JC – Kitchen Trench Drain Repair Project

04/05/05 – Queen City Final Paperwork arrived at TE for review. TE to pass along to Mark Hardin soon.

01/14/05 – TTC sent out allowance confirmation with final instructions to Brian for project final payapp.

01/11/05 – Change Order Approved. TTC signed today and sent to QCM for signing. $8028.68. QCM removed 2 hours from the change order for miscommunication on the handle removal.

11/18/04 – Tiles are installed, Steam kettles are being installed by Peck, Piping is being finished by Peck, QCM will be down this evening to anchor the remaining leg holes. TE would like County to request second shift of Peck workers to complete steam piping so kettles are ready to go by 5 a.m. on Friday morning. Bernie is to call TTC back when he gets off the phone.

11/09/04 – The trench pour is not smooth enough to meet TE expectations. QCM said they will grind down to make smooth and backfill with sand based concrete to meet specs. Siemering is onsite prepping the floor for new tiles. Peck will be in next week to finish the steam kettles. The project schedule is very tight and Mark Hardin and Terry Cannon are trying to keep on top of items as they arise to meet the November 18th schedule. The kitchen should be ready for use on Friday morning November 19th.

11/08/04 – Epoxy on new concrete issue has been resolved. We have directed QCM to follow a new schedule. TE and County met Siemering tile onsite this morning to review the scope of the work. Floor tiles won’t be onsite until Monday 11-15. To accommodate this change of plans, the following new schedule is being incorporated into this project: QCM will demo forms 11-08, County will process Siemering background checks, QCM will provide new studs for kettle installation to replace the ones damaged during removal on 11-09,11-10. Siemering will prep the floor on 11-11 and 11-12, QCM will apply first coat of epoxy on 11-11, no QCM work on Friday, second coat on 11-13, attach stainless steel angles on 11-13, Siemering will begin tile installation on 11-15, finish on 11-16, QCM will install steam kettles on 11-17, Peck will finalizing steam kettle piping on 11-18. Project will be punchlisted by TE. This is our drop dead timetable.

11/04/04 – TTC visited the site. Things are going well. New schedule looks like this: 11-4 pour new trench let cure, 11-5 acid etch new conc, 11-8 apply first coat of epoxy, 11-9 apply second coat of epoxy, 11-10 start tile work, 11-11 complete tile work, 11-12 reinstall steam kettles. PHB will have to finish steam piping by 11-11 and we confirmed today with Mark Hardin that only condensate would be stainless piping. PHB can continue to work during the day while QCM works at night.

11/03/04 – PHB is on site doing steam work. QCM has found and removed the valve handle. The new concrete will be poured on 11/04/04. TE has received and is approving the Pitt-Guard Epoxy Coating (USDA and FSIS approved) for use on the trench surface. QCM is to follow the recommended installation procedures for this epoxy for proper installation including concrete preparation (acid etched or brush blasted) and pour the concrete so that it is self-priming as listed on the cut sheet. QCM is also to provide 3 vandal resistant floor drain covers on the existing trench floor drains and two stainless steel angles to support the stainless grating being put back in place.

11/01/04 – Peck reported that they are all set to begin the steam piping work and have coordinated with Tony about this project. They should be on site and ready to work in the next couple of days.

11/01/04 – Karen Draper from the City Health Department returned my call and told me that our plan to install smooth concrete with an epoxy coating in the Justice Center trench with vandal resistant flood drain grates. After my latest phone call we actually discussed the existing condition and the Health Department is very much inclined to approve our new design with the concrete and epoxy coating where we remove all instances of standing water under and around the SS trench in lieu of the concrete/epoxy hybrid. Karen said that any FDA or USDA approved epoxy adhesive and sealant will suffice so QCM can submit what they plan to do to TE and we will look it over and give it our blessing as soon as we receive it. QCM please also provide the stainless steel angle irons along each side to support the grating, attach with adhesive and i would recommend that anchors be installed in the vertical sides about every 6 ft o.c. to hold the angles in place while the grate will hold down the top. PDF

10/27/04 – QCM is on site and beginning work. TTC showed up at 8:00 to coordinate final details as all the important people took care of business from 7:30 – 8:00 p.m. QCM must submit security releases for the coring company TODAY!

10/25/04 – QCM is ready to begin work on 10/25, they need approved security checks but are planning on being on site at 7:30 p.m. as scheduled.

10/11/04 – QCM delivered the project schedule and it was forwarded to MWH and HS. TE approved the timetable for mid November completion.

10/11/04 – TTC & HS are asking contractors to give a price for replacing the insulation on the steam piping behind the steam kettles while the system is down in October/November. TE is exploring a insulation base paint that can be applied. Hy-Teach Thermal Solutions www.hytechsales.com is one site for this paint that TE found. We have calls into their engineering department for information.

09/24/04 – Notice to Proceed was given by MWH via a phone call. TE to setup up pre construction mtg.

Bidding is complete.

JC – Kitchen Trench Drain Repair Project Read More »

JC – Battery Room Fan Coil Upgrade

07/12/05 – Final paperwork arrived today for this project. TTC copied the documents, signed the final pay application and dropped it into the mail for the County.

06/30/05 – Filter rack is fixed. Final paperwork has not been received. O&M’s have been delivered to the County via a hand delivery by TTC. TE contacted PHB today about final paperwork status. PHB will get out soon.

06/15/05 – O&M’s Received today. They were approved and will be held for final payapp paperwork. PHB should be down in the next day or two to fix the filter rack and then they will send in all final paperwork.

06/09/05 – PHB called to questions the $2500 allowance on this job because it was not in the contract. TTC checked the bid documents and the contract and PHB is right. The original bid of $24,400 did not leave enough room to add the allowance alternate without going over the $25k limit by ORC. We will now have to write a change order to increase the budget slightly to accommodate the newly added automatic air vents which are a necessity in a chilled water system like the one we are using at the JC. Final paperwork should be down to you in about a week.

06/07/05 – PHB reported that they would be down to finalize the punchlist about June 20 – 27 or so.

06/01/05 – TTC sent an email reminder to PHB to finalized punchlist and finish the filter box.

05/05/05 – Punchlist distributed to PHB. PDF

04/05/05 – TE stopped at site today to punchlist the FCU job. SBO did the site work. Punchlist will be distributed very soon.

03/15/05 – PHB requested a change order for the new automatic air vents. TE asked for the cost and will suggest the County accept this allowance usage as part of the project that wasn’t included in the original scope. We are awaiting a cost associated with this additional work. I can see now that the last payapp was approved for too much money because we have a $2500 allowance that hasn’t been used at all, but that is okay now because we need to pay for this additional work and that will come out of the allowance. I guess PHB didn’t break out the allowance as a separate line item on the schedule of values.

03/15/05 – TTC coordinated with Howard and Bernie since payapp only left $2300, TE wanted to make sure that controls and electric and vents were all installed and working by the end of the week so that TE can do a punchlist soon. TTC left a messages on Bernie’s cell phone.

02/28/05 – IBI Permit set in PHB hands. Fill up and startup of new FCU should happen within a week of electric hookup and IBI approval. Tentatively we could be looking at startup at the end of next week.

02/25/05 – TTC notified PHB today that the return transition is not necessary on this project as it would prohibit access to the return filters. The supply transition is being fabricated at this time and PHB should be out to install it in the next week or so.

02/16/05 – TTC checked on the status of this project today. Piping looks good. Insulation needs to be installed. Thermostat has to be installed. Unit has to be started. Pressure test has to be removed. Final piping must be filled and checked.

02/07/05 – Doug Turner was onsite making the tie-in connections over the last weekend. They drained the system and refilled it and made the tie-ins

02/02/05 – Permit has been applied for by Peck for this project.

01/25/04 – Peck was onsite to review project. TE is to provide stamped signed dwgs for permit and to discuss supply diffuser and return grille on fan coil unit.

09/23/04 – Bids Received and Posted. TE awaiting County’s approval to proceed with contract. See bid results below

09/13/04 – Bidding Underway

JC – Battery Room Fan Coil Upgrade Read More »

JC – Task Force Room Upgrade

09/18/05 – The city has approved the whole permit. This job is complete.

07/22/05 – Steve Ossege called and said the City does not know of any approved independently support handrail system that meets code. He will however approve the platform arrangement discussed on site.

07/18/05 – Ed Enderle of DK called today and quoted $2450 to build a platform and railing for the Task Force Unit. TTC asked them to look into temporary handrails that were eluded to by Steve Ossege. More information to follow.

06/27/05 – TTC and DK have been working on getting the permit issued and closed for a week. Amit Gosh called and verbally told me that he was signing off on the permit today. TTC relayed this information to DK for finalization.

03/24/05 – JCI reported that wiring and status condition has been wired from Task Force unit to DDC. Programming is complete and task is complete.

03/22/05 – DK delivered the final payapp today along with all the final paperwork. TTC will sign and send to Diedra in the Sheriff’s Dept for project completion.

02/24/05 – Debra Kuempel (DK) deliver payapp #2 today. It was approved by TE. All final paperwork should be complete next week.

02/22/05 – DK stated that all final paperwork was sent over last week to TE. TE is going to finalize and send to Diedra Burns this week.

01/25/05 – TE contacted Ed Enderle as all work is complete and signed. TE request final paperwork and signed punchlist!

01/24/05 – TEI called DK and spoke to Michelle Combs in regards to when we may expect Pay Application #2 and final documents. Michelle was not aware that the project was finished and said that she would check with DK personnel and will call back, I told her that Ed Enderle may be of assistance.

12/15/04 – Debra-Kuempel Pay Application #1 not found at Hamilton County. Transmittal and ThermalTech records indicates that the application was mailed September 24, 2004. Doris called and left a voice message for Michelle Combs informing her that the application was lost and asking her to resubmit an original application.

10/12/04 – DK has finished project. The allowance has been used to get a new power source for the computer room unit that doesn’t shutdown the UPS system. TE has instructed DK to finalize paperwork and punchlist to complete this project. Howard reports that things are working okay to date (4 days runtime at this point)

09/29/04 – TE emailed DK for an update and schedule.

09/23/04 – TE directed Debra-Kuempel to redo their Change Order/Allowance price to re-use the existing MCC starter that use to be for a now abandoned pump to the get the cost under $5000 so we can use the allowance money without writing a change order for this project. We have $5000 in allowance money to use towards re-doing the power to the computer room unit. Once this is complete all work on this project and the punchlist items should be taken care of at the same time. Look for completion by September 30, 2004. The will coordinate all field visits with Howard Seal before starting on site.

TE has to finalize power change work with Debra Kuempel.

TE has distributed punchlist.

Compressor short cycling has been eliminated by utilizing the hot gas bypass feature to change the performance of the system.

TE to work on a new power source must be found and the unit hooked to emergency power panel instead of the current UPS connection.

JC – Task Force Room Upgrade Read More »

JC – Exhaust Fan Upgrade

06/15/05 – TE received final paperwork and change order signed for this project. TTC will be mailing it down to Diana with final balance report for HC records. This project is complete. The County is getting $3256 back on this job! O&M’s received and forwarded to County.

05/25/05 – PHB Jerry Govert called today to organize final paperwork. TE sent out a change order to recouple the $3256 in remaining allowance money. All final paperwork should be received in a couple of weeks. PHB should include the CO Credit with final paperwork.

04/22/05 – TE does not or has not seen final paperwork on this job. The balance paperwork was marked as received but no pay applications have been received. Please submit with all final paperwork for payment. Please provide all final paperwork and allowance usage details because we did us the allowance on this job.

02/25/05 – TTC ask Ken Shad to give me final paperwork and allowance change orders to wrap this project up today. He said that he would get right on it.

02/16/05 -TTC has requested all final paperwork on this project including balance reports. PHB sent to TE office on Tuesday. TTC to review.

01/18/05 – PHB stated that all work is complete including the 2 new 5 HP motors. The exhaust % increased by 18-20%. TE is awaiting all final paperwork on this job for closeout. Rick Ahrens will stop by to take a look at a motor squeal on Thursday.

12/27/04 – Howard reported today that EF-C1 has high pitches squeal. TE called Peck, but they appear to be out of office today. TTC will try first thing Tuesday morning again.

11/26/04 – PHB has acquired all existing cfm data from the fans. TE is reviewing to provide a direction to the PHB construction team. It appears as though the allowance money should be used to replace the motor on EF-D2 from 3 to 5 HP. The wire size is sufficient. The existing 3 hp bearings will be taken out and put on EF-D1 as that fan needs a bearing replacement. PHB reported that even with the duct cleaning there are still some security grilles that are clogged with dirt and the secure design makes them virtually impossible to clean out from inside the cell area. TE to advise how to handle this situation. Sam Boehringer will be reviewing submitted data on Monday November 29 at TE and then we will setup and onsite meeting to go over the project with the owner in the coming week. We have a $5000 allowance to use for these repairs.

10/15/04 – TE has contacted PHB about and updated schedule for this project.

10/05/04 – Pre construction meeting was held and PHB plans on starting in 2 weeks. Schedule is basically one EF per month.

09/20/04 – SOSS revised for additional Champion monies and will deliver on 09/21/04.

Champion provided duct cleaning on existing systems. Hired through ThermalTech.

Peck Hannaford & Briggs won the bid ($26,050). Base Bid, Alt 1, Alt 2 and $5000 Allowance. EF-C1, EF-C2, EF-D1

Contract written and being reviewed.

JC – Exhaust Fan Upgrade Read More »

JC – Boiler Room Exhaust Fan Upgrade

05/23/06 – TTC archived this project because there is no way to make this work without a lot more make up air into the room.

10/28/05 – TE still has not found a viable solution for the heating problems in the space and will look at other usages.

10/24/05 – TTC has not found a usable scheme for boiler exhaust to date. There is not enough cold air to make a dent in boiler room temperature without additional cooling.

10/14/05 – TE cannot find an exhaust fan design that works without additional cooling.

10/04/05 – TTC & SBO have visited the site and are designed the new exhaust fan design to help remove heat from the boiler room.

JC – Boiler Room Exhaust Fan Upgrade Read More »

Justice Center – Backup Chiller Project

09/01/06 – TTC worked out final billing details with Bridgette today by phone. DK is sending over final invoices for payment.

08/30/06 – Steve and Terry finalized the number required on the final payapps. Laurie is typing up the final change order for the project. TTC has to coordinate the change order payment with Tony Matre.

08/29/06 – TTC reviewed the final pay application by Debra Kuempel. Change orders amount were added to the contract amounts and this is not correct so TTC has to contact DK to figure out the correct billing method.

04/03/06 – JC asked DK to insulated the chilled water lines to prevent pooling under the chillers.

03/24/06 – DK has not been on site doing any work. They may wait until it gets warmer outside to make the boiler changeover work. The chiller scope is nearly 100% complete.

02/23/06 – TTC was on site today to look over chiller project. New 12″ mains look great and are installed and cored drilled and anchored.

02/22/06 – We approved some small allowance work today described as: *Cut (2) 11/2″ nipples off existing thred-o-lets on Chilled Water Supply and Return piping. Weld on B/W caps on to existing thred-o-lets to cap lines off. *Install 2″ thred-o-lets with ball valves and caps at the bottom of 12″ Chilled Water Riser for drains on both supply and return piping. Total cost for the work outlined above is $642.00

02/16/06 – Howard asked about replacing valves if they don’t hold and about removing a 1-1/2″ nipple in piping when drained down. These are two agenda items for Friday Const Mtg.

02/10/06 – TTC release this email after talking to Howard this morning:

Steve, When you go to the drain the Chiller plant at the JC, it was our belief in the bid documents that the butterfly valves near the chiller will hold the water in the system and prevent a complete drain down of the mechanical plant. If this turns out not to be the case and we have to drain down the entire building, there is a concern about who is replacing the nitrate in the CHW. It is my belief that this is a condition that will be covered by the allowance we have on this project if it proves necessary. I don’t foresee this being more than $500 or so if in fact we need this. Please let me know how the valves hold next week when you begin to tie into the existing system. If you have any questions, please let me know. thx, ttc

02/02/06 – TTC contacted DK about working on the chiller project and they said they would get started.

01/17/06 – TTC held the pre construction meeting today and distributed the meeting notes. The boiler project will start 03/15/06 and last for 60 days. The chiller project will begin immediately and last for 60 days.

01/10/06 – Pre Const Mtg scheduled for 01/17. Everyone has confirmed for meeting.

12/13/05 – Contracts were returned for corrections. TE corrected, printed and returned to the County for submission to the commissioners.

11/08/05 – Tony gave TE the okay to type the contract for Debra Kuempel on this job. We are taking the base bid and $2000 Allowance.

11/07/05 – TTC opened and tabulated bids for this project. See link below.

10/28/05 – Prebid meeting was held with all contractors. Bids due Friday to TE.

10/24/05 – Drawings are complete up to TTC’s review. Prebid is set for this Friday.

10/14/05 – TTC promised final design complete on Wed 10/19.

10/03/05 – Tony approved our recommendations and we are going with the plan to put in the chilled water tie

09/29/05 – TE recommended to the County that no electrical xfer switches be included in the temporary job because the expense of putting in electric switches just isn’t cost effective to providing emergency generators on site at the time it is needed. Feeding the chillers is problematic. TE will bid the mechanical work out as a small project.

09/27/05 – TE pulled all the old designs from the archive and setup the new project. Electrical is a big issue as this will put the project over $25,000 unless we use generators.

Justice Center – Backup Chiller Project Read More »

JUSTICE CENTER – Backup Boiler Project

09/01/06 – TTC worked out final billing details with Bridgette today by phone. DK is sending over final invoices for payment. TTC sent out the change order for the job to Steve V.

09/01/06 – Tony approved the $1597 change order by phone today. TTC to advise DK to wrap up the project.

08/30/06 – Steve and Terry finalized the number required on the final payapps. Laurie is typing up the final change order for the project. TTC has to coordinate the change order payment with Tony Matre.

08/29/06 – TTC reviewed the final pay application by Debra Kuempel. Change orders amount were added to the contract amounts and this is not correct so TTC has to contact DK to figure out the correct billing method.

