR for approval.

07/23/07 – TTC spoke to Tim Myers today about project closeout, change orders, punchlist and controls. TTC discussed the allowance usage with Tim which totaled $13459 to date not including the refrigerant changeout which is a different cost. TTC emailed CRA about distributing the correct paperwork for change order pricing from Triton on this job and listed 6 items that need to be priced for this project.

1. Extra Diffuser for 1956 building. 17 in Qty. Linear Slots and 2×2’s to meet job requirements.
2. Refrigerant Check, Removal, Replacement on RTU-1. This work wasn’t included in the allowance cost but we authorized Triton to do the work on a separate ticket.
3. Overtime for IT closets and occupation over one weekend (i believe KM authorized triton to do this work)
4. Replacement cost for handrail? Triton removed it but someone else threw it in the garbage. Hobert is supposedly looking for it today but Triton will have to replace it if it can’t be found.
5. Demolition of all housekeeping pads in boiler room. This was Empire work but Triton had to do it all because Empire refused to do it. If Triton is going to pay the steel cost as a change order to Empire which I now believe they will after speaking with Tim Myers this morning, Empire either has to reimburse them this cost or deduct from the steel change order cost. Tim brought up a good point. A $2029 redesign fee is steep. That is 20 hours of a ThermalTech Principal time or 40 hours of a contractors time. It did not take that long. Redrawing that steel took about 6 to 8 hours. That fee should from the sub-contractor $500-$700. Please try to get them to give us a “real” cost and the housekeeping pad back charge could go away. As a side note, the new designed decreased the amount of steel and grating required, why are they paying an upcharge of $2522.97?
6. Replacement of 2 electric heaters. Provide 2 recessed ceiling heaters in the 1956 stairwell in lieu of the scheduled heaters. Return the surface mounted fin heater and the wall heater.
07/17/07 – TTC has scheduled a backcheck of the plumbing punchlist on Thursday. He will meet Jason on site for the walk through. Triton has committed to Approved Products being on site to finish the balance portion of the work starting on 07/23. TTC sent 2 sketches to CRA for plumbing ASI’s.

07/03/07 – The job is mostly complete aside from outstanding issues. The MRDD people are in and using the building. Items that we are still working on include: balancing HVAC & water, relocating a fp line out of the elevator shaft, final test of FM200, hot water boiler loop, controls, roof drain near unit, and punchlist by all contractors.

06/26/07 – All TEI punchlist were generated last Friday. TEI gave Jim Lape a complete set of extra materials required on this project to included in substantial completion for the project. TTC was onsite with JMW plumbing early Monday morning to discuss punchlist items which they are addressing. TTC spoke with Kevin about roof drain issue on 1956 building and we agreed that changing the scupper might be the best option. We can drain it down to the canopy roof.

06/15/07 – TE will be generating a punch list next week.

06/07/07 – RTU is still surging. we are trying to find out the status of the jci & carrier contractors. JMW plumbing will be on site on Friday to demo the 4″ plumbing vent from the elevator room. we believe fire protection is complete and ready for testing.

06/04/07 – Inspections are scheduled for Tuesday 06/05. MRDD personnel are moving equipment into the building today. ttc did not approve payapp #6 for triton and asked them to back down the % on the ground floor of the 1956 bldg to 90% and controls down a bit lower.

05/30/07 – TEI was on site on Tuesday for our weekly walk through. TEI contacted the vendors with questions, TCO milestones and coordination issues at the MRDD to help get it ready for the MRDD move on June 4. Items include ceiling layout, diffuser locations, ductwork insulation, EF flashing, fire protection work, elevator details, sump work, controls, etc.

05/21/07 – Triton reported that all fire dampers were completed over the weekend and that mason would be finishing up wall penetrations today and tomorrow. Kevin Maue seemed unimpressed with the quality of the work being done over the weekend and hopes they pass inspection. Tim, Terry and Kevin will walk the site on Tuesday AM to check progress and get commitments for completion.

05/17/07 – Triton will not be working this weekend but will have another crew on the MRDD job starting on Monday and they will have masonry sub helping with the patching of the duct shaft. The new RTU will not be ready to be ran this weekend.