08/24/06 – Al Bell reported that the high pressure sensor was re-ordered and will be installed very soon.

06/26/06 – Howard reported that DK will be onsite tonight and begin the work on the final changes to the job. JCI and DK have not been in contact with each other yet on the new sensor.

06/06/06 – TTC contacted both JCI and DK again about progress. JCI came in last week but needed a different part to make it work. DK is supposed to be down this week but TTC will find out more details from Steve Vater and let everyone know. As of Monday, Howard had not heard from DK about coming back.

05/23/06 – TTC emailed both Debra Kuempel and Johnson Controls to try to get them scheduled to finish this project up. TEI will pay the JCI cost to the job and DK will bill towards the allowance to wrap this up.

04/03/0 – DK is going to be on site the week of 04/10 to finish up the boiler work. JC asked for insulation on chilled water system to prevent condensation. TTC relayed this information to Steve Vater and asked DK to coordinate their time and visits directly with Howard Seal.

03/24/06 – DK has not been on site doing any work. They may wait until it gets warmer outside to make the boiler changeover work. The chiller scope is to b nearly 100% complete.

02/23/06 – TTC visited the site today with the contractor and Howard. TTC wants to remove a check valve from the main steam supply from the courthouse because the pressure drop will be to great to keep this device in line. An existing chain operated gate valve on boiler #3 will suffice in place of the one noted on note #3 on the dwg. The non-return valve can come out as planned. At this temperature outside the steam plant from the courthouse can’t be shutdown until 7pm and it must be back online at 3am. DK will have to coordinate this with Howard and the CH staff.

02/22/06 – We approved this allowance usage today:*Install (2) 3″x21/2″ weld reducer on new 3″ pump condensate piping at tie-in point to existing piping. Existing pump condensate piping is 21/2″ in size. Debra-Kuempel quoted total cost for the work outlined above is $261.00

01/17/06 – TTC held the pre construction meeting today and distributed the meeting notes. The boiler project will start 03/15/06 and last for 60 days. The chiller project will begin immediately and last for 60 days.

01/10/06 – Pre Const Mtg scheduled for 01/17. Everyone has confirmed for meeting.

11/08/05 – Tony gave TE the okay to type the contract for Debra Kuempel on this job. We are taking the base bid and $2000 Allowance.

11/07/05 – TTC opened and tabulated bids for this project. See link below.

10/28/05 – Prebid meeting was held with all contractors. Bids due Friday to TE.

10/24/05 – TTC & SRB visited the site to pickup some last minute details about returning condensate the DA system when the Justice Center is on its own steam. Drawings are complete up to TTC’s review. Prebid is set for this Friday.

10/14/05 – TTC promised final design complete on Wed 10/19.

10/03/05 – Final design is being complete. Job is ready to bid out for small projects.

08/23/05 – TTC visited the site and found that bypass valve is already in place so that piping work does not need to be done. At this point there are a couple of viable options: 1) put in a new valve near the jc side of the bridge or automate an existing pneumatic valve in the courthouse. TTC sent an email to Tony, Howard and Mike looking to explore our options.

JUSTICE CENTER – Backup Boiler Project Read More »

Justice Center North Electrical Device Identification

01/10/07 – Project completed in 2006.

08/24/06 – Drawings were delivered to Hamilton County Facilities. There are no open issues on this project.

05/17/06 – Close-out meeting; no open issues. All work by Queen City has been completed. I will be working on getting the drawings completed within the next several weeks and send (3) full sized sets to Hamilton County Facilities (Attn: Bert Watts, Jim Eby, Howard Seal). Queen City presented (2) binders, each with copies of the old and new panel schedules. On the new panel schedules the items listed in bold have been verified; the items listed in normal type are transferred over from the old schedules. The binder also includes diagrams of the MCC’s and Switchgear. A CD was also provided which contains all of the new panel schedules in Excel format.

11/15/05 – Contracts have been submitted.

Justice Center North Electrical Device Identification Read More »

JC – Replace Sallyport Sliding Gates

02/19/07 – TTC is approving and passing along all the closeout documents for this project. TTC is archiving this project today.

01/02/07 – TJ Williams submitted a letter expressing their extreme disappointment with the County not approving the Change Order for the extra work incurred during the Sallyport project. TTC forward to Mark Donnelly for the County to file with the records are address separately if they deem it necessary. PDF

12/26/06 – TTC archived the project today. Legacy has the smallest bit of paperwork to turn in on this project. Once Donnelly has that, this project is complete.

12/14/06 – Mark called today about closeout and Legacy reported: The guides at the justice center are painted. I am not sure the status on TJ Williams. Kenny is in a meeting until about 5. As soon as he gets in I will get an update and get you the information. I have been working on the close out documents and we are about 80% done. We still need to finalize the certified payroll from two of our sub-contractors.

12/04/06 – Close out meeting was held today. 3 items on punchlist were discussed. Pay App 01 was discussed. Legacy to provide a revised Payapp 01 with allowance shown. TTC signed payapp 01 for Mark D to use as soon as a revised schedule was provided by Legacy. Legacy provided one by email but TTC edited it and sent it back out to the contractor with 8% retainage per the project manual. TTC also sent Allowance Clarification 01 to the contractor for signing.

12/01/06 – TTC sent out formalized punchlist items today and reminded everyone about Monday’s meeting. PDF

11/20/06 – The project is complete. There are two punchlist items which remain: touch up paint on door frame and the control panel box that TJ damaged during construction. The doors are working, the fencing and hardware are all installed properly and TEI visited the site for a punchlist walk through. The TJ change order was denied but it was agreed that the allowance money could be used to pay for the extra expenses. TEI has asked for closeout documents on the whole job to wrap it up. We are having a closeout meeting on December 4, 2006 as a final meeting.

10/10/06 – The structures are installed the concrete is finished. We need to let it cure for about 2 days before we install the overhead doors. TJ Williams has some temporary power and control patches installed in the building that have to be replaced. Overhead door is supposed to bring down the doors on Friday of this week. TJ Williams has not started the change order work on the loop control. We are hoping they will do that this week when they come down to do the rest of the work ready on the project. Legacy has a new PM on the job. Ken has taken ill. Howard was able to get the new guy into the building for the concrete today. In a week or so we should have operation of the new doors. The Sheriff may re-stripe the parking lot and move the dumpster outside the scope of our job.

09/15/06 – Legacy contacted us today to report the steel has been ordered. 09/25 looks like a delivery date on that. The doors are in town and waiting to be installed. Legacy may be down next week to do some anchor work on the new structure and Howard confirms that all security cameras are still in operation after TJ Williams completed their partial demo. Saw cutting and more general work scheduled for mid week of next week.

09/04/06 – Change has left our office to the contractor. Project should move forward immediately. Contractor planning on being on site this week.

09/01/06 – Change Order for $3775 was approved today by Mark at meeting in his office. Sheriff will do demo of existing fencing. Legacy will sink new polls for fencing company. TTC approved stainless steel anchors for this project since galvanized were hard to order on time. TEI to write change order asap.

08/30/06 – Legacy reported an error in the change order pricing and a misunderstanding on ThermalTech’s email. New pricing was sent to TTC by fax today. TTC will forward the information to Mark Donnelly on this project for a decision.

08/29/06 – Change Order prices came back today as $1800 for fences with Sheriff demolition and $7195.00 if Legacy does everything on the job. TTC passed along to County. HS was checking with Sheriff’s for their willingness to still do their part.

08/24/06 – Today we approved the electrical submittals and asked for an immediate change order cost for the new door location on this project from Legacy. We have been waiting at least one week for this amount.

08/16/06 – We have had two kickoff meetings for construction. The first issue was the location of the new doors. The Sheriff has now put forth an edict that the busses that enter the site should be closed between the doors. This was not the case during the original design. TEI has issued a change order to collect costing information for this change order. It shouldn’t be too much money as the a lot of the scope is already included. The Sheriff is willing to provide additional demolition of the existing fencing to make this work and Howard stated that the existing dumpster fencing must remain as is, TEI said that is fine. TTC called Ken Jones today and found out that the CO cost is not ready yet and the security checks have not been sent in yet. TTC advised Legacy to move forward immediately with providing this information and the job is ready to begin. Spencer approved the submittals on his and TEI will distribute them as approved to the vendors.

07/25/06 – We received today that the contract was approved. Pre Construction meeting scheduled for 08/02 at 2pm. TEI to contact Legacy Construction for meeting.

06/19/06 – TEI revised the contract and mailed 3 originals to Mark Donnelly for submission for approval. After approval we will convene a kickoff meeting for the owner and contractor.

06/01/06 – Contract was submitted to prosecutor for review.

05/25/06 – Contract was written for Legacy and mailed to Mark for approval.

05/23/06 – Bidding is complete. Addendums were issued. Bid were opening on schedule. TEI drafted our first contract and will give it to Mark for submissions to the prosecutor department. We luckily increased the project budget because the job came in over the estimate but within the 10% margin but still under the actual Archibus estimate.

04/11/06 – Final Client Review sent was sent to Howard and Mark including the work from CRA and THP. There are still some issues to resolve before bid issuance. Mark and Terry increased the budget to $80,000 to cover the additional work added to the job by a more extensive structural drawing set and permits being added back the project. Security Cameras and lights had to be moved to allow for new overhead door placement on project. TTC coordinate with Howard Seal on this point. TEI located the South camera and light on the dwgs and in talking with the Howard the North camera and light were also located on the plans accordingly. County comments are due back on Friday. Final set is due to Purchasing on Monday morning.

04/05/06 – A second design meeting lead to some changes in the door placement. TEI developed a new drawing showing the perpendicular arrangements of the new overhead doors and modified the drawings notes accordingly. Power will be brought from existing connections. The razor wire will be removed and replaced by the contractor. The north door shall be the first to be replaced. The old sliding gates will be completely removed from the job. TEI added special notes to allow other manufacturer’s to be submitted on but they must be approved before bid day by the engineer. The specs were updated and the ITB number and dates have been acquired. A review packages was sent to the team for initial review.

03/21/06 – TTC and Mike Haney spoke today about the project’s structural requirements and THP had some great ideas. Since these are overhead doors they can be turned perpendicular to the building and only be 15 ft wide thus making the doors smaller and the support steel smaller. This sounds like a great idea. TEI will approach the owner about this condition.

03/16/06 – Design meeting schedule on site. Sheriff has approved type of door that we will use for this project. Now we just have to finish the structural design and bid the project out.

02/10/06 – TEI release a review set for comments to the County for this project. TTC still has to discuss product with overhead door and finalize ITB. We have not requested an official ITB from purchasing yet.

02/08/06 – TEI and CR met on site with Howard and Tony and reviewed scope of work.

JC – Replace Sallyport Sliding Gates Read More »

JC – ID & Fingerprinted Dual Duct Box Upgrade

03/15/07 – All Closeout is complete. Howard is satisfied but JCI has a bit of tweaking to do on the sensors. This project is ready to archive.

02/28/07 – JCI dropped off as-builts and O&M and final payapps for this job. TTC to approve and send to Tony. TTC approved and gave to Laurie to send to Tony.

08/30/06 – Triton has all schedules for the proejct and are putting the submittal data together right now. They are not sure about having 8 or 9 vav boxes on their PO.

08/23/06 – Construction Meeting Held. Job should be completed in 60 days. Triton to provide equipment, JCI to provide installation power and controls. PDF

05/09/06 – TTC compiled the complete state term contract and will deliver it to Tony’s office in the morning of 05/10/06. TEI is sending 4 copies of the contracts, spec book, and 1 copy of the JCI bid documents.

02/16/06 – Tony asked for final contract documents to be sent over so he can move the project forward. TEI will have these to Tony by 02/17/06.

01/10/06 – JCI has provided all contract documents for a state term contract. Sam compiled everything and TTC needs to review it. TTC will then deliver to Tony for use on this project.

12/13/05 – TTC has contacted JCI numerous times about submitted an actual state term contract. Al Bell will work with Joe Schutte and get one prepared for this job.

11/08/05 – TE heard back by email form Jill Williams and we will set up a quotewire job for this.

11/07/05 – TTC opened and tabulated bids for this project. See link below. The project bids came in over $25,000. Tony and TTC decided that the best way to get the job done at this

10/28/05 – Prebid meeting was held. Bids are due 11/04 to TE.

10/24/05 – Project is ready for TTC review. Prebid is this Friday at the JC.

10/14/05 – Project is ready for review and bidding.

10/04/05 – TTC & SRB have visited the site and are redesigning the dual duct boxes. We have contacted JCI about scope of Sheriff’s upgrade to use on this job. Drawings are done. Specs need to be finished and scope needs to be ironed out.

JC – ID & Fingerprinted Dual Duct Box Upgrade Read More »

JC – HTX Upgrade

02/26/08 – Final paperwork, O&M’s and As-Builts have been sent to the County for closeout. This job is complete.

02/21/08 – TTC received the final pay application on this project and signed it immediately and sent it to Tony for closeout on this project. ThermalTech agreed to do the as-built drawings for Tony on this project.

12/05/07 – Today we worked on allowance cost and change order submissions by PHB. TTC asked for finalization and closeout paperwork from Bernie on the job. 3 allowance have to be finalized and TTC asked the County if there were any other tasks on this project they needed done with the remaining allowance money.

11/15/07 – PHB reported today that the equipment went in exactly as drawing except for some minor change in piping right above the heat exchanger. TTC said he would accept a markup on this change and incorporate it into the electronic dwgs for the job and give it to the County for final As-Builts. PHB is working on final closeout documents this week and should have them to TEI for final approval very soon, they only items they are waiting on is JCI sequences.

10/17/07 – JCI does not have the right sensors in the HTX system for their controls. We are investigating replacing them or using an old one. this needs to be resolved quickly.

10/01/07 – TTC & GD visited the site last week and reviewed the project installation. The job was very well done by PHB. GD requested that the strainers be installed in the horizontal position to alleviate water hammer. This is an arduous task for PHB but they are going it today. TTC approved payapp #2. JCI said they were almost finished with controls but had to add flex tight to the controls at the valves. Howard was going to run the system in manual to see how it works. TEI still must provide a punchlist for this project.

09/12/07 – Howard called with a questions about isolating the PRV for maintenance. TTC said it was isolated on the PID. TTC will stop down tomorrow to review with contractors and will setup a progress meeting with GD to go over design.

09/03/07 – In the past week we have approved a pad extension onto the front of the existing HTX pad layout to allow the piping to be connected to the existing piping easier. We have approved new butterfly isolation valves from the allowance monies and TTC approved payapp #01 for the project. In the field TTC approved a slight modification to the layout of the steam traps for easier maintenance and TTC and Walt discussed the atmospheric steam vent that is supposed to be connected to a tube inside the trap and came shipped separately.

08/23/07 – PHB asked about new steam control valves vs old. TEI directed them to the Add01 where hot water control valves are reused but not steam valves. Steam are new CV-27 types and 3″ in size. Howard asked about HTX loads and copper tube sheet strength. TTC asked GD and TZ for info. TTC scheduled a field trip on Friday to the building to review the progress of the project.

08/20/07 – PHB did get the new steam isolation valve installed. The Spence valve and 2″ gate valve was also replaced. Howard said that 2 of the hot water isolation valves are corroded and need to be replaced. TTC asked PHB to give us a price to replace this valves. These particular valves are not more than 5 or 6 years old as they were put in during the

08/17/07 – PHB is installing the steam valve, Spence valve and 2″ gate tonight after hours. TTC will check in with JC tomorrow on progress.

08/03/07 – TTC gave PHB requested information on the Spence valve, isolation valve and existing steam pressures. The Spence valve has unions on both sides for easy replacement. The isolation valve shows 6 inch on the dwgs and with the insulation on the piping, there is no easy way to confirm it isn’t 6″. The steam pressure is 65 psig max for normal operating pressure so PHB’s request to buy a 150 psig isolation valve will be fine. TTC & HS picked the location so that the HTX could be isolated from the system for this work.

05/30/07 – TTC contacted PHB about the equipment orders. The HTX vendor asked for more money for sizing the HTX at 10 psig but TEI emailed PHB and showed that 10 psig was called for on the schedule. This may hold up equipment ordering.

05/21/07 – TEI returned submittals via email to Bernie Tobergte today. Now comes the equipment order and scheduling. TEI will deliver hard copies to Tony and Howard.

05/14/07 – TEI has all submittal data and will review on 05/16/07 and return to PHB by week’s end.

03/14/07 – TM & TTC have contract and are ready for kickoff meeting.

02/01/07 – Contracts have been sent to BOCC for confirmation and then we will kick off the project.

01/02/07 – TEI has submitted all contract and bid documents to Facilities for Prosecutor review but as of this date, we have not had any information back on this project.

JC – HTX Upgrade Read More »

JC – Revolving Door Replacement

12/07/07 – CRA left message with Steve Jones regarding project status.

09/28/07 – CRA approved door shop drawings and sent to Southern Ohio Door. Next meeting to be held prior to start of construction.

09/18/07 – Pre-construction meeting was held. Notice to Proceed issued at pre-construction meeting.

09/04/07 – Signed contract received.

07/26/07 – CRA received minor comments back from Prosecutor. Contracts revised and sent.

06/21/07 – Bids received. CRA directed to accept and issue contracts.

05/29/07 – CRA reissued documents.

05/23/07 – Bids came in higher than estimated. Directed to raise the estimate to $85,000 and re-bid.

02/20/07 – Kick-off meeting was held at 9am in the Courthouse Room B-103. The possibility of installing remote lock down security revolving doors in the south building was discussed.

01/30/07 – CRA received the approved SOSS.

01/16/07 – CRA SOSS was authored and delivered.

JC – Revolving Door Replacement Read More »

JUSTICE CENTER ODR Kitchen Upgrade

05/22/09 – TEI has not been paid on this project yet.

03/02/09 – All work completed several months ago.

08/25/08 – Progress is being made on project. No Conf Call today.

08/22/08 – Permit has been issued and give to County (almost 2 weeks ago). Construction is proceeding. MAH is handling the conference calls.

08/07/08 – TEI submitted drawings for permit and copies of permit set to County and Andre for review and their records.

07/30/08 – TEI has been to the site several times getting additional field work for this project. Original load locations do not work for new kitchen equipment loads. 30 days panel load data is required. We will try to get permit on 3 day info.

09/05/08 – Permit obtained without metering. Work is in progress.

JUSTICE CENTER ODR Kitchen Upgrade Read More »

JUSTICE CENTER Domestic Pump Upgrade

08/24/10 – As-Builts converted and sent to GBBN and Bert.

08/13/10 – Waiting for final payapp and closeout. As-Built dwg is complete.

07/28/10 – Project is complete. TTC to delivery as-built dwgs to Bert.

07/23/10 – TTC is approved O&M’s on these jobs for Bert. Dwgs are being bound. Paperwork looks fine.

05/26/10 – Project is complete. We are awaiting closeout paperwork.

05/13/10 – I approved payapp #2 today and asked Gary for closeout documents.

04/26/10 – Project complete. TEI will release a no item punchlist and begin closeout.

03/19/10 – Corporate came down to investigate a blown fuse situation when opening the cover panel on the new pumps. JCI is looking to hook up the remaining sensors back to the new pump package for Howard. TEI will issue a punchlist on this project.

02/24/10 – QCM pumps have been verified in the shop for payapp. They will start on Monday at 6am and this is confirmed with Howard and Gary.

02/04/10 – QCM scheduled to begin work on 02/22/10. TEI asked for an updated schedule.

01/26/10 – Equipment is ordered and extra pump has been approved.

12/31/09 – Submittals have been approved and sent back to QCM. We still don’t know if Tony has approved the change order for an extra pump.

09/04/09 – Contracts submitted to the County.

08/27/09 – Bid open today. One Addendum was issued.

06/23/09 – Tony said the SOSS has been signed. We are awaiting approval and the PO. The existing Systecon domestic package is variable speed and will most likely be replaced with a new variable speed system that has readily available parts.

06/17/09 – Terry and Mike visited the building to create the SOSS.

JUSTICE CENTER Domestic Pump Upgrade Read More »

JUSTICE CENTER – Kitchen Oven Replacement

10/28/10 – Project is complete and ready for closeout. New paperwork has been received.

10/5/10 – CBS will receive $2,150.00 allowance monies instead of the $5,000.00 due to using $2,850.00 for upgrades to both ovens.

09/29/10 – Project complete. Need closeout documents.

08/13/10 – Waiting for closeout docs. Payapps sent in as paid.

07/28/10 – Oven look good. Punchlist items look to be complete. Training should be complete. Ready for closeout.

07/23/10 – Both Ovens are installed. TTC sent an email punchlist to CBS who said they would address these issues on their next visit downtown. Several of the items on the list require adjustment when the ovens are off. They said it would be no problem. Oven #1 had an issue with a door opening switch which CBS fixed and now all seems to be well.

05/26/10 – Kickoff meeting schedule for June.

05/13/10 – We are trying to setup our next const mtg on this job. Equipment should be here soon.

05/05/10 – Ovens are ready for shipping. Project is ready to startup in two weeks.

04/26/10 – Waiting on Oven delivery to begin the project. Contract checked in and is ready when equipment arrives.

02/24/10 – Tony confirmed the submitted oven is approved by Aramark for this project. Other submittal data is acceptable.

01/26/10 – TEI owes CBS submittals on this project.

12/31/09 – Oven submittals have been received. TEI to review and approve, especially the prison option to be finalized.

09/04/09 – Contracts submitted to the County.

08/24/09 – CBS was the low bidder. TEI interviewed CBS and they seem to have everything included in the bid. The bid very aggressive and want to make sure they can sell the ovens when complete.

07/29/09 – This project went out for bid last Monday. Prebid 08/05. Bid Opening set for 08/24.

06/23/09 – Tony said the SOSS has been signed. We are awaiting approval and the PO.

06/17/09 – Terry and Mike made a visit to the building to look over the equipment and the installation. There is some electrical work and mechanical work to perform but the bulk of the cost will definitely be the equipment itself.

JUSTICE CENTER – Kitchen Oven Replacement Read More »

JUSTICE CENTER Kitchen Hood Suppression Upgrade

10/28/10 – Cintas has not sent in AIA pay applications yet for payment.

09/03/10 – The kitchen passed its final inspection. All contractors were instruction to complete closeout documents and send final payapps in.

08/13/10 – All contractors reported for work. Cintas is compete. DK is complete. QCE did not finish yet. Final fire alarm test will be schedule after QCE is finished.

07/28/10 – Work is ongoing. QCE was on site and hooking up fire alarm contact last night. Cintas was not on site but Ansul system appears to be 90% complete.

07/23/10 – Cintas & QCE electric will begin work next Monday on the systems both Fire & Elec. We are scheduling a fire test pm Friday July 30. We are trying to get DK to fix the Aqua Vent system by then.

05/26/10 – Kickoff meeting schedule for Thursday.

04/26/10 – County reports contracts are ready to be signed. Then we will begin.

03/23/10 – No updates

02/24/10 – Under contract review. QCE called to ask about status. TTC updated them.

02/03/10 – TTC sent BW the prebid mtgs notes for contract approval on this job. We are waiting for construction to begin.

01/23/10 – We continue to wait for approval to proceed with this work.

12/31/09 – All bids have been received. TEI has delivered contracts to Tony for approval. We are waiting on approval to move forward.

09/08/09 – Steve Ossege discussed the hood coverage with Terry Cannon. All hoods that cover grease producing equipment. This means that one hood in the JC kitchen must be covered. The other hoods can have the sprinkler heads removed. All hoods must keep the fusible links in place with the hand pull stations. The Aqua Vent bid is still under review at the prosecutors.

08/24/09/ – Daryl Meadows and Steve Ossege will provide city direction for TEI work. Our design is complete. We just need to bid out the Ansul system replacement.

07/29/09 – Kitchen Hood Fire Suppression Upgrade is almost complete. This project is set for small bidding next week. The cost estimates show the project can be under $25,00 but not by much. The drawings are complete. The specs are complete. We will be inviting fire suppression contact

06/23/09 – Aqua Vent project in contract approval stage. Kitchen Hood project in code review and design stage. Cintas has not emailed or called TTC back about code requirements vs final design of this small project. They have given this information to the County before and I suspect they don’t want to design it for us. TEI has to update the hood suppression system, the interface to the fire alarm panel, and new relays for the remaining equipment for FA signals. This might be after the cost estimates are finished for 2009.

05/22/09 – The Aqua Vent repair has been bid out and we are awarding to Debra Kuempel for about $12k. Contracts are being written. TEI sent out the bid tab and told DK to get hard copy paper work to Tony by 05/29/09.

05/19/09 – Cintas has provided the estimate and a scope for the fire protection work on this project. TTC to use for bidding.

02/02/09 – Terry and Mike are finalizing a small project bid manual for this project this week. We are planning on bidding the 3rd week of February.

10/18/08 – Approved but new hoods not required. What upgrade is left to do? TTC to inquire with Howard.

08/07/08 – SOSS submitted for approval to County.

JUSTICE CENTER Kitchen Hood Suppression Upgrade Read More »

JUSTICE CENTER – Aqua Vent Upgrade

10/28/10 – DK sent final paperwork in for approval yesterday.

09/29/10 – Last 2 change orders were sent to Debra for closeout per Tony’s direction.

08/13/10 – All contractors reported for work. Cintas is compete. DK is complete. QCE did not finish yet. Final fire alarm test will be schedule after QCE is finished.

07/28/10 – DK finished change order work last evening. TTC check it over and was on site. All but one nozzle is working properly. We need a final approval from Howard before testing with City Friday.

07/23/10 – TTC told DK they needed to be done next week with their work. Rick returns Monday for verification. Nozzles have been replaced but 3 still need fixed. TTC will try to have DK fix these when they fix the rest of the equipment on the rinse cycle.

05/20/10 – Sent Tony and Howard final change orders with prices from Debra for wrap up. Awaiting approval.

05/12/10 – Met Debra today on final change order prices. We don’t have everything we need. I will contact Tony with questions on scope of work and change order cost. Terry sent a proposal to Tony and Howard for comment.

04/26/10 – DK sent changes orders for final repair cost to extra items such as the rinse cycle piping and solenoid. TTC and TM to decide next course of action.

03/23/10 – DK reported a list of problems with the Aqua Vent operation. TTC answered several of these answers and asked the County for direction on several others. DK also asked for a sequence of the original Aqua Vents but we don’t have that.

02/24/10 – DK coordinated final work with Howard to be this week and next.

02/03/10 – DK scheduled control panel installation on 02/22/10 when Howard returns. The owner accepted one change order and rejected the extra electrical work change order. DK has not responded to the TEI email about the change orders.

01/26/10 – Aqua vents assemblies have been rebuilt at Debra Kuempel. Control panel parts have been upgraded at DK. Change orders have been submitted for new valves and shock arrestors. We have approved this work. The change order for extra electrical time has not been approved by Tony.

12/31/09 – Rick Kuethe reports the solenoid valves are in and DK will start next week provided their men are approved and Howard Seal gives him the okay to start working.

JUSTICE CENTER – Aqua Vent Upgrade Read More »

JC – 20 ton Chiller Replacement

07/29/11 – Glen reported there is no turn down on the screw compressors.

06/29/11 – Tonnage looks to be about 10 to 15 tons. Final came in 11.7 tons. TTC sent review to Tony and Glen Wilhoit for their use.

05/05/11 – Waiting on people and load count from County.

04/25/11 – TEI asked Tony and Glen for more information on the space and to mark up the existing dwgs for space and layout, then we can quickly and efficiently run the model for HamCo.

03/30/11 – No further progress yet. Tony said we might write state term contracts for him.

02/22/10 – Tony asked us to do a load calc in the Sheriff area to confirm a new chiller size for the space serving the Sheriff space for additional cooling.

JC – 20 ton Chiller Replacement Read More »

Justice Center Kitchen Flooring Study

07/06/10- Attended Kick-off meeting with Bert Watts and Tony Matre.

07/15/10- Submitted SOSS to Bert Watts.

9/27/10- Meeting with GBBN, Fred Orringer (Kitchen Consultant) Jerry Vogel and Andre Tudor to discuss the logistics and operational issues for implementation of the possible flooring replacement.

9/27/10- Transcript of meeting sent to Bert Watts for clarification of scope and summarization of issues discussed in the meeting from the same day.

12/3/10- Bert Watts called to clarify questions on scope. It was determined the report would be issued to the Owner 1/18/11.

1/18/11- Final document was sent to Bert Watts electronically for review.

1/31/11- Bert Watts instructed GBBN to request color and slip resistance texture samples from the vendor for presentation to the Sheriff.

2/3/11- GBBN requested UreCon color samples from Key Resin. Key honored request to send color samples for the epoxy topcoat as well.

2/15/11- Color sample chips arrived along with slip resistance samples.

2/17/11- Color charts arrived.

2/18/11- Bert Watts sent a list of proposed kitchen equipment to be replaced in the flooring project. TEI and GBBN are to investigate possible connection and logistics costs for this equipment for inclusion into the final Study.

2/21/11- Bert Watts called to indicated the final report with modifications is due 2/28/11.

3/3/11- Delivered final copies of Flooring Study to Bert Watts.

6/28/11- Bert Watts requests SOSS from GBBN to include ThermalTech as consultant.

6/29/11- GBBN sent final scope document to ThermalTech for coordination of SOSS scoping.

6/30/11- SOSS completed and delivered to Bert Watts.

Justice Center Kitchen Flooring Study Read More »

JC – Flooring Replacement

07/01/11 – SOSS is submitted to Bert Watts.

07/14/11 – Signed SOSS and associated purchase order received by GBBN.

07/22/11 – Sample Agenda for Kick-off meeting sent to Bert Watts

07/26/11 – Bert Watts returns comments to Agenda to GBBN.

08/03/11 – Kick-off Meeting held at Justice Center with Sheriff and Facilities.

08/03/11 – Original Epoxy Resinous Flooring samples delivered to Jerry Voss.

08/11/11 – Second set of samples with sand mesh variations delivered to Jerry Voss.

08/15/11 – Jerry Voss reports the final selection for the epoxy resin has been made. The original smooth version was accepted.

08/16/11 – GBBN conducted kitchen equipment survey for main kitchen and ODQ serving line.

08/17/11 – Communications with Mobile Kitchen Rental company and Andre Tudor held.

08/18/11 – Conversations held with CPS about possibility of using old SCPA kitchen or Iowa Street Bake Shop for temporary JCC kitchen held.

08/29/11 – GBBN meets with Jerry Voss to retrieve samples of epoxy flooring and to take some clarification dimensions.

08/31/11 – Conference calls with two Mobile Kitchen vendors to discuss potential units for use and technical requirements for utilities and installation requirements.

09/14/11 – Meeting with Epoxy Flooring Systems and Key Resin to discuss logistics and details for replacement of the existing quarry tile and installation of the new epoxy flooring. Requests made for additional flooring samples, mock-up and existing installations to visit by the Sheriff’s Department.

09/20/11 – Meeting with JCC Building Manager and Trades to discuss utility improvement suggestions during flooring renovations.

09/28/11 – GBBN and TEI meet with Duke to discuss temporary electrical service to Temporary Kitchen Unit to be placed either in the JCC South Parking Lot or the B&B Parking Lot.

02/23/12 – County requested change order to have steam manifold piping replaced behind the steam kettles so Trades does not have to work in this space during construction.

03/08/12- Pre-construction meeting with CBS held at the Justice Center.

03/26/12 – ThermalTech, Debra and MSDC settled on a drainage system that is compliant with current code and the Clean Water Act. We cannot use the storm catch basin on this job. A secondary plan was proposed by the county to pump the discharge to the county catch basin near the Sallyport. TEI will issue this drawing as a Bulletin to the project.

03/28/12 – Mike Barth and Spencer Johnson of GBBN met with B&J Electric, Duke Energy, and CBS on site on 03/27/12 to discuss electrical service to the modular temporary trailers. The existing abandoned wood utility pole (on parking lot side of the fence) is a duke pole, and Josh Davidson of Duke stated that Duke will remove the pole at NO COST to the project while the work is being completed. Mike and Spencer notified Bert Watts, and He stated that he would like to see the pole removed if there is no cost. This information was forwarded to the contractors. This will make the installation of the temp electrical service to the trailers easier.

04/04/12- Meeting with Kitchens-To-Go and CBS to discuss finish floor height of temporary kitchen and loading docks.

04/10/12- Bert Wats initiates requested Change Order items for repair in existing kitchen.

04/12/12 – P201-EQ-5 drawing was sent to Spencer Johnson from Terry Cannon stating it had been completed on 4/3. The only item he was not 100% clear on is where the Zoeller pump would be installed into if Debra had a concept about that. Whatever they wanted to do was okay with Terry but this shows the routing, material, and protection scheme Thermal Tech wants to use.

04/18/12- Bert Watts approves Change Order Request for temporary kitchen loading dock redesign.

04/25/12- CBS sends Change Order Requests #1-9 to GBBN.

04/25/12- CBS sends Change Order Requests #10 to GBBN.

04/26/12- CBS informs owner that Duke and IBI have approved electric service for temporary kitchen.

04/26/12- Bert Watts approves Change Order #1 for CBS.

05/01/12- CBS sends Change Order Request #11 for additional signage.

05/01/12- CBS sends Change Order Request #12 for additional plumbing repairs.

05/03/12- Bert Watts approves Change Order Request #2.

05/08/12- Temporary Kitchen Equipment training for Kitchen Manager and Kitchen Staff.

05/15/12- CBS receives existing kitchen to begin demolition work.

05/18/12- CBS initiate request for additional time on contract.

05/22/12- CBS questions response to RFI-3 for mixer electric relocation. GBBN and ThermalTech response in favor of original response.

05/23/12- GBBN meets with CBS to review existing mud slab condition in Main Kitchen and Walk-In-Coolers and Freezers.

05/29/12- GBBN meets with CBS and GILL33 representative to discuss options to specified deep fill repairs. Representative confirms modified epoxy deep fill specification is correct methodology.

05/30/12- Change Order Request #15 is rejected and GBBN directs CBS to proceed with original concept for WIC/WIF mud slab repairs.

05/30/12- CBS sends Application for Payment #2. Only one copy is sent along with electronic version and letter describing Change Order Request directions about delayed payment for time extension considerations.

06/01/12- GBBN visits site with Key Resin to investigate WIC/WIF existing mud slab condition.

06/18/12- GBBN meets with CBS/Wesselman to discuss existing mud slab repairs.

06/.21/12- GBBN meets with CBS to review mesh/chair installation before pour of slab replacement.

06/25/12 – TTC and SJ have visited the site multiple times discussing the work on the floor and hub drains. additional drains were discovered during construction and those outlets were discussed too. Basically we are following the plan that is set forth on the design documents and not doing additional work.

06/27/12- Change Order #1 and #2 authored by GBBN. COP #1, 2, 3, 5, 7, 8, 9, 10 and 12 addresses in Change Orders including time extensions.

07/31/12- GBBN performs punch list review for WIC/WIF.

08/02/12- WIC/WIF Punch List issued.

08/12/12- Main Kitchen punch list performed at JCC Kitchen. Preliminary sent to Bert Watts for review.

08/13/12- Bert Watts sends minor revisions to punch lists and approves punch list to be sent to CBS after revisions are made. GBBN sends punch lists for Architectural, Equipment, Electrical and Plumbing to Bert Watts.

08/16/12- GBBN signs Application for Payment #4 form CBS and delivers to Bert Watts.

08/24/12- Bert Watts states the refrigeration trailers are now gone from the parking lot. Trailers are sealed and ready for transport.

08/29/12- Bert Watts confirms the trailers have been removed from the parking lot. One trailer unit remains to be removed.

9/19/12- Change Order #3 authored and sent to CBS after Bert Watts approves content.

10/10/12- CBS sends list of closeout documents for approval.

10/11/12- Bert Watts sends electronic version of contractor affidavit for Prevailing Wage Compliance to be added to list of closeout doucments.