05/14/07 – A lot has happened since my last entry. We have attended weekly const mtgs. We have attended several additional field trips for construction issues. The 1992 building has reached occupancy. The 2nd floor move was today. The 1992 RTU-1 unit is up and running but not under full control. The FM200 system is not fully tested yet even though the room is built. The 1956 building has ceiling grid in the entire building and now diffusers and fire protection piping is being installed.

04/17/07 – TTC and TA walked the project with all the contractors in lieu of a const mtg. The RTU is on the roof. The Server room is nearly complete. Cintas is working to complete the testing procedure and set it up for us. Shaft wall is offset form fire dampers. TE approved shifting the wall over to catch the sleeve of the fire dampers. The wall holes in the return shaft are open and Triton asked about filling them in (even the ones that weren’t done by them). TE directed Triton that they could sleeve the chimney with the boiler vents. The elevator room exhaust fan will reuse one of the openings that goes up to the chimney. A gooseneck may have to be added to the top of the chimney to keep the exhaust 10ft away from our unit intake.

04/13/07 – Project progressing as expected.

04/06/07 – Project progressing as expected.

03/30/07 – Project progressing as expected. Triton reported that the Liebert unit can’t be started today because of a breaker size issue (req 40A we have a 20A spec’d). TA resolved with TJ and Triton will have startup technician for unit after power is provided. TE received submittals today from JCI and GD has been looking them over all day. KM & TTC emailed Triton with acceptance on the retro-commissioning items on RTU-1.

Replace the Supply Fan Motor $3566.00 – APPROVED

Replace two bad compressor contactors $408.00 – APPROVED

Repair static pressure control for exhaust $2720.00 – APPROVED

Replace one bad condenser fan motor $1149.00 – APPROVED OR REPLACE WITH ALL 6 DEPENDING ON PRICE TBD

Perform leak check of Ref system, repair and replace refrigerant as needed $2339.00 – HOLD

Cleaning of coils and inside if unit including combing of coils as needed $1633.00 – APPROVED

Repair of Inlet Guide Vane and controls $3931.00 or replace same with VFD control $5108.00. – APPROVED BASED ON AVAILABILITY OF PARTS

03/23/07 – Lobby lights are on order and all issues with this item have been resolved. 480V electrical service has been changed over by Duke Energy, has been inspected and is up and running. 240V service to be removed the last week of March 07, tentatively.

03/20/07 – 02/19/07 – Last week the structural steel modifications began for the Carrier unit changes. Triton provided a dwg to SSA and CRA showing the new steel dims. SSA is sending back a proposal. The return duct shaft is open and must be sealed to provide proper airflow back into the unit. CRA is checking on some mold issues in that shaft from a roof leak. The FPC dwgs have been submitted to the city. The new FM is located and routed through an existing coredrills in the connector. TA release approval on change orders for TJ Williams for emergency lighting battery packs and dishwasher power in the 1992 building. Triton is still behind on the VAV boxes for the 1992 building and will have to work with Empire for ceiling pad out.

02/09/07 – TTC walked the site last Tuesday to check on progress. MEP is moving forward okay. Duct chase holes have not been cut yet. Triton is installing ductwork on the 1992 building

01/17/07 – Triton has coordinated with Empire on existing work. Kevin is worried that we don’t have enough written documentation that we told Triton to get this work coordinated and scheduled with the owner

01/15/07 – Somehow this job has not been tracked. Here’s the catch up data. The MC is Triton, the EC is TJ Williams, the PC JMW plumbing. We have had several job meetings. Triton has been poorly represented at these meetings. Last week after missing a rescheduled job meeting, Triton came on board with some initiative in catching up to the rest of the contractors. Triton has added more people to the job and is beginning new HVAC in the 92 building. Triton has demolished two floors of work in the 56 building. Triton has 2 men finishing the demo of the multi-zone unit and boilers in the basement of the 56 building. Triton has submitted an RFI questions who is cutting the holes in the shaft floor for his ductwork. TTC responded the GC and this was confirmed by CRA. The RFI was replied to but Empire responded they did not agree. The work is shown on the Demo and Arch dwgs for the GC and the summary of work says superstructure work is by the GC. The CWW has denied the underground permit and tap because the CGE pit is in the Right of Way of the street. TEI has negotiated with them and Cin-Day Fire Protection to provide the new line inside the building through the connector and throughout the building. This should save money and remove trenching and such in the yard. Kevin Maue has agreed that he likes this approach.