10/23/12- Application for Payment #5 received from CBS. GBBN approves pending Bert Watts approval.

10/31/12- Response received from CBS and the plumbing subcontractor on the punch list items.

JC – Flooring Replacement Read More »

JC – Sheriff Data Center FP Upgrade

08/17/11 – TTC conducted a phone interview with JB Schmitt and Dalmatian. He went over the details of the project, timelines, permitting, scope of work, contractor assignments, background checks and proposed contract. TTC felt Dalmatian really understood the project best because it is mostly a clean agent system. JB Schmitt had some trouble remembering what all their sub-contractors were supposed to be responsible for on this job but they said regardless of that whatever was on the drawings was covered in their bid. Subcontractor work will include: GC – patching all the walls and clipping down the ceilings. Agreement was made that no permit is required on this job. Fire – Dalmatian will get their fire permit ASAP after contract PO is given to JB. They are providing the clean agent system and all the ancillary equip.

Elec – Had to power up the FPC panel and provide Fire Alarm interface and shutdown for CRAC unit and power to the mech for dampers. This has to be permitted too. Mech – HVAC dampers and installation. No permit for HVAC work, too minor. TTC recommends to proceed with the contract knowing to discuss the coordination at greater length at the pre const meeting where we can request the full project team to join us for the kickoff meeting or do that at the first const meeting where we can discuss the schedule with the tenants. All work during normal work hours was agreed to. Schedule is contract and PO by mid-October or so. Construction to begin in mid-November. Project complete be end of year.

08/18/11 – Contract for JB Schmitt was written and sent to Bert Watts for review and approval.

08/25/11 – Contract has been created for JB Schmitt. Ready for review and processing.

09/20/11 – BW has approved the contracts for this project. All background checks will need to be obtained and forwarded on to Bert. They will then need to be approved to work on the sites before the project starts up. BW notes the equipment in the data room is very sensitive.

02/22/12 – Inspection complete and approved by city. Ready to closeout project. TEI to request closeout.

03/28/12 – As-builts received and TEI to approve next week and send to Bert.

04/16/12 – Closeout O&M approved by Terry Cannon. As-Builts completed by Ryan Jacimine. All documents should be to HamCo on Tuesday 04/17.

04/17/12 -TTC e-mailed Tom at JB Schmidt that O&M’s were approved and he sent electronic As-Builts to the County. He is also approving Payapp #1 for $39,330.00 and the paperwork is done. There was a $2,500.00 allowance on this project which was billed for in Payapp #2. There is no supporting documents for that allowance usage. TTC asked Tom to send over an official request for those monies or if not used then a deduct change order can be written for that amount. The 3S O&M’s are fantastic, but they reference that no building fire alarm work was included in this O&M manual which is odd. TTC asked if Tom could get with Biederman and find out if there is an as-built programming drawing or reference sheet we need to pick up the new fire alarm point on the fire alarm system so TTC can at least include a one page in this O&M so someone at the County knows what module that is landed on.

04/17/12 – TTC sent electronic as-builts to Bert Watts and will drop off the O&M’s in the morning.

06/25/12 – TTC approved final payapp and sent to Bert. This should be the final documents required.

JC – Sheriff Data Center FP Upgrade Read More »

JC – 2010 Plaza Repairs

LEED Partner: THP

03/28/12 – All work complete; except asphalt patch at Courthouse ramp expansion joint. Asphalt patch along joint needs to be replaced. Currently waiting on warmer weather.

04/25/12 – THP requested final punch list schedule from RAM end of March with no response.

5/19/12 – Ram completed asphalt repairs. Ram completing concrete injection work with plans to complete work June 1. Final work is weather dependent.
Ram completed punch list repairs. THP to review status of closeout documentation with Ram.

9/26/12 THP Reviewing closeout status. All construction activities are complete.

JC – 2010 Plaza Repairs Read More »

JC GYM AHU Fall Protection

Partner Lead: THP

08/27/12 – County requested an SOSS for the design services for RTU fall protection.09/12/12 – THP had a meeting with Rodney. After meeting Rodney not sure of specific needs for fall protection. Rodney plans to review internally.

09/25/12 – County update: HC and CMI met to review equipment and operational access. CMI will review the condition and make recommendation; but currently a direction has not been determined. THP will be notified once a direction from HC and CMI has been determined.

03/12/13 – THP received and reviewed safety report recommending a platform without a ladder to access the RTU. Does the County want THP to submit a SOSS?

JC GYM AHU Fall Protection Read More »

JC RTU Fall Protection

Partner Lead: THP

08/27/12 – County requested an SOSS for the design services for RTU fall protection.
09/12/12 – THP had a meeting with Rodney. After meeting Rodney not sure of specific needs for fall protection. Rodney plans to review internally.

09/25/12 – County update: HC and CMI met to review equipment and operational access. CMI will review the condition and make recommendation; but currently a direction has not been determined. THP will be notified once a direction from HC and CMI has been determined.

03/12/13 – THP received and reviewed safety report recommending a platform without a ladder to access the RTU. Does the County want THP to submit a SOSS?

10/31/13 – Project on hold. Hamilton County reviewing need and scope.

JC RTU Fall Protection Read More »

JC Parking Lot Improvements

Partner Lead : THP

02/15/12 – Bids received February 15, 2012. John P. Tumlin is the apparent low bidder. The bid was within budget. THP to review the bids and provide a letter of recommendation (if appropriate).

03/29/12 – County processing Tumlin contract.

05/30/12 – Project start date on hold until completion of Justice Center kitchen and use of parking lot by temporary kitchen. Tumlin scheduled to start work September 1 and submittals should begin to be arriving at THP. 2. The County has requested the drawings be updated to reflect changes in the sidewalk adjacent to the parking lot. The sidewalk changes will impact the final parking count and slightly modify the perimeter of the parking lot. 3. THP and Tumlin working through submittals. 4. Anticipated work to start mid September.

09/02/12 – ThermalTech met with THP and County to discuss additional lights and cameras for project. ThermalTech to work with THP to get biddable document and charge to BW General Fund Number.

09/24/12 – Tumlin mobilized with fencing for phase I installed.

09/25/12 – Preconstruction meeting occurred. 3. 09/25/12 Tumlin plans to begin work on site the week of October 5.

10/05/12 – HC, THP, TTE and TJ Williams had a meeting to discuss additional lighting and security camera options for the project area. At the end of the meeting, pricing for the lighting and camera was requested.

10/22/12 – Tumlin provided proposals for the camera and lighting options.

10/22/12 – Tumlin provided a proposal for an asphalt overlay vs. a sealing repair option.

10/29/12 – Bert Watts approved the camera, lighting, and asphalt overlay options.

10/29/12 – THP directed TTE to complete electrical drawings reflecting the new work. Drawings will be used for permitting.

10/31/12 – Tumlin has submitted most items to-date. The fencing and line striping submittals are still in process.

11/19/12 – Change Order #1 executed. CO #1 adds asphalt overlay and deletes asphalt coating.

11/19/12 – Change Order #2 executed. CO #2 adds security cameras and lighting to the parking lot.

11/19/12 – Change Order #2 executed. CO #2 adds concrete curbing and adjusts the site fences.

01/30/13 – Project Updates: Phase 1 Trenching complete. Phase 1 Concrete and bollards complete. Phase 2 Concrete work 70% complete. North apron and entry only remaining work. Phase 1 & 2 Asphalt and line striping on hold until spring to allow for acceptable weather.

01/30/13 – Pay Application #1 approved.

02/26/13 – ThermalTech spoke with Andy at TJ Williams, and TJ is nearing completion of the installation. Waiting on inspections and Duke to energize panel at the booth.

02/19/13 – Pay Application #2 approved.

02/28/13 – Project Updates: Trenching complete. Concrete and bollards complete. Control equipment installed. Lighting Installed. Booth Installed. Asphalt overlay and fencing work on hold until weather is more conducive.

03/20/13 – Tumlin and THP had a meeting to review fencing posts. The fence subcontractor proposed a single post at the gate connecting both the chain link and architectural fencing. THP to review with the County on 3/28/13.

03/26/13 – Pay application #3 approved.

03/28/13 – Project Update – Per information on 3/20/13 meeting, Tumlin plans to begin asphalt work between mid-April to the May 1. Phase II will remain closed until all work is complete (asphalt, striping and fencing).

04/24/13 – Tumlin, the asphalt sub and THP met to confirm asphalt repair areas and discuss the project schedule.

04/25/13 – Project Update – Architectural fencing posts installed.

05/30/13 – Project Update – Asphalt, line striping and numbering complete. Fencing, final bollards and control equipment training to be complete by the end of the week. THP anticipates completing a punch review next week and final closeout paper work by the end of June.

06/27/13 – Project Update – Work complete except punch list. THP and Thermal Tech published list and Tumlin responding.

08/28/13 – PTZ camera on sallyport wall viewable but not controllable through Viconet software. Nor-Com not authorized Vicon distributor, and can not obtain drivers to make the Bosch camera talk to Viconet. TEI working directly with Vicon to attempt to resolve.

08/15/13 – Tumlin submitted initial paper work. THP reviewed and current package acceptable. Still waiting final submittal.
10/24/13 – Tumlin submitted change order for PTZ camera ($5,000 add). Hamilton County verbally approved.

10/30/13 – Hamilton County directed THP to process final change order for execution.

10/31/13 – THP issued final change order #4 (no cost).

10/31/13 – Tumlin waiting on subcontractor for final paper work.

01/30/14 – JM said they are down to one warranty item. BW said they have some issues to seal when it gets warmer.

03/18/14 – THP sent closeout paper work to Bert.

04/03/14 – Hamilton County, Tumlin, and THP met to discuss asphalt repair warranty issues. Repairs issues are minor and Tumlin will coordinate repairs with their subcontractor. THP publish an email to document the meeting.

05/17/14 – Tumlin completed all warranty work.

JC Parking Lot Improvements Read More »

JC Chilled Water Pumps

Partner Lead: TEI

10/18/13 – Small Project package Issued for bidding.

10/29/13 – Bid submitted by contractors, tabulated by ThermalTech and sent to Tony.

01/14/14 – Pre Const Mtg held with Peck.

01/17/14 – Submittals sent in by Peck.

01/28/14 – Submittal returned by ThermalTech FAC.

01/30/14 – PHB resubmitted pump package with larger impeller.

02/24/14 – ThermalTech check on status of order. No work back from contractor yet.

03/26/14 – TTC visited site to coordinate the leveling of the base of the pump vs the flange. After we discussed with the vendor, we are going to level the base, then provide a new flexible connector and spool piece as a change order to the project.

04/12/14 – Project is complete and ready for punchlist by ThermalTech.

05/15/14 – Punchlist scheduled in June. PHB working on closeout docs.

06/17/14 – Punchlist complete. PHB told to send in final payapp and close out the project.

JC Chilled Water Pumps Read More »

JC UPS Replacement

Partner Lead: TEI

01/30/13 – Project issued for bids, bids received and opened, Queen City Electric is low Bid. Waiting for Purchase order and signed contracts to conduct pre-construction meeting and give notice to proceed.

02/26/13 – ThermalTech, facilities, and QCE had pre-construction meeting on 02/22/13. QCE to supply list of employees to AKM for BGC verification. QCE sent ThermalTech a pencil copy of the Schedule of values to review. ThermalTech also reviewing the UPS submittals for release.

03/27/13 – Product submittals reviewed and approved. QCE to schedule replacement pending delivery of equipment.

04/24/13 – ThermalTech Contact QCE – requested that they send in the names of all working on project and the site specific safety plan for the project. QCE to send in schedule for work based upon days after delivery of equipment.

06/26/13 – South tower UPS (80 KW) load bank test had (2) failed attempts. first the trucking company did not deliver the equipment to site. Second, the load bank that Eaton brought to the facility for the load bank test did not work. Third test was successful, except QCE tripped 400 amp fuses in switchboard. AKM to send ThermalTech costs accrued by HamCo for 2 failed attempts and fuses to for back charge.

08/27/13 – Both UPS systems are installed. Both are on line. QCE to have final inspections and provide punch list and then closeout.

08/28/13 – Barth brought up at the Partner meeting the panel location coordination between the new UPS and Heat Pump Water heaters and egress issues between the two. We will see when the inspectors inspect this installation.

10/31/13 – Project was final inspected on 8/28. TEI to do final punchlist soon. Don’t closeout without getting certified payroll from contractor.

02/25/14 – TEI contacted QCE to discuss punchlist and remainder of closeout materials necessary to close out project. TEI scheduling punchlist (tentative date = 03/05/14) with Joe Merkt.

04/22/14 – TEI conducted punchlist visit while on site for Ameresco Arc Flash project field work. Punch list to be issued by the end of the week.

05/28/14 – TEI received final pay requests from QCE, and O&M manuals. TEI to review for completeness and forward to AKM upon reciept of approved COs.

06/25/14 – TEI received approved CO’s. Upon receipt of close out documents, TEI will process documentation for project closeout.

07/30/14 – TEI received all closeout documents EXCEPT warranty. TEI contacted QCE and upon receipt of warranty, will process final closeout documents.

08/25/14 – TEI receives at the end of the week of 08/18/14 the warrantee – dated valid from 07/17/13 through 07/16/14. MB contacts AKM to see if this is acceptable to HamCo. TEI contacted QCE to question if this was a “Typo”? TEI to process final pay application and closeout documents per AKM.

09/24/14 – Project Complete. Ready to Archive. Bert to send CAD files for Archibus update. TEI to update and send back.

JC UPS Replacement Read More »

JC LC/Pod Intercom Upgrades

Partner Lead: TEI

10/31/13 – Issued for bidding on 10/31/13.

01/24/14 – Contracts set to Bert Watts, waiting for approval from prosecutor to schedule pre-construction meeting.

02/25/14 – Contract in Phasor’s court to be signed and returned and sent to purchasing for purchase order. Tentative pre-construction date is 03/19/14 at 2:00 PM

03/26/14 – Project went to BOCC and was approved. Waiting for contracts and PO to schedule pre-construction meeting.

04/22/14 – Project preconstruction meeting scheduled for Monday 4/28/14 at 2PM, meet in the south tower lobby to discuss schedule, background checks, etc.

05/28/14 – TEI approved all submittals on 05/27/14 and Bert Watts issued Notice to Proceed on 05/28/14. Phasor to provide schedule and notice of all BGC from ICS.

06/25/14 – ICS has all of the head end equipment at their ship and is in the process of programming all of the equipment. A project kickoff with Bldg personnel, Sheriff’s personnel, Facilities, TEI and Phasor to be scheduled mid next week. Anticipated start date is on or around July 14, 2014.

07/30/14 – Phasor mobilized to Justice Center for work on this project. Currently installing all of the head end racks in each of the LC’s. Upon completion of install of the racks, and bolting in place, then Phasor to route 120 power to each of the racks. construction meeting scheduled for Aug 6, 2014 at 1:00 PM.

8/25/14 – All racks are installed in place in all of the LC’s. Phasor de-mobilized for approximately 2 weeks waiting on the delivery of the speakers for replacement in the pods. ICS received the first shipment (approximately 200 units) the week of 08/18, and the second shipment of approx 200 units has shipped and is scheduled to be delivered the week of 08/25. The order is scheduled to be completely fulfilled no later than 09/05/14. Phasor has re-mobilized on 08/25/14 to begin the replacement of the speakers, starting with the problematic unit in George 51.

09/24/14 – In the North Tower we have 289 new installed and approximately 140 old speakers left until we determine which we are going to use the Lexan plates on. In the South building, they have went through Lincoln 52 and were able to install 51 new and 5 existing were left in. They are currently working on Lincoln 51.

10/28/14 – The north tower is 100% complete with installation. The south tower is 100% complete with installation of systems on 3,4 and 5. ICS has placed order for balance of speakers that were not included on original order (receipt of speakers is approximately 10 weeks out – first of 2015). Phasor to pull off project after 10/29/14 punchlist with ThermalTech until such a time that speakers are on site.Phasor stated that the amount of remaining lexan plates should be adequate for the remaining scope of the project.

01/27/15 – The south tower is 100% complete with installation. TEI completed punchlist on 1/26/15 of the south tower. Phasor and ICS to complete punchlist and provide closeout documentation.

02/24/15 – Phasor submitted O&M manuals and as-built drawings to ThermalTech for review and submitting to the county. O&M’s turned over at the 02/26/15 meeting.

03/25/15 – project complete and can be archived.

JC LC/Pod Intercom Upgrades Read More »

JC FA Workstation Upgrade

Partner Lead: TEI

10/28/13 – Issued for Review to Tony and Joe. Saving FACP for re-use on this project.

10/31/13 – Issued for bidding 10/31/13.

01/24/14 – Contracts sent to Tony Matre, waiting on approval from prosecutor to schedule pre-construction meeting.

02/25/14 – Contract in Phasor’s court to be signed and returned and sent to purchasing for purchase order. Tentative pre-construction date is 03/19/14 at 1:00 PM

03/26/14 – TEI conducted a pre-construction meeting at site with Joe Merkt and Tony Matre on 03/19. Phasor Electric submitted to John Nester the list of contractors to work on site with BGC, for approval. As soon as BGC are approved, work to be scheduled. Anticipate all work on site to be completed in one work day.

04/22/14 – All background checks except Matt Biederman have cleared. This project to commence immediately upon the approval from BGCs.

05/28/14 – Workstation installed on 05/21/14. At point of install – there were 2 ground fault troubles. Phasor returned to site on 05/27/14 to address, and Joe Merkt indicated that the troubles were clear from the panel. Phasor on standby mode to see if they return.

06/25/14 – Ground faults cleared on the system. Upon receipt of closeout documentation from Phasor, the project will be processed and closed out.

07/30/14 – The panel developed an earth ground, plus another ground fault appeared on loop 7, in addition to a mis-matched device on AHU-C7A, and the printer was locking up. TEI contacted Biederman and Matt Biederman, Phasor, and ThermalTech met on site to develop action plan for all of the trouble codes that are occurring since the upgrade to the 3030 panel. A module and a relay was replaced by Phasor (received from Biederman), and the printer program was modified, and bldg manager is now monitor the condition and report back. Joe Merkt asked Matt Biederman to provide a cost to replace the existing printer.

09/26/14 – Closeout documents being processed, no printer will be installed. Bert asked if ground faults was resolved, we said yes.

03/25/15 – Project complete and can be archived.

JC FA Workstation Upgrade Read More »

JC Wall Mural Repairs

Partner Lead: GBBN

01/14/14 – John Nester contacts GBBN about a Kick-off Meeting to discuss the fallen panel in the Lobby.

01/15/14 – Kick-off Meeting held with Tony Matre, John Nester and Joe Merkt. It was decided to approach the issue with two possible solutions, remove and patch the walls or to restore the murals..

01/15/14 – GBBN makes email contact with Stephen Knapp the original artist and installer. Stephen indicated he would search his files for past documentation.

02/03/14 – GBBN and John Nester meet with Kramer Feldman Inc and Joe Merkt to discuss having KFI generate a proposal for both options, removal and restoration.

02/07/14 – Kramer Feldman Inc submits the proposal for both options to GBBN. GBBN forwards on to John Nester and Bert Watts.

02/11/14 – Bert Watts requests a SOSS for the solicitation of three proposals from selected vendors to perform the required work.

02/12/14 – GBBN submits the SOSS to Bert Watts.

02/25/14 – GBBN sends an email with the mural sizes and composition to Bert Watts for discussion with Artworks as a possible restoration source.

06/26/14 – Project on Hold.

09/26/14 – Bert said he has received comments on the mural and will send out a package to get mural updated.

JC Wall Mural Repairs Read More »

JUSTICE CENTER Drinking Fountain Upgrade

Partner Lead: TEI

01/26/16 – Have not made any progress on replacement drinking fountain bubblers since last meeting.

03/24/16 – TTC met with Dan Brewer and Mike Felton of Streamkey about the drinking fountain upgrades at the Justice Center. We will try to get factory replacement parts for a pneumatic style upgrade. More info to come from Acorn in the next few weeks.

03/25/16 – Streamkey sent an equipment cut and pneumatic upgrade diagram to ThermalTech for review.

03/29/16 – ThermalTech reviewed that data and sent to County for approval. We will probably go with a pneumatic assemble with a physical pushbutton arrangement that will be field installed by contractor. We are trying to get one mockup version from Acorn prior to bidding.

04/22/16 – Drinking fountain equipment specs continue with Streamkey. I believe we have worked out all the details and are ready to order one for install.

04/26/16 – Drinking fountain was going to be ordered through ThermalTech but now a new design was sent.

05/02/16 – Drinking fountain ordered and paid for by TTC.

05/25/16 – Drinking fountain is finished and should ship this week for next week arrival

06/09/16 – First drinking fountain delivered to County from Acorn. County to install in near future.

06/30/16 – Dan tried to install first retrofit kit and it did not work. Streamkey will be down next Wednesday at 8am to go over design changes on Acorn part. TTC will try to attend that meeting.

07/18/16 – Streamkey emailed County to ask for new date to meet everyone on site. County said they would contact Mike when Dan was back on site and available.

07/25/16 – Acorn sent new sketch to our standards except they denoted some pipe thread changes so the new piece will screw directly on to the old piece. New part probably 20 days out with shipping.

08/16/16 – The new part is in, Mike Felton and Dan are in email contact with each other about installing the new part for testing.

09/26/16 – This months test was a success. The retrofit works. TTC to update the original cost estimate if needed. [pic]

JUSTICE CENTER Drinking Fountain Upgrade Read More »

Justice Center Elevator Room Cooling

Building Operations Project

07/30/14 – Terry and Tony decided to use a PO from and old JC project and try to do this project with those monies. Do North building as Small Project Bid.

09/24/14 – SOSS approved. Joe on vacation. TTC to kickoff next week.

10/17/14 – Kickoff meeting complete. Mike Folck and Ryan Jacimine currently working on design and load calcs.

11/24/14 – Bids are in and the project came in at $22,038.50 for all three contracts. Debra Kuempel is the apparent low bidder on both the mechanical ($15,949.00) and electrical work ($2,247.00) and JCI ($3,842.50) for the controls scope. After bids were open Tony put the writing and awarding of this contract on hold

12/11/14 – Project on hold awaiting release from AKM.

01/27/15 – DK called about project. AKM confirms project is still on hold.

03/25/15 – Project still on hold.

04/27/15 – Project is on hold until further notice.

07/29/15 – Tony discussed starting this project up again. TTC contact original bidders to inquire if November bids are still valid. Debra and JCI.

08/26/15 – All contractors still on board with project. We are waiting to start this year.

09/23/15 – Tony approved the project and released ThermalTech to prepare the contract for Debra Kuempel and JCI for the work to upgrade the H&V unit.

10/28/15 – Contracts written for three vendors. Tony to get approval on Debra and JCI contracts.

12/08/15 – TEI contact Debra and JCI for hard copy paperwork for the contract. DK returned their immediately. We are still waiting on JCI.

01/26/16 – Contracts under review by Prosecutor and out for signature with vendor.

02/08/16 – Dave Gleason dropped off performance bond and Tony informed Nester we had the paperwork.

03/30/16 – Waiting on work to start by contractors. ThermalTech has returned all submittals.

04/15/16 – Tony says getting background check in order for work is underway.

05/20/16 – Vendors checked on status of PO for project, TTC inquired with Tony.

07/15/16 – Debra is completed with Mechanical work, Electrical work is supposed to be be completed today. JCI will be in next week to do controls and controls programming.

07/21/16 – TTC was on site Thursday to look at the installation. ThermalTech will release a punchlist to vendors. Unit is not started yet and JCI controls are not in place. Mechanical and electrical installation looks good so far.

07/27/16 – Talked to Debra and JCI. All work is complete, next step is that DK will perform startup on the unit and check refrig charge for us. The room control is the the thermostat on the wall. TTC may check OA return vs room recirculation for this unit.

08/04/16 – Unit was tested by Debra and all seems well. TTC to stop down and take measurements and check out room configuration.

09/01/16 – TTC to verify loads and check unit soon.

09/08/16 – Payapp 1 & 2 sent to tony from Debra. No payapp received from JCI yet. DK sent electric payapp #2 directly to Tony, TTC to retrieve.

09/23/16 – ThermalTech sent sequence instructions to County. Balance report from DK shows unit is running at 1400 cmf vs 2250 scheduled.

10/28/16 – JCI will be on site next Wednesday to look at programming.

11/16/16 – Debra turned in a $1000 change order which will be rejected on this project and picked up on a new project. This work was to resheave the the existing unit to speed up the fan and increase the CFM. JCI finished reprogramming the controls to match the ThermalTech sequences. TTC sent payapps #2 in for both DK mechanical and electrical for closeout on this project to Tony Matre. This project is read to archive and close.

Justice Center Elevator Room Cooling Read More »

JUSTICE CENTER Mobile Command Center

Partner Lead: TEI

09/28/16 – Kickoff discussion about electrical connections for mobile command center. They need a 50A double pole breaker for this mobile command center.

10/25/16 – TE met with trades, documents routing and connections. Project submitted to IBI for permitting.

01/25/17 – Installation complete. All inspections are complete. Project can be closed out and archived.

JUSTICE CENTER Mobile Command Center Read More »

JUSTICE CENTER JC/CH EGEN Study

Partner Lead: TEI

07/22/15 – Ongoing project that was on hold. Bert Watts directed TEI to complete the study. Work on study is on-going.

10/28/15 – Work is on going. Mike Barth and John Nester are coordinating the work with this study – and completing once the switchgear PM specifications package is completed.

03/22/17 – TEI will set up meeting with John Nester to kick this project back off beginning of April.

05/25/17 – Bert said to go ahead and wrap this survey up. It will probably be asked about soon. What strategy distributed or combined EGEN equipment?

10/26/17 – Project has been cancelled.

JUSTICE CENTER JC/CH EGEN Study Read More »

Records Center Asbestos Study

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sent list of buildings to be included in Asbestos Abatement Reporting.

03/30/12 – Meeting with Tim Schuh of Facilities Department to discuss Archibus Input Strategy

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

05/11/12 – Pinnacle notifies Mike Jackson that field investigation work will commence the following day.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

02/28/13 – Pinnacle sends GBBN a proposed completion schedule for remaining work.

03/18/13 – Tony Matre calls GBBN to request a status check on Pinnacle’s delivery schedule.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

02/24/14 – GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/Web Central is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14- GBBN sends another email and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

8/29/14- Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications with Tony Matre for final invoicing of these projects.

Records Center Asbestos Study Read More »

Mt Airy – Water Service Upgrade

08/31/05 – Dave stated that JFS will hold onto the next Neyer pay applciaton unitl some additional work is completed at the site. TTC said that is fine, TE will forward on the next pay app.

08/18/05 – TTC talked to Ken Neyer today and they will send the pay app directly to ThermalTech for payment. I will hold or sign it and send to Dave at the end of the project.

08/11/05 – TE stopped by the site today and talked to Robert and inspected the work to date. The new “hot box” looks good. We agree that you would advised to put bollards around the new water service backflow preventer. The pad is much closer to the roadway than I had envisioned and at it is going to need to be protected from road traffic. The trenches for the new water line are too low in some areas and too high in others. I believe Neyer is coming back to grade more in a week after another rain or two. Part of the roadway is still unfinished and according to Robert they still have some work down at the Rec Center which in looking at the site down there, I tend to agree. It appears that their pay application % are fine to me for the work they have completed. I didn’t get inside the main office to check on the electrical work for the heat tape at the time of this field trip.

08/08/05 – As of last week, I know that the PC was on site performing all site work and routing all the material into the cottages. One questions was raised and answered by the JFS. We received the first payapp on the project. TTC to hand deliver on 08/09.

06/13/05 – TE received submittals from Ken Neyer. They will be logged and sent to Dave Woodside for his use and approval.

05/25/05 – TE had pre construction meeting today via a conference call. PC is scheduled to start in about 2 weeks. They will send submittals to TE today or tomorrow. Dave reported that the Grant is valid until May 2006.

04/19/05 – Dave Woodside reported that the prosecutor has approved the contract and it was sent to Ken Neyer on 04/19.

03/15/05 – Second bid opening is complete. Ken Neyer Plumbing was the apparent low bidder. His bid is so low that TE is questioning the validity of the bid. TTC called Ken Neyer, Jr. on both Monday and Tuesday to go over scope and get confirmation that the bid is valid. TTC left another voice mail at 8:00 p.m. in hopes that we can get an answer in the morning to pass along to Dave Woodside.

02/25/05 – Second Prebid Meeting was held. One contractor came to the prebid. No new questions were asked that required an Addendum. Bidding should proceed normally.

02/16/05 – Bid Opened and were rejected due to improper contact with the Engineer and no contractors accepted Addendum 2 which was officially released and received by all.

01/20/05 – Addendum 01 distributed.

01/19/05 – Prebid Mtg Complete. CWW contact Nancy Drexler agreed that during the city water upgrade if we provide a backflow preventer in the first office and feed the rest of the complex after the meter that this would the meet the requirements of the CWW for backflow prevention. TE will update the bid package to reflect this design change in Addendum 01.

11/04/04 – TE to provide an SOSS to Dave Woodside

Mt Airy – Water Service Upgrade Read More »

Elevator Maintenance Bid

01/10/06 – TTC completed the escalator contract per Kerry’s comments and merged with previous comments. TA will hand delivery 4 copies to PBS today at 1:30 p.m.

01/09/06 – TTC delivered PBS elevator to PBS and bid tabs for their use.

01/06/06 – TTC delivered 230/800 contracts to Tony at the 237 WHT pre const mtg.

01/04/06 – Kerry returned electronic copy marked up. TTC to check over and approve.

12/21/05 – TTC returned electronic copy to Kerry for revisions.

12/12/05 – Contract revisions arrived from Kerry Dowling. TTC to make changes and send out ASAP.

12/09/05 – Kone called today to inquire about new contracts and cancelling old contracts for buildings they did not win under the new bid. Terry told them that new contracts should be forthcoming for official use by end of next week.

11/21/05 – TTC answered questions from the County about contracts. Everything appears to be in order.

11/17/05 – All contracts have been given to County for approval. TTC noted that there is no real need to have a supplementary conditions with the project manual as that is all outlined in the maintenance contract and we don’t use AIA contracts with this type of bid.

11/16/05 – TTC finished the elevator contracts for 230, 800 & PBS and sent them to Joe and Tony for distribution. This time, we coordinated issues like termination clauses, contract amounts with the combined bid savings and decided to split the savings 50/50 between the PBS and Facilities.

11/03/05 – After an initial scare that Addendum 01 did not get posted, Gina realized that the bid doesn’t open until 11/08 and therefore Addendum 01 is posted to demandstar and already has been sent from Ohio Blue.

11/01/05 – TTC is writing the Add01 for escalator project. This job should open next Tuesday. The SOSS has been signed for the escalator change order part of the job.

10/25/05 – Abell/Irvine called today to say that their office has been on Colerain Avenue since 1986. They have got their questionnaire answered and turned in with their bid. TTC ask Purchasing to fax a copy of it over to ThermalTech for review. TTC told everyone that the bid spec stated up to 5 buildings with 5 years experience. Tony called and discussed with TTC the new elevator contracts.

10/24/05 – Bids were opened. Fujitec did not bid the job. Kone didn’t their bid bond, Schindler withdrew their bid after TK’s opening bid, ThyssenKrupp and Abel/Lincoln turned in appropriate bids. TTC contacted both vendors for qualifications. TK provided a fax with all the documentation today. I have not heard from A-L but their number turned out to be long distance so I don’t consider that a good thing.

10/18/05 – The escalator bids immediately went back out on the street because no bid against Kone. Joe and Terry set the new bid estimate based on past numbers for the work in an attempt to make sure Kone didn’t try to overbid as they may be the only one entering bids on this project.

10/14/05 – The final addendum was issued to the contractors that dealt with questions from the prebid and mostly insurance and indemnity. TTC incorporated answers from the HamCo prosecutors office and risk managers for those issues. Also there is concern that one of the vendors does not have a full time office in the City as required by the bid. They also have not met the 5 project requirement of the specifications. This will have to be followed up on in the interview process.

10/03/05 – This Wednesday is the prebid meeting. I will meet Tony and Mike at 230 at 10:30 a.m.

09/21/05 – Project Manual completed and sent out for public bid. Bid opening scheduled for Oct 19th. Prebid mtgs scheduled on Oct 5th per everyone’s attendance request. Project budget estimated at $650,000.

09/20/05 – TTC completed the bid manual and sent out for review. All comments came back, TTC incorporated them into the manual and sent back to Maureen for advertising dates and SBA %. TE will turn over to County on Wednesday for bidding.

08/31/05 – Tony emailed today to say that TE is to keep the original insurance requirements from the original bid.

08/30/05 – Finalizing the bid process. Insurance requirements for Kone are final question before setting up public bid forum. Waiting on word back from Todd Dalton at Kone and AKM.

07/18/05 – Meeting went great. TTC has some work to cleanup old bid. AKM to inform TTC about 2020 building. Kone had some verbiage changes to contract. TTC has to modify bid form for combination bids.

07/12/05 – TTC setup a meeting with Tony and the elevator vendor for Friday.

07/05/05 – Project manual built by Sam. TTC has to get new information from Kone on new testing requirements. TTC talked to Sam Kinman today at PBS while on a walkthrough at PBS and was told that October’s escalator work is going to be an additional $30k on top of the standard contract. TTC will talk to Kone about new scope and testing for this bid and project manual.

Elevator Maintenance Bid Read More »

ADAS – Due Diligence MEP Study

11/03/05 – TTC contacted THP for coordination and kickoff on this project. We will wait till they contact us to start working directly with Wes Miller at the site. According to Mike Stiles, the building could certainly use an electrical upgrade that could be upwards of $1mil in cost.

10/25/05 – TTC and Wes Miller setup a walk through today for Sam and Mike to gather info for the SOSS for this project.

10/24/05 – TTC contacted Wes Miller, THP and Diana Supe about finalizing the SOSS for this project. It appears to be much larger than originally thought. KLH has already visited the site and did a walk through with the Facility Director Wes Miller. TTC will re-contact and set up a field trip for TE to build the SOSS by Wednesday.

ADAS – Due Diligence MEP Study Read More »

Energy Manager Project

01/16/07 – TTC compiled new format energy report and sent to Tony & Ralph. After December bills come in, TEI will present year end Energy report for Tony and Ralph.

06/01/06 – TTC sent Governors Award Application out for review. Markups will be incorporated and sent out UPS on June 2, 2006 to ODOD.

05/22/06 – TTC and Tony discussed the Governor’s Award for Energy that is due on June 02, 2006.

05/18/06 – Talked to Compass Energy about being an authorized buying agent for Hamilton County. There are so many things I like about this approach. I typed up and email to Tony to outline his benefits. We are awaiting approval to move forward.

05/05/06 – Strategic is very interested in bidding County work but mostly PBS. TTC sent the indemnity clause to them that County always requires and they want a conference call on 05/16/06 to discuss Q&A.

04/05/06 – After a second conference call, Tony has requested a write up from TTC outlining the possible cost and savings for bidding our dereg electric. TTC shall get this complete in a week.

03/23/06 – TEI sent Tony & Ralph the CCAO Report for 2005 updated with all the latest numbers. TEI sent Tony & Ralph the 2005 Monthly Report through December with the final CCAO numbers included. Next on TTC’s agenda is to update the yearly master and then the 2006 report for CCAO gas cost.

03/20/06 – Terry requested the Nov/Dec CCAO bills again as the latest packet doesn’t have them. TTC also contacted the CCAO for the information and talked to Amanda and she said she would fax them down to TTC but as of 3:40 p.m. they have not arrived. TEI cannot reconcile 2005 gas without this information.

03/15/06 – Talked to Joe Ewing today about Electric Deregulation Bid for county. We setup a conference call next week to discuss possibilities. TTC reconciled the 2006 Cinergy Rate schedule with an actual JC bill for February. This is a very big accomplishment towards reconciling the bills each and every month.