09/14/06 – Weekly design meetings continue. We reviewed cost estimates with the client and architect. Final estimates and drawings are due on September 25th for review and bidding is scheduled shortly thereafter.

MRDD – 1520 MADISON RD RENOVATION Read More »

MRDD Jackson Center Renovation

07/28/09 – Peck dropped off O&M’s today for this project. TEi will review them and give them to kevin for Closeout.

06/23/09 – This project is complete. I am not sure if Kevin has received all his closeout documents, please check and confirm at monthly meeting.

05/22/09 – We are closing out the project with TJ Williams next week. All work is complete and we are down to closeout documents. the Substantial completion for this project is Feb 20, 2009.

04/15/09 – CR Architecture + Design awaiting final punchlist items to be completed and closeout documents.

04/10/09 – Back punchlist issued.

03/09/09 – TTC sent out punchlist for Mechanical, Electrical and Plumbing and finalized Allowance & Change Order Payments with the punchlist so the contractors had everything they needed to close out the project.

02/19/09 – Project was punchlisted yesterday. Punchlist due at the end of the week.

02/02/09 – TTC continues to attend const mtgs for TEI. TTC drafted a letter to TJ Williams outlining the problems with the licensed door operator. The letter states that TJ Williams is responsible for hiring the licensed sub-contractor per the drawings and specs. We are however going to try to minimize the cost to TJ of this extra work that we believe they did not have in their original bid.

12/23/08 – Const Mtg 9 shows we are ahead of scheduled. TEI needs to address the sink in room 47, the trench drain, the curve sink is on site, the junction boxes need to be t&m by tj.

11/24/08 – Phase II is complete. TEI must do a Phase II punchlist. Peck requested a sheave change on HV-1 to get new airflow. TEI approved and sent to Kevin. TEI completed new allowance change orders for TJ Williams and sent them to John Parfitt for approval. TJ Williams revised payapp was received.

10/16/08 – Phase I is complete. Phase II has begun. Trenching for new sink was this week. No reports after TTC clarification was given. We are hoping things go well.

09/10/08 – TTC contacted Carrigan & Grimm about WC-4 for this project. MRDD wants light lens on warehouse lighting. Phase 2 is first. Phase 1 is second. All permits are approved.

08/25/08 – HVAC and Plumbing submittals are complete. TEI sent back to contractors. Building & HVAC permits are ready. $2,769.87 for the building permit $1,045.45 for the HVAC permit.

08/22/08 – TEI sent permit drawings to the project team. TEI sent out all HVAC submittals back to PHB.

08/08/08 – No update on approved IBI permit for this project.

07/29/08 – TTC hand delivered third revision contracts to KM at MRDD. We are awaiting project kickoff.

Bids came in acceptable. Pre Award meetings are complete. Contractors are approved.

MRDD Jackson Center Renovation Read More »

MRDD Due Diligence Report

09/21/09 – Kevin called with final comments on the final draft. TTC incorporated these and other comments into the final printing. TEI made 3 copies and mailed 2 of them to Kevin. Per Kevin’s request we will assemble the report into pdf format and email as well.

08/25/09 – Reports are due Sept 4 to Kevin Maue.

07/29/09 – All buildings have been visited. The reports are about 50% updated. Cost estimates, write-ups and grade cards remained to be inputted.

06/18/09 – TTC turned over the final Beckman report for Kevin to review. TTC spent a few days proving that the EH rate is the best rate for the County in these buildings. During this investigation, we found that several of the MRDD buildings are already on the EH rate but are also buying gas on the open market from a broker. TEI has visited Beckman, Northside and Franks so far and completed the field work. The Beckman report is complete. The Northside report is going to be sent to Kevin next. TTC will have Folck & Counts write up and estimate the Franks Adult Center report next week. Kevin said that we will be visiting the schools next. Try to get a date and time for Danny and Amy to do the next building.