02/27/06 – TTC has to sign up for energy conference in Columbus. TTC and AKM discussed today on phone. TTC will drive up on Wed morning.

02/16/06 – TTC delivered the final report to Tony Matre and Ralph for use a couple of weeks ago but made one final change to the pie chart today. TTC is now working on deregulated electric and updating the individual building charts for a meeting with the bldg managers.

12/28/05 – TTC entered all the 2005 Gas data and got it input into the main spreadsheet for the County. TTC also began answering the CEC questionnaire.

12/09/05 – TTC discovered a billing anomaly in the CCAO billing for FT rate. It is a question that TTC can’t explain. The CH burnertip price is about $2 higher than the rest of the buildings for the same gas (it is all FT from the CCAO). Tony and Terry called the CCAO about the situation and left a message for assistance.

12/02/05 – TTC received the Energy Report packet today from the County that we will use as a template for LCC and this year’s report.

09/27/05 – Tony called and Terry sent our all 2004 Utility Data to Tony for his use. We sent a PDF and and excel file.

09/21/05 – First pass at Energy Star application yielded a grade of 33 for the 230 building. Passing is 75. TTC reviewed all data that Sam put into website. We believe that although we have additional data for additional months, this only hurts the ES score. Sam is removing extra months. The new score was in the mid 40’s. TTC manual calculated the buildings kbuth/sf to be 64.5 which is still lower than required for an Energy Star rating. TE is learning as we go on the application process for this website.

09/20/05 – Sam is currently entering 2004 data for 230 East Ninth.

09/16/05 – Set up user account at Energy Star for Hamilton County. We will be entering data for 230 East 9th Street for qualifications.

07/20/05 – TTC and Tom Kennedy met with Tony Matre and Mike Florimonte to discuss a proactive approach to getting the 230 East Ninth building LEED-EB certified. TE is to put together a business plan to make this work for the County

07/20/05 – TTC received the Alliance To Save Energy rejection letter for our March 2005 submission on the IT rate at the Courthouse. TTC forwarded the letter to Tony Matre.

07/19/05 – TTC finished the electric utility reports up through June 2005 and distributed to the County. TTC will work on reconciling the gas utilities next.

07/13/05 – Tony sent the CCAO summary to TTC for inclusion in to the energy files.

06/03/05 – TTC submitted the 2005 Governor’s Award to the State of Ohio. PDF. TTC submitted all 2004 energy data to Ralph for reporting.

05/26/05 – Downtown Six Pack Cinergy bills should started to arrive today at ThermalTech. There is no need to continue to copy Cinergy bills for EM work. I know will receive all the bills I need to do the monthly tracking. This should save Pat and Donna some work each week. If by chance I am missing one or two, I can request those manually.

05/20/05 – TTC has spent the better part of 3 days re-writing the TE software to accept all the new Cinergy Market Generation Riders so that I can correctly calculate and reconcile the energy bills for 2005. I estimate 2 more days of work before they are approved for use.

05/10/05 – TTC picked up Energy Authorization letter and will request data from Bill Fleisnner.

04/27/05 – TTC requested a County release for new energy data and to be authorized for the e-clips program to see Cinergy bills online, plus receive duplicate bills for the main 6-pack of buildings. The County should provide this letter.

03/31/05 – TTC sent in “Stars in Energy Alliance Application” PDF

03/25/05 – TTC startup monthly charts showing electric and gas, usage and cost and plotted on column graphs. TTC synchronized data with Tony’s local disk.

02/25/05 – TTC completed all the 2004 Energy Pulse Data Input. Graphs printed for 6 pack buildings. I am started to reconcile data vs. pulse data. A lot of energy bills are missing from 2004 and I have to contact Cinergy to get the actual bills for comparison. That request should be made on Tuesday.

02/18/05 – TTC attended the 9th Annual Ohio Energy Conference in Columbus and tabulated the 2004 237 WHT Energy Data.

02/11/05 – TTC will be working from TE and attending the Ohio Energy Conference next week for 2 days.

02/10/05 – TE registered TTC for the Ohio Energy Conference today. See you in Columbus next week.

02/08/05 – TTC collected more bills and is having Laurie at TE re-organize the bills by year, building, then service for easier updating..

02/04/05 – TTC got 230 E9th electric input for 2004. Looks like building has started using more energy and more 24/7 hours. TTC pointed out on graph to AKM.

02/02/05 – All 2004 bills have been tabulated. TTC and AKM set a schedule of having Energy Star program applied for by May 2005, having LEED-EB applied for by May 2005 and having Deregulated Electric bid on street by May 01, 2005. Cinergy has provided ALL 2004 interval electric data in an email today.

01/28/05 – TTC organized bills collected from 2004 for water, gas and electric.

01/2 1/05 – TTC organized bills collected from 2004 for water, gas and electric.

01/14/05 – TTC created water spreadsheet for 237 WHT. There are unexplained phenomena that need further investigation.

01/07/05 – TTC requested data from all current registered Cinergy Suppliers for Deregulated Electricity for County Bidding Purposes.

Energy Manager Project Read More »

XPEDX – DUE DILIGENCE STUDY

05/21/07 – The team presented the both phases of the Due Diligence study and the BOE move in programming and cost to Jeff Alluto, Diana Supe, Kevin Maue and John Michel and Bill Stautberg today. We went over existing conditions and possible future costs if the BOE takes occupancy of the building. Phasing plans and cost were turned over to the owner for this report. MEP wise the building is in good shape and will work for this and future needs.

05/14/07 – TE has DK on site for mechanical HVAC testing. TEI visited the site last week to get more FPC, EC and PC information. Report is due for review this Friday with MD and partners.

04/27/07 – TE awaiting signed SOSS.

04/18/07 – TE got prices from one contractor to perform Due Diligence on the AHU’s units at the site for $1900. We have a couple of request still pending.

04/17/07 – TTC & TA visited the site with CRA and THP and County Officials to take pictures, look at equipment and assess the requirements to prepare the Due Diligence Report.

XPEDX – DUE DILIGENCE STUDY Read More »

CMC Evaluation

05/22/09 – Report delivered. We are in question and answer phase.

04/15/09 – In progress – due 4-13-09. Pending signed SOSS for CR-107a and CR-107b.

03/18/09 – 50% draft submitted.

03/13/09 – SOSS CR-107a and CR-107b submitted.

02/18/09 – Kick-off meeting held.

01/27/09 – SOSS signed.

01/12/09 – SOSS Requested.

CMC Evaluation Read More »

BLACKOUT/VULNERABILITY STUDY

04/27/07 – The final report is going to be delivered to Hamilton County Facilities Department today, April 27, 2007.

04/20/07 – TE received word from Hamilton County Facilities and are currently working on the final report.

04/13/07 – TE awaiting word from Hamilton County Facilities to proceed with final report.

04/03/07 – TA turned over draft copy report to Mark Donnelly by hand for review.

03/30/07 – Project progressing as expected.

03/23/07 – Hillcrest and Patrol Hdqtrs are complete. 800 Broadway is scheduled for next week.

03/20/07 – Patrol Hdqtrs fieldwork is complete. Hillcrest is scheduled in the next couple of weeks. Whole project is scheduled to be completed by end of March 07

03/14/07 – Patrol Headquarters, 800 Broadway and Hillcrest Campus have been added to the list of buildings to be evaluated. Field work for Patrol Headquarters and 800 Broadway has been performed. Hillcrest will be completed next week.

02/28/07 – 5 out of 6 original buildings have the report completed and turned over the Hamilton County Facilities Department.

02/19/07 – TEI will wrap up this project. 3 buildings are left to complete. CH, CAB, River City, Coroner’s Office are complete.

02/02/07 – The write up is very nearly complete on this project. TA is hoping to finish today.

11/03/06 – Write up is progressing

09/29/06 – Field trip is scheduled for week of 10/02/06

09/22/06 – Field trip is scheduled for the week of 9/25

09/15/06 – 5 out of 6 buildings are complete. Working on 6th next week.

BLACKOUT/VULNERABILITY STUDY Read More »

2010 COST ESTIMATES

07/24/09 – The cost estimates were finished on Wed 07/22 but Bert found several that needed more work or were empty. We finished these today. TTC reviewed every project new and old for completeness. The LEED portion was difficult and I an not 100% sure the data will be totally usable by HamCo fo its 2010 needs but it is the first step towards getting greener buildings. The projects are complete. CRA will be printing manuals for the next 5 days.

06/23/09 – TTC reviewed the Rebuild America and ECM Screening Tool with Tim and issued the original cost and scope documents to the team for updating our scope items for the cost estimate project. I have found several projects that are duplicates and especially have some questions about the Hillcrest site where they appear to be repeated twice and maybe three times. Terry will call Bert to discuss.

06/19/09 – The SOSS is approved and we have begun visiting the buildings. Terry and Mike have been to the 250 WHT building. The remaining projects are being coordinate by several TE employees for field trips next week. For this project we will have Terry, Tim, Andy and Mike Folck performing mechanical estimates. Mike, Danny and George will be performing the electrical estimates. Today we had our internal TEI kickoff meeting and internal Archibus training for input.

2010 COST ESTIMATES Read More »

BOARD OF ELECTIONS Third Floor Renovation

10/16/08 – Bert reports the BOE is very happy and has given Facilities a kudos for the work.

08/22/08 – Permit is in County hands for IBI. Bert said city permit was also received.

08/08/08 – According to City Permit Tracker Website this project is APPROVED.

08/01/08 – TEI has submitted three drawings to IBI for permit for this project.

09/05/08 – Permit approved in August. TEI submitted final payment for permits so final inspection can be scheduled.

BOARD OF ELECTIONS Third Floor Renovation Read More »

FIRE ALARM & FIRE SUPPRESSION MAINTENANCE BIDS

02/02/10 – Cintas submitted paperwork for a change order cost to the JC work for 2010 based on building count inaccuracies. TEI may review? No word on Tony on what he needs.

12/31/09 – The only development aside from all contract being approved is that JCI will not agree to the contract published with the project. The Admin bldg is going to have to be inspected outside the scope of this project. TTC recommended Hamco take out a change order on SA Communale contract and get them to do the building for 2009. A separate agreement will have to be reached with one of our vendors to get the 2009 testing complete. Tony is working on final contracts.

09/11/09 – TTC sent final contracts to Tony for delivering to Kerry for review. We have 5 contracts on this job and everything is under budget. SA Communale got most of the buildings, Cintas, JCI and Simplex each got one of the buildings.

08/25/09 – Addendums 1-5 have been sent out and extended the bid to Sept 4. One company protested the bid and forced Addendum 5 and we published the actual service contract with the last addendum for their use.

07/29/09 – We have collected almost all of the building summary sheets for the project back from the building managers. TTC & DPC are working on the new spec, combined bid forms, etc for the large Addendum.

07/15/09 – Addendum 01 went out to bidders and extended the bid opening date to August 19th.

06/23/09 – Today was the first prebid meeting and it was less than stellar. The addendum on this project will be quite large and we have to get better equipment counts in all the buildings. The printouts that were provided do not have all the equipment the contractors want to see for an accurate bid. We will most likely extend the bid opening by one month, detail the scope of work better, combine the bids, rework the building summary sheets, take combined bids for better pricing, add an alternate for the five year required testing and add an alternate for the County workers to self perform all the weekly and monthly testing.

FIRE ALARM & FIRE SUPPRESSION MAINTENANCE BIDS Read More »

ELECTRICAL DEREGULATION 2009

01/28/10 – Talk to PBS & Tony. All paperwork should be in. There are some lingering questions about contract signee’s and interval meters at several locations. As these get solved to the satisfaction of DERS these accounts will be brought on line too.

12/31/09 – Contracts are being signed. Interval meters request have been sent out. TTC forwarded the emails to hamco directors for signature and suggested everyone accept option 2 where the cost $446 each of the interval meter be rolled into the monthly bills for 24 months. Bill Fleissner is our contact at DEO for this. There was significant conversation between Matre and Cannon about us believe the entire cost was under $1000 for interval meters. DERS indicated 11 accounts required them. TTC rebuffed that by providing interval data on 9 of those accounts. DEO came back with another 19 that required it because peak demands were over 100kw not 1000kw as TTC believed. In the end written documentation is clear that the threshold is 100kw. PBS has already signed and faxed their approval to DEO. Final contracts and insurance have been worked out between Kerry, Tim and DERS. TEI provided backup savings calcs for the groups approving DERS savings estimates at significantly lower numbers (DERS numbers include cost savings and cost avoidance savings as one lump number).

10/20/09 – We have about five vendors registered and we have extended the contract question phase. We are opening the project on Nov 19. We have no contract questions yet on this project.

09/22/09 – Tony and Terry discussed insurance requirements with Tim Grabenstein for this contract. TTC sent the final copy for review to Tim. TEi asked for comments back by Friday.

09/21/09 – Contract comments came back from Tony and Kerry. Jim and Terry merged them into a final contract. We received the ITB-92-09 for this project. TEi will issue the final documents for public distribution on Oct 1. Contract questions and comments will be due Oct 15th. Bids are due in November.

08/19/09 – We completed our meeting with the Prosecutor’s office RSM will write a preliminary contract. TEI will write the end. 6 certified suppliers will be invited. Ralph will present to the commissioners for their review. Ralph, Tony, Kerry and myself have agreed to the plan.

07/20/09 – TTC sent Tony a revised SOSS for bidding out electrical services for the County. Ralph also asked about the Voltage Guard hardware which TTC and NV replied that TEI was very weary of this technology. We are doing more investigation.

06/23/09 – The report is approved and we have presented the results to the Commissioners. There are a few projects for energy savings that we should pursue in this year.

ELECTRICAL DEREGULATION 2009 Read More »

Archibus Drawing Updates

6/18/10-Met with Jack Randle of In4 and Michelle Ray of Hamilton County Facilities Department to discuss In4 scope of work verses Architectural Partnership scope of work. First Floor of Alms and Doepke mentioned. Michelle to investigate status.

6/21/10- Received email from Bert Watts with attachment documenting building drawing red-marks for correction.

6/22/10- Verified with Bert Watts the First Floor of Alms and Doepke is to be added to list of drawing corrections.

6/23/10- Submitted SOSS to Bert Watts at monthly Partner Meeting.

6/29/10- Approved SOSS delivered to GBBN.

7/02/10- Drawing updates completed and reported to Bert Watts.

Archibus Drawing Updates Read More »

2011 Project Request Estimating

4/26/10- Bert Watts discussed Estimating Project at Monthly Partner Meeting

5/8/10- Bert Watts email with attachments listing Partner and Project Manager Project List received.

5/12/10- GBBN received estimates for services from Mike Strine at Pinnacle Engineering for Asbestos Abatement Services.

5/13/10- GBBN submitted SOSS to Bert Watts.

6/23/10- Met with Walt Heckel of THP to coordinate all projects involving “All Partners”.

6/23/10- Conference call with Susan Barrett of IPM to discuss Communications Building Projects estimated earlier by IPM.

6/24/10- GBBN submits proposal requests to vendors for printing and assembly of project binders.

7/01/10- GBBN met with Bud Wells at Parkhaus Garage to discuss vegetative roof project request

7/02/10- IPM/GBBN visited Communications Center to discuss two project requests.

7/03/10- GBBN visited 2020 Auburn to discuss and document two project requests.

7/18/10- QCR delivers final binder tab revisions to GBBN to allow for final binder assembly.

7/19/10- Deliver project request binders (9 sets) to Bert Watts at the Courthouse.

7/20/10- Record set of Binders delivered to MEP Partner TEI.

7/22/10- Bert Watts delivers revisions to Binder Summaries for GBBN to insert into sets for partners.

7/23/10- Record set of Binders delivered to structural Partner THP.

7/27/10- Bert indicated the binders are to be slightly realigned from GBBN’s submission. Bert will take the 9th set of binders and realign them for GBBN’s reference. GBBN’s current office copy set of binders will be delivered to IPM for their records.

7/29/10- GBBN to received 9th set of binders from Bert Watts at the monthly partnering meeting.

2011 Project Request Estimating Read More »

Workforce Investment Board Vestibule Renovations

Current Comments (5/26/2010)

Project complete. Working on closeout documentation. CRA completing work.

Past Comments

Masonry repair work in progress.

Vestibule removed and new vestibule under construction.

New piers anticipated next week.(2/24/10)
Contractor completed demolition of vestibule.(2/24/10)
Sink Hole investigation:
Dug test well to footings and no fill below footing.
Pumped 5 yards of flash fill into void.
Plan to complete second test well on adjacent wall.
All phases of work approved.
THP subconsultant to CR Architects.

Workforce Investment Board Vestibule Renovations Read More »

2012 Project Cost Estimates

06/27/11 – Project 1208 was updated. Barth already had the cost separated as Bert wanted.

06/24/11 – Project estimates are complete. We are currently putting final touches of the estimates for this year.

05/24/11 -started field work on most estimates. Several have been input. Added one based on field work.

04/27/11 – We will be kickoff off this project next Monday and doing the work in May 2011.

2012 Project Cost Estimates Read More »

Emergency Generator PM Bid

06/29/11 – Tony reported today that the contract is approved.

05/03/11 – ThermalTech turned over final paperwork to Blaine for contract writing.

04/27/11 – Engineer’s office is writing a one year contract, Comm Center asked me to looked at three year bids and Tony asked me to write a contract for five years for the Facility buildings.

03/30/11 – Bids are due Thursday at 11am. TTC will attend. Three Addendums have been sent out on this job. We are taking prices on base bid, alternate and unit prices.

02/25/11 – Project is out for bidding. Prebid Mar 11, Bid Opening Mar 24. Note: TTC has to fix bid form for more clarity on bid day.

02/22/10 – Tony and Mike have approved the project manual and TEI will be sending to Jill Williams for bidding on Friday Feb 25.

Emergency Generator PM Bid Read More »

ENERGY MANAGER 2011

08/25/11 – Ameresco work is in final stages for contract negotiations. More controls meetings are schedule. Ameresco is presenting final report early Sept.

07/29/11 – 10 color copies of the final report have been mailed to Ralph per his request. The 2010 Report is complete.

07/07/11 – Energy Star bills have been entered for 230, Admin, and 800 Broadway. Field trips were scheduled for 230 and Admin, but have to be moved back to July 26 to coordinate with Florimonte vacation.

06/24/11 – Ralph said that he is sending Jeff’s questions over for final changes.

05/04/11 – Deliver 2 hard copies to Tony & Ralph today. Ralph said that if Jeff Aluotto approves this report, we can print these in color and be done. Also for 2011 report, he would like Hillcrest added, 237 WHT removed and the water data expanded.

04/26/11 – Delivered the final report to Ralph for 2010 including water from 2009 and 2010 completed for all major buildings. In 2011 we will add water for the remaining buildings and try to back date that information to 2007. We are trying to update the Energy Watchdog website before the final import at the end of May. It is nice to report that we saved over $1,000,000 in 2010 on our 3 major energy conservation measures.

03/30/11 – TTC finished inputting water bills. Thursday Amy will integrate into the report. Friday, Terry will finish the report.

03/14/11 – Duke has confirmed that ThermalTech has correctly included all the Administration Bldg electric into the Energy Star website. With this information, we are going to move forward with Estar approval.

03/01/11 – TTC has to add the deregulated electricity calcs to the report.

02/22/11 – TTC gave Ralph and Tony their final copy to review. Comments are back and TTC will finalize to give to Ralph for review by EOB on Friday.

01/24/11 – Folck has entered all bills that have been received. Terry and Amy are starting the Energy Report this week. Hopefully to be completed early February.

09/29/10 – All bills ThermalTech receives have been input into Watchdog. Next week have to do the bills kept at the CH.

07/28/10 – We are working on the new HamCo RFP with a couple of ESCO. RFP’s are due Aug 16.

05/26/10 – We received the 237 bills. Folck will input them. We will then generate the April bill.

05/06/10 – We modified Energy Watchdog to allow us to start entering electric commodity for Hamilton County ins 2010. Folck will enter all bills to date starting this afternoon.

04/26/10 – We delivered 10 copies of the final report to Ralph last Thursday. We delivered an updated electronic copy with the years of each project added to the Appendix today per Ralph’s request. We will continue to update bills in Energy Watchdog.

03/22/10 – Ralph and Tony have returned the Energy Report with comments. TTC will compile the final report. All previous reports uploaded to web.

03/05/10 – ThermalTech sent the final report to Ralph and Tony for commenting. TEi will compile the final report when comments are returned.

02/24/10 – Attended the 14th Annual Ohio Energy Conference with Tony & Ralph. Got the Energy Report about 50% complete. We are adding new buildings this year which means fixing the baseline model from 1997 and forward. It is harder than expected and taking longer.

02/22/10 – We have collected all utility data for 2009 and input into our worksheets

02/04/10 – Energy Watchdog data is input for 2009 for all buildings except for missing CCAO bills for Courthouse. We are working on the 2009 report and trying to finalize all the bills.

01/28/10 – Terry and Amy will be updating the report in Feb 2010. Andy is putting in the Watchdog data and Energy Star data this week.

12/31/09 – More bills are being input. The energy watchdog website should be up to date by mid January.

09/22/09 – Some bills are missing. TTC contacted Tony about Coroner’s gas bills. Jackson called about Coroner’s office water usage. TTC emailed the 2010 cost estimate report and explained the cost and program to reduce water usage.

08/19/09 – We completed our meeting with the Prosecutor’s office RSM will write a preliminary contract. TEI will write the end. 6 certified suppliers will be invited. Ralph will present to the commissioners for their review. Ralph, Tony, Kerry and myself have agreed to the plan.

07/20/09 – TTC sent Tony a revised SOSS for bidding out electrical services for the County. Ralph also asked about the Voltage Guard hardware which TTC and NV replied that TEI was very weary of this technology. We are doing more investigation.

06/23/09 – The report is approved and we have presented the results to the Commissioners. There are a few projects for energy savings that we should pursue in this year.

05/22/09 – The final report was turned over to the commissioners and we attended the commissioner meeting on 05/18. Mike Folck is updating all the water bills from 2009 and 2009. All data has been entered into Energy Watchdog through April 2008. We are not updating our monthly sheets until next year.

04/05/09 – The report is ready for TTC to review. I will get this done this week. I emailed Ralph & Tony about working with Ameresco on the 2009 energy projects.

01/26/09 – TTC & MAF finished the ECM Summary table and sent to Ralph Linne & Tony Matre. Ralph forwarded it to Jeff Aluotto for use. We are awaiting and update on how to write the SOSS for the work.

ENERGY MANAGER 2011 Read More »

2012 Project Estimates

Current Comments (9/28/2011)
Past Comments

Project complete.

THP added 250 William Howard Taft assessment into Archibus.

June 6 THP updated Archibus entries for 1431 and 1432.

Project estimates completed and loading into Archibus June 3, 2011.

THP reviewing project estimates, deadline for data entry into Archibus is June 3.

May 5, 2011 SOSS approved.

THP developing SOSS.

March 31, 2011 requested SOSS to complete 2012 project estimates.

2012 Project Estimates Read More »

2012 Project Request Estimating

03/31/11- Kick-off Meeting with Bert Watts during regular monthly Partnering Meeting. Tabulation Lists to be issued to all partners.

04/28/11- SOSS delivered to Bert Watts at monthly partnering meeting.

05/16/11- Met with Scott Lemond of ARC to discuss printing schedule and deliverables.

05/12/11- GBBN and IPM visited with Greg Smorey of the County Engineer’s Office to discuss the CAB 8th Floor Phase 2 Renovations.

05/18/11- Met with Greg Smorey of the County Engineers Office to review scope of project request for the Phase 2 renovation of the 8th floor not renovated in Phase 1.

05/31/11- Meeting with Greg Gelhaussen of the County Engineer’s Office at Ripple Road Engineer’s Garage.

06/14/11- All project Request Estimating is closed and completed.

06/23/11- Bert Watts email indicating three Project Requests have been eliminated.

06/27/11- Bert Watts email indicating one additional Project Request has been eliminated.

06/30/11- Deadline for all consultants to complete any requested revisions to Project Requests.

07/05/11- Delivery of electronic files and lists of projects to ARC printing

07/27/11- Binders received from ARC printing. Bert Watts accepts delivery from GBBN

07/29/11- GBBN delivers and installs corrected spline and cover slipsheets.

08/05/11- GBBN delivers partner sets of binders to THP and IPM.

08/25/11- GBBN delivers partner set of binders to TEI and CD’s of 2011 and 2012 to all partners.

2012 Project Request Estimating Read More »

2011 General Services

01/14/11-SOSS submitted.

01/21/11- Bert Watts forwarded the new Contractor Safety and Health Specification section that is to be included in all future HCFD project manuals.

01/24/11-SOSS signed by BOCC and issued to GBBN along with Purchase Order.

01/25/11- Modified Standard Bidding Documents to indicate Christian Sigman as Interim County Administrator.

01/27/10-Attended HCFD Partnership monthly partner meeting.

01/27/11- GBBN forwarded to the other Partners the revised Master Specification Table of Contents and Legal Wrap showing the inclusion of the new Contractor Safety and Health specification section.

02/04/11- The meeting with Amy Hoh to kick-off a new project to modify the existing office partitions was cancelled.

02/14/11-Kick-off meeting with Sean Winfield of CAGIS to initiate an estimate to enlarge the CAB 10th Floor Conference Room.

02/15/11- Bert Watts agreed to perform the CAGIS work under this contract in lieu of a SOSS.

02/18/11- Drawings and estimate for CAGIS project sent to Bert Watts.

02/24/11- Attended the regularly schedule Partnering meeting at the Courthouse.

03/12/11- Met with Bert Watts to review the as-built conditions at Parkhaus Retail spaces. GBBN took measurements and photographs of space

03/15/11- GBBN sent as-builts to Bert Watts for review. Additional MEP input to be performed by GBBN due to lack of involvem,ent by ThermalTech.

03/25/11- Meeting with GBBN, ThermalTech and Duke Energy to discuss potential energy savings and partnering programs.

03/31/11- Attended the regularly schedule Partnering meeting at the Courthouse.

04/28/11- Attended the regularly schedule Partnering meeting at the Courthouse.

05/11/11- Interior Project Management performed background checks at the Justice Center. GBBN delivers results to Diana Supe.

05/12/11- GBBN staff performed background checks at Justice Center. GBBN delivered results to Diana Supe.

05/26/11- Attended the regularly schedule Partnering meeting at the Courthouse.

06/23/11- Corrections for new County Administrator made to standard front-end specifications.

06/30/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated after Partnering Meeting.

07/06/11- Meeting with ThermalTech to review Courthouse Courtroom Ceilings for redesign of the soffits and ceilings with Tony Matre.

07/29/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated before Partnering Meeting.

08/25/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated before Partnering Meeting.

09/29/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated before Partnering Meeting.

2011 General Services Read More »

Record Center Storage Facility

Project Lead: GBBN

08/18/11 – Call from Bert Watts to discuss needs for permitting.

08/19/11 – GBBN contacts County of Hamilton Zoning. Indications are the City of Cincinnati is AHJ.

08/19/11 – GBBN contacts City of Cincinnati concerning Zoning and Permit Requirements.

08/22/11 – GBBN reports back to Bert Watts concerning permitting and structural requirements. Bert Watts requests SOSS be generated.

08/22/11 – GBBN delivers research into Use Group and Storage Code Requirements to Bert Watts.

08/24/11 – Bert Watts reports that Facilities is waiting for Clerk of Courts approval to place storage unit on site.

09/14/11 – Bert Watts sends documentation of basis of design structure to GBBN.

04/09/12 – Call placed to VersaTube for heavier gauge metal panel order to comply with Fire Rating Design.

05/04/12 – Footings poured after inspection and approval of formwork by Building Inspector.

05/25/12 – GBBN meets with VersaTube representative to take delivery of missing components.

05/28/12 – GBBN finalizes translucent panel order with VersaTube

05/30/12 – Payment send overnight for translucent panel order.

06/20/12 – Delivery service called to request fence be opened for delivery of extra panels.

06/27/12 – Graybach confirms latest extra panel delivery has been received.

07/23/12 – Inquiries to Graybach to determine when work to recommence on site.

07/24/12 – Graybach sends updated schedule for completion of project.

07/24/12 – GBBN visits site to review fallen fireproofing. Gates locked and only observation from outside gate.

07/25/12 – GBBN visits site and photographs and documents progress and remaining items to be completed. Reports to Bert Watts.

08/27/12 – Punch List site walk through performed.

08/28/12 – Punch List sent to Bert Watts and John Nester for review. After approval from both the punch list sent to Graybach.

08/29/12 – Graybach confirms final inspection approval received from City of Cincinnati Buildings and Inspections.

10/22/12 – Graybach instructed to complete as-built drawings showing actual built foundation dimensions.

10/30/12 – GBBN reports to Graybach Change Order invoice to be paid by end of this week.

03/08/13 – Graybach sends letter from City of Cincinnati Permit Office about closing out the Special Inspections on this project.

03/09/13 – GBBN contacts Thelen about logistics for completing the Special Inspections.

03/20/13 – Special Inspections visit by Thelen scheduled. Visit is postponed due to snow.

03/22/13 – Special Inspections re-visit by Thelen scheduled. Visit is postponed due to snow. again.

05/15/13 – Thelen; to send Special Inspections from to City of Cincinnati Buildings and Inspections.

Record Center Storage Facility Read More »

Record Center Second Accessory Building

Project Lead: GBBN

09/27/12 – Call from Bert Watts requesting SOSS for second similar facility on the same site.

10/02/12 – GBBN submits SOSS to Bert Watts.

10/03/12 – GBBN receives approved SOSS.

10/23/12 – GBBN submit preliminary bid package to Bert Watts for Owner review.

10/26/12 – Bert Watts gives conditional approval of documents. Awaiting approval from Ralph Linne before final distribution to Purchasing.

10/27/12 – GBBN receives ITB information from Purchasing for Legal Wrap.

10/30/12 – Bert Watts notifies GBBN of Ralph Linne approval to bid.

10/30/12 – GBBN sends documents to Purchasing and ARC Reprographics for Bidding and Distribution.

10/31/12 – GBBN copies of bidding documents received from ARC Reprographics.

02/07/12 – GBBN receives signed SOSS back from Facilities Department.01/21/2- GBBN received stamped engineering calculations from VersaTube.

01/03/13 – GBBN submits permit application to City of Cincinnati Permit Center.

01/10/13 – GBBN delivered signed and stamped updated surveys to the City Permit Center.3. 1/15/13 Facilities sent signed contract and PO to Graybach to begin submittal process.

01/16/13 – Graybach acknowledged receipt of contract and will begin process of approvals with VersaTube.

01/02/13 – GBBN attends Zoning Variance Hearing. Preliminary approval granted.

01/03/13 – Official Zoning Variance Letter received.

01/18/13 – GBBN receives telephone call from City of Cincinnati Permit Center indicating permit has been approved. GBBN forwards information and final permit cost to Graybach.

02/18/13 – Graybach begins excavation for footing installation.

02/19-13 – GBBN reports to Grayback frozen ice is laying in footer trenches. Graybach arrives on site and pumps water out of trenches.

02/20/13 – Graybach pours concrete foundations.

02/26/13 – GBBN visits site and notifies Graybach blanketing is blown off footings. GBBN requests damaged gutter strap be repaired on existing building when new building erection commences.

03/21/13 – Graybach informs GBBN that building framing sent by building manufacturer is incorrectly sized for the 16–0″ required width.

03/22/13 – Graybach issues letter to building manufacturer to inform them of the width discrepancy.

03/27/13 – GBBN inquires with Graybach about additional information on corrective measures. Graybach responded that corrective materials were delivered by the Building Manufacturer 03/26/13 – Graybach intends to recommence work 04/01/13

04/01/13 – Graybach receives corrected truss framing members to continue construction.

04/17/13 – Graybach notifies GBBN that all four corner trim members sent by building manufacturer ware sent too short. Construction can’t continue without correct trim pieces. GBBN instructs Graybach to get correct full length trim and not piece together add-ons.

04/23/13 – GBBN sends inquiry about delivery date for correct trim members and projected date for recommencement of construction.

04/29/13 – Missing pieces received from building manufacturer. Graybach to resume work this week.

05/14/13 – Missing pieces have been installed. Interior studs and lath to begin next week.

05/15/13 – Thelen; to send Special Inspections from to City of Cincinnati Buildings and Inspections.

05/21/13 – GBBN visited the site and determined the remaining work is the spray applied fireproofing, overhead door, gutters/downspouts, painting and door hardware.

05/23/13 – GBBN visited the site and took progress photos.

05/30/13 – Interior Fireproofing studs information and details sent to Thelen for Special Inspections.

06/05/13 – Spray applied fireproofing to be installed.

06/12/13 – Graybach had spray applied fireproofing inspection with the City of Cincinnati. The overhead door was installed.

06/19/13 – Gutters, downspouts, painting and door hardware installed.

06/24/13 – GBBN visited site and noticed two downspouts, not one per the drawings, have been installed on each of the front and back of the building. This error was brought to Graybach’s attention before the drain tile was extended to receive the new building storm drainage.

07/19/13- GBBN visits site and conducts punch list inspection. GBBN forwards punch list to County and Graybach.

08/23/13 – Graybach sends proposal for proposed Site Allowance requested work by County.

08/25/13 – Graybach forwards proposed storm piping support detail to County and GBBN for review.

09/04/13 – County authorizes Graybach to order EZ Sleepers and miscellaneous materials for storm drainage anchorage. Graybach hopes to work on site Monday 9/9/13.

09/09/13 – GBBN visits site to review materials and detailing of storm drainage anchorage. GBBN sends details to County for review.

01/23/14- GBBN contacts Graybach about final closeout documents and final payment status.

01/24/14- Graybach indicates closeout documents ready to send. Final Inspection completed with the City of Cincinnati Building Department. No final Certificate of Occupancy documentation received yet.

01/27/14- GBBN contacts City of Cincinnati Building Department to inquire about final Certificate of Occupancy. Informed that former inspector has retired. Joe Luster is called to inquire about status and voice mail left.

03/07/14- GBBN receives return telephone call from Jim Zimmer of the City of Cincinnati Buildings and Inspections. He indicated the final inspection was performed by the City on 07/18/13 and all was found to be in compliance. Waterworks signed off on 02/18/14 and was last remaining department required for final sign-off. Final paperwork and project closeout is now ongoing by the City.

Record Center Second Accessory Building Read More »

RECORDS CENTER Masonry Investigation

Partner Lead: THP

02/03/16 – County staff reported masonry cracking throughout the building, and requested THP investigate.

02/25/16 – THP visited the site, confirmed the conditions, and is developing a SOSS.

03/24/16 – THP provided an SOSS for review.

04/04/16 – County approved the SOSS.

05/26/16 – THP completed field investigation of the facility. THP developing analysis and final recommendations.

07/26/16 – Draft report finished.

07/28/16 – Plan to publish final report by August 1st.

08/01/16 – Draft report published to Hamilton County for review.

08/08/16 – Hamilton County Returned comments and THP published final report.

RECORDS CENTER Masonry Investigation Read More »

RECORDS CENTER Slab & Facade Repair

Partner Lead: THP

08/16/16 – Hamilton County requested a SOSS for all phases of work noted in THP’s report dated 8/8/16. Soil investigation, design and bidding to be completed by early December. Construction schedule anticipated Spring of 2017.

08/18/16 – THP met with Terracon to develop the soil investigation proposal.

08/23/16 – THP published SOSS for review.

08/18/16 – THP met Terracon at site to review existing conditions for purposes of receiving a proposal for geotechnical services.

09/07/16 – THP met Terracon at site to confirm and mark interior and exterior borings and test pit locations.

09/12/16 – Terracon completed exterior borings.

09/13/16 – Terracon completed interior borings.