MRDD Due Diligence Report Read More »

MRDD 1520 Madison Road Renovation

12/31/09 – There are minor control issues with the economizer in question but the building and controls are working as designed. TTC archived on 12/31/09.

10/20/09 – Kevin has JCI coming out to change return air humidity to zone average humidity on RTU-1 on Thursday. TTC may attend. Three items remain on the service punchlist. TTC contacted Brett to get answers about economizer control,

09/22/09 – I believe the final controls punchlist items to be complete is to acquire the software CD’s and backups of the current settings.

08/25/09 – Building is overcool in mornings. JCI is supposed to come out and fix timing and response loops. Many emails and phone calls have been made trying to get this done.

07/29/09 – Today we received updated As-Builts on the controls for the building from Chuck Vedder. I forwarded them to Kevin Maue for his keeping. I am also printing out a full set of 11×17’s to keep in the basement of the MRDD building again for our use. Everything seems to be running really really well.

06/23/09 – Triton, JCI and Carrier have finally been to the building enough to help us change the programming on the unit to get it to coordinate with the JCI system. This project may finally be finished. Things are working well in both buildings.

02/02/09 – Triton is reporting that Chuck Vetter will finalize this project for 1520 Madison. TTC contacted TJ Williams for the smoke detector work on the 1956 unit. TTC sent a summary email for controls to Brett at Triton for final completion items. The unit is finally running well but the building pressurization & the duct heaters are not working quite right yet.

10/16/08 – Grady says Triton will put together a final sequence that incorporate everything that is really working on the project and the way it works.

09/26/08 – Const Mtg 2 is over. TEI responded to TJ Williams RFi about another light in the hallway. TEI is approving the PHB Honeywell controller for the HVAC unit.

08/25/08 – Triton emailed today to discuss remaining closeout items. TTC explained about OA sensor.

08/22/08 – Triton is ordering a new board for Boiler 2. Triton relieved the pressure on the hot water system to prevent relief valve issues. Triton may have to get TJ to troubleshoot the overloading problem on the recirculation pumps. Kevin emailed that the OA sensor was flaky again.

07/29/08 – Brett Harpel of Triton discussed final control sequences with JCI. Modifications to system were made a month ago and again last week. Building is running fine. KM wants TEI to bless the control system as it meets design intent of the specs. JCI replied stating TEI sequences were in fact in place on RTU-2 but local overrides were keeping the system from operating as designed on that day.

Triton asked to switch the disconnects serving the RCP to troubleshoot low voltages problems at Boiler-2.

Triton to test expansion tank pressure to see if it is causing over pressurization.

MRDD 1520 Madison Road Renovation Read More »

MRDD – Beckman Fire Protection and Fire Alarm Upgrades

10/28/10 – Phase 1 & 2 are nearly complete. Punchlist is scheduled for 10/29/10 at 8am. All lights are installed, we want to change bulb color to cool white. We need price from Quality on isolation valve. QFP has been advised to replace the ceiling tiles in the main Administration area from the allowance monies.

09/27/10 – Next Const Mtg was rescheduled to Oct 6, 2010.

07/28/10 – Contracts have bee approved and signed. Awaiting first const mtg.

07/23/10 – Bids have been opened and approved. Pre Award meetings are complete. QCE is the electrical. Quality is the Fire Prot Contractor. Contracts have been written and approved by the Prosecutor dept. We are submitting a package back to the bldg dept to answer their concerns on permit issuance.

05/26/10 – Drawing stamped and signed. I will pick up the GC dwgs on Thursday and take to the permit office after Partner meeting. Budgets look good. Emergency lighting is an issue to design and may add more detail to for bidding. ITB was assigned 047-10. Bid set due June 4.

05/16/10 – Client review meeting brought up several issues that we have to fix before permitting. We will permit on 05/26.

MRDD – Beckman Fire Protection and Fire Alarm Upgrades Read More »