09/21/16 – Terracon completed test pits, and THP observed and surveyed exterior elevations.

10/11/16 – THP received Terracon’s preliminary documents from field work and soil testing.

10/14/16 – THP issued documents for Owners Review.

10/18/16 – THP issued Bid Set of documents.

10/25/16 – Prebid meeting completed at Records Center.

10/27/16 – THP issued Addendum 01.

11/03/16 – THP issued Addendum 02.

11/17/16 – Bid opening. KFI and SSRG submitted bids, and SSRG was apparent low bidder.

11/18/16 – THP conference call with SSRG to review misc. questions about bid.

11/18/17 – THP issued letter to Hamilton County recommending SSRG be awarded the project with all 4 alternates accepted.

12/02/16 – THP emailed pdf of AIA Owner-Contractor agreement between County and SSRG for review.

12/06/16 – THP delivered hard copies of AIA Owner-Contractor Agreement to Hamilton County.

02/21/17 – SSRG emailed THP submittals for micropiles.

02/27/17 – THP reviewed and returned SSRG’s submittals for micropiles.

03/23/17 – Project update: SSRG working through background checks of employees and THP scheduling preconstruction meeting.

04/03/17 – THP published submittal log and sent back mortar submittal as revise and resubmit.

04/04/17 – THP reviewed and returned submittals for masonry, sealant, and coatings.

04/27/17 – SSRG working through background checks. Pre-construction meeting anticipated in mid-May (after background checks are complete).

05/01/17 – THP received and reviewed pencil copy of Application for Payment #1 from SSRG.

05/03/17 – Preconstruction meeting at site with Hamilton County, SSRG, and THP.

05/03/17 – THP visited SSRG warehouse to document steel tubes and brackets in storage.

05/04/17 – THP issued notes from preconstruction meeting.

05/19/17 – THP met SSRG at site to review sealant samples.

05/22/17 – THP approved Application for Payment #1 and delivered to Hamilton County.

05/31/17 – Progress meeting with project team, and THP site visit to document progress.

06/01/17 – THP issued 5/31 meeting notes and field report #1.

06/01/17 – THP reviewed and approved SSRG Application for Payment 2, and delivered to Hamilton County.

06/07/17 – Progress meeting with project team, and THP site visit to document progress.

06/07/17 – THP issued 6/7 meeting notes and field report #2.

06/14/17 – Progress meeting with project team, and THP site visit to document progress.

06/15/17 – THP issued 6/14 meeting notes.

06/16/17 – THP and SSRG met on site to document quantities of unit price exterior tuckpointing completed at CMU walls.

06/21/17 – Progress meeting with project team, and THP site visit to document progress and coordinate with SSRG and ECS Construction.

06/21/17 – THP issued 6/21 meeting notes and field report #3.

06/22/17 – THP emailed status of unit cost quantities to SSRG and Hamilton County for review.

06/07/17 – THP received and reviewed pencil copy of SSRG application for payment 3.

06/28/17 – Progress meeting with project team, and THP site visit to document progress, develop punchlist, and document quantities of unit price interior tuckpointing with SSRG.

07/27/17 – All work complete except punch list and power line area work. SSRG scheduling with Duke Energy a shut down.

08/02/17 – THP visited site to review completion of punchlist items, and met with SSRG to review mortar samples for tuckpointing repairs to be completed at northeast corner of building.

08/11/17 – Duke Energy interrupted electrical service.

08/12/17- SSRG began cash allowance work.

08/13/17 – SSRG finished cash allowance work, and Duke Energy re-established electrical service.

08/17/17 – THP visited site to review completion of cash allowance work.

08/21/17 – THP issued field report no. 5 from 8/17 site visit.

08/22/17 – THP received and reviewed pencil copy of SSRG Application for Payment #4.

09/05/17 – THP reviewed and approved change order #1 and contractor’s fourth application for payment, and delivered to County.

09/06/17 – THP developed as-built drawing set and emailed to County and SSRG.

09/28/17 – SSRG assembly closeout documents.

10/09/17 – THP received and reviewed project manual binders from SSRG, and requested revised warranty documentation from coatings manufacturer.

10/16/17 – THP received revised coatings warranty and updated project manual binders.

10/26/17 – Waiting on closeout documents to archive this project.

10/23/17 – THP received final application for payment from SSRG and requested additional required AIA closeout documents.

10/30/17 – THP received and reviewed AIA documents from SSRG for final application for payment, and contacted SSRG about status of lien waivers for subcontractors.

10/30/17 – THP delivered project closeout binders and SSRG’s final application for payment to Hamilton County.

11/09/17 – THP received and reviewed subcontractor lien waivers, and emailed SSRG about providing new documents with corrected information.

11/20/17 – THP received revised subcontractor lien waiver documents from SSRG and forwarded to Hamilton County.

11/27/17 – THP received approved/signed copy of SSRG’s final application for payment.

RECORDS CENTER Slab & Facade Repair Read More »

PATROL HQ Asbestos Study

Project Lead: GBBN

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sent list of buildings to be included in Asbestos Abatement Reporting.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/Web Central is ongoing. GBBN was granted access to the database to complete the drawing downloads. Electronic drawings for SPHQ campus had to be generated for Facilities CAFM partner to input into Archibus. TEI and Facilities deliver existing drawings and electronic files to GBBN for creation of electronic drawing files.

07/01/14 – GBBN sends another email and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

8/29/14 – Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications with Tony Matre on final invoicing for these projects.

PATROL HQ Asbestos Study Read More »

Sheriff HQ – Electrical Device Identification and Arc Flash Study

05/30/08 – Ginter sent the panelboard schedule in excel format. TEI forwarded to County and sent allowance usage certificate to Ginter for signing. Ginter has to provide an approved IBI permit at conclusion of this project.

04/09/08 – All Work is complete. TEI will finish and stamp the permit drawing for Ginter. Ginter will get IBI for making the conference room on emergency panel for colonel. This will use the last of the allowance money and closeout the project.

01/07/08 – Ginter has completed punchlist items. MAH will conduct back check when meeting on extra work takes place. The Colonel would like to have some receptacles on emergency power in the conference room so they can use as a command center. The work will be discussed with final approval from Tony Matre.

12/14/07 – Change order was requested for Ginter to access the $2000 allowance. TEI has requested additional itemized backup and an explanation of the additional devices from Ginter. Jim Ginter sent the additional items to TEI and MH is reviewing for approval today. MH created the punchlist for the project and is distributing the punchlist to the contractor today as well.

12/11/07 – Construction meeting was conducted and punchlist was created moving toward a final closeout. Punchlist items will take a few weeks because of the lead time in ordering engraved labels. Aside from some misunderstanding in the labeling requirements the work appears very thorough. Ginter turned over mark-ups. Ginter to submit pay apps and TEI to write a deduct change order for unused allowance.

11/30/07 – As promised Ginter reported today that this project is complete. TTC responded back to their email that we would use the const mtg for our punchlist and to advise about allowance usage on this project so TEI could write a deduct change order for closeout. TTC also sent all the closeout documents to Ginter for use on this job.

11/28/07 – Ginter provided an update today stating the the ID project was going well. TEI will setup a const mtg the week of 12/10.

11/09/07 – TTC distributed Pre Const Mtg minutes from last week. Ginter is on the job and ready to complete by the end of this year.

08/31/07 – TTC received word from HCFD that the insurance issue has been resolved. TEI awaiting word from HCFD so that this project can move into the Construction Phase.

08/15/07 – NR wrote: “Any idea about when this project is going to be ready for construction?” Bert( HCFD) responded: “I am still working out Insurance issues with Michael Ginter, he is working on getting me the correct Certificate of Insurance. Jim and I are working on getting the LEADS background checks completed.” TEI awaiting word from Hamilton County Facilities Department to move into construction phase.

08/10/07 – TEI awaiting word that the contract has been signed by Ginter Electric so that this project can move into the construction phase.

07/30/07 – NR received word from Bert Watts at the Hamilton County Facilities Department that the contract was sent to Ginter Electric last week for their signature. TE is awaiting word that the contract has been signed so that this project can move forward with the construction phase.

06/29/07 – TE awaiting word that the contract has been signed to that this project can move into the construction phase.

06/22/07 – Contract has been awarded to Ginter Electric. The contract has been sent to Mark Donnelly; TE is awaiting signed contract to proceed with pre-construction meeting.

06/15/07 – Hamilton County Facilities is reviewing the bid tabulation. TE is awaiting word about which contractor has been awarded the contract so that we can move forward with this project.

06/08/07 – This project opened for bid yesterday. TE is awaiting the bid tabulation from the Hamilton County Purchasing Department.

06/01/07 – This project is set for bid opening on June 7, 2007.

05/25/07 – The pre-bid meeting was held on site today. Those in attendance included Kevin and Steve Kallmeyer of Kallmeyer Electric, Jim Ginter of Ginter Electric, Nick Richmond of ThermalTech Engineering, and Walt Hendrick/ Mike Jackson/ Ken Caruso of Hamilton County. A site tour was given as well as a specification and drawing review. This project is expected to go to bid on June 7th of 2007.

05/21/07 – Project went out for bid on May 18, 2007. Pre-bid meeting has been scheduled for Friday, May 25 at 10:00am. Meeting place is the lobby of the Patrol Headquarters. NR contacted Captain Mark Hendrick to discuss working hours. It was decided that normal working hours would best suit this project because of limited access to certain areas of the facility. NR sent an email to Mark Donnelly informing him of this.

04/27/04 – Drawings for the Device Identification portion of this project are complete and will be present for Hamilton County review in the meeting today, April 27 of 2007. The Arc Flash Labels are at the printer and should be completed within the next 2 weeks.

04/20/07 – Arc Flash Labels are being dropped off to the printer next week. The Device Identification portion of this project is complete and the drawings will be complete next week.

04/13/07 – Single Line Diagrams have been established and Arc Flash Study has begun. TE found discrepancies with the As-Built drawings and what was found in the field so they are making another field visit today, April 13, 2007. This visit is meant to trace the source of the panels in the barns and out-buildings. There is an automatic transfer switch in the Property Room that needs to be traced also. Dan Myer of TE will also be on site to meet with a county employee to locate above ceiling equipment.

04/06/07 – Kick-off meeting was held. Project is moving along as expected.

03/30/07 – Kick-off meeting is scheduled for next Thursday, April 5th of 2007.

03/23/07 – Project progressing as expected. Kick-off meeting tentatively scheduled for the first week in April. TE to set up meeting with Hamilton County Facilities.

03/20/07 – Fieldwork is progressing and is about 80% complete.

03/14-07 – NR created project journal and filled in back data from previous meetings. Project awaiting signed SOSS to be returned to TE. 90% of field work has been completed for the Device Identification portion of this project. Field notes not inputted electronically per awaiting signed SOSS.

Sheriff HQ – Electrical Device Identification and Arc Flash Study Read More »

SHERIFF PATROL HQ Street Widening

09/29/10 – Project closed and archived.

08/16/10 – We talked to Debra Kuempel today. O&M’s were submitted and I believe sent to the County last November. We have been holding for the final change order. Kevin and Donna at DK agreed the Change Order Credit was going to be $5761 for this job. Laurie is typing, we will delivery for signature to DK today and then they can get their closeout docs in order and we can close this job.

08/13/10 – Payapps updated for both contractors. As Built dwgs completed by TEI. QCM needs to sign the change order and send to Bert.

07/28/10 – Check on DK change order work and approve as-builts for project completion.

05/26/10 – DK is installing the fiberglass pan in June. We are awaiting QCM closeout docs.

05/15/10 – TTC is working on closeout documents for QCM. We have the final payapp but I don’t know if we have the O&M manuals so I contacted QCM again to check the status.

04/26/10 – Project is complete save the fiberglass pan issue.

03/23/10 – DK got an okay to provide pricing for a new fiberglass drip pan for the panel as we wait for THP to work on better site drainage.

02/22/10 – TTC signed additional payapps for QCM and DK for payment on this job. We are ready to close it out. There is an issue about a ground fault alarm and wiring on the fire pit. DK said they may just replace the wire and be done with it.

12/31/09 – Debra Kuempel did the overnight work on the conduit sealant upgrade and I believe we are down to final closeout. We have a warranty issued with the pit having a grounding issue at the fire alarm panel. DK has sent a technician to repair.

10/20/09 – TTC sent out punchlist today to contractors with instructions to closeout project. We are accepting CO#09 for blacktop from QCM. We have to work out the $10,000 allowance with Debra Kuempel and the $7500 with QCM for this project to write the final Change Orders. The email included instructions to closeout and finalize change orders and allowances.

09/22/09 – The project is nearly complete. TEI will be performing the punchlist in the next few weeks. DK is going to be on site on Thursday to finish up their work. Queen City Mechanical submitted change orders for processing today. We received a new COR #8 for piping. TEi asked for more info on this change order. We should be able to close out in a month.

08/26/09 – Final tie-ins for both fire protection and fire alarm are being made. By the end of this week, everything should be 99% complete and ready for punchlist.

07/27/09 – Bert and Terry talked last week about having TEI modifying our permit to list the Fire Pit as existing equipment. TTC called but the Inspectors office was closed. I will try back again later. The County has asked for the CWW to submit their drawings and apply for a permit for the work separately.

06/23/09 – All the permit issues have been resolved. TTC contact QCM mechanical by email and phone to get an update on status of fire main trench. No update but TTC will check on 06/24 when he visits the site for the FA project. DK has not been back to the site since the new power was brought back online. We believe they will return when they work on the trench with QCM.

05/22/09 – DK has finished the transformer relocation. The building is back up on Duke power from the new transformer. The cables are being collected for pickup. Prus provided the new fire main and fire pit for us. QCM will be out 05/26/09 to begin trenching the parking lot for the remaining work on fire alarm and fire sprinkler work.

04/03/09 – TTC sent an email update to the team for the pit, given it is located in the parking lot. Tony is going to look at the final location. Bert and Tony to advise. Luckily, we talked about this happening in the pre construction meeting.

02/19/09 – GCWW has brokered a deal to have Ray Prus provide the water tap to the R/W for QCM from the new water main. Ford Development will build the pit from that location. We have asked for a credit from QCM for the smaller scope.

02/0509 – QCM informed us that a new water main is being installed in Hamilton Ave. I advised QCM to investigate using that main instead of the one we originally projected for use.

02/02/09 – TTC modified the project schedule and sent out for approval to all the vendors. Jackson questioned the actual shutdown and switchover date but TTC told him that was not set in stone yet. The City has approved the water permit. We are waiting on ODOT approval of the plans before digging.

01/05/09 – Payapp #3 came in for DK and ThermalTech approved and sent to Bert. This payapp went to Bert first which may delay this payment.

10/16/08 – ThermalTech sent profile drawing to QCM for submission to state. TEI sent new permit drawings to Debra Kuempel for permit application. DK is getting price from Duke for work on this project per the scope of work on the specs as TEI wrote.

08/29/08 – Contracts approved. Pre Const Set for next Thursday.

08/22/08 – No update from County. TEI inquired about proceeding. Tony answered that contracts will be in front of the Board next Wed. 08/27.

08/08/08 – Tony reported the Prosecutor has contracts for approval. They are pushing hard.

07/31/08 – County reported that all contracts are at Prosecutor’s Office awaiting approval.

07/30/08 – TEI has delivered all contracts to Contractors for signing. TEI sent stamped permit drawings to Queen City Mechanicals for CWW permit application. QCM stated that CWW will want permit tap fee as soon as permit is awarded. This process may be the longest lead item of the whole job.

07/18/08 – Pre Award Meeting complete. All contractors recommended for project. Debra and Queen City Mechanical both stated they understood the project, the schedule and agreed their price was valid for this scope.

SHERIFF PATROL HQ Street Widening Read More »

SHERIFF PATROL HQ Signage Upgrade

01/24/11 – TTC asked for a written letter from KFI to proceed with closeout as the punchlist is not fully complete as the scratches on the sign have to be touched up.

10/28/10 – We have visited the site several times as the foundation has been poured, electrical has been run and masonry work is ready to begin.

09/29/10 – Holding for State to complete road work.

08/13/10 – Payment 1 has been sent.

07/28/10 – TEI to approve payapp and send to Bert. It looks good, have to visit the site to see the sign.

04/26/10 – We are on hold until June.

03/23/10 – It has been reported that the sign is complete.

02/24/10 – John Brockman called with a question about backlighting the can. TEI will return the call.

02/05/10 – TTC visited Ernst signs and worked out final details on the sign building scheduled for April. TTC updated all parties.

12/31/09 – TTC submitted a permit answer to HamCo building inspections. The next step is theirs. We may have to resubmit to start the project again.

09/22/09 – The new street is very close to the sign. The County is working with ODOT to finalize the sign work. Our contractors are preparing a new shop drawing to the County permit office with the galvanized steel frame.

07/29/09 – No updates because Street Widening is still on hold.

06/23/09 – KF has not returned our call or emails about sign permit approval. At this time it is being held for review by Marty in HamCo Bldg Dept awaiting our clarification on how the sign post will be embedded into the sign base and what material it will be. We may need a meeting or conference call with KF and Brockman signs.

05/22/09 – Zoning has approved our sign permit. The bldg department is questioning the supports for the sign. Tom Speer is checking his design for us.

03/02/09 – Pre-Construction meeting held. KFI will order materials and store sign at HQ to allow invoicing. On hold until street widening is complete.

SHERIFF PATROL HQ Signage Upgrade Read More »

Patrol HQ – Parking Lot Security

06/14/11 – The Lighting submittals were returned to TJ Williams on 5/19/11 and the fence submittals were returned on 5/27/11. Mike Barth spoke with Andy last week and he is estimating that lights and fence would be coming in over the next few weeks. Mike will call Andy again this week to get update.

06/29/11 – The pole light is not going to be acceptable to be reused on the ground due to size. We are working on a replacement light and updating our drawings to reflect the changes.

07/28/11 – MCB stopped by Patrol HQ and reviewed completed installation of flood lights. Installation of fence is complete. Upon receipt of closeout documentation from TJ Williams, closeout procedures will be completed.

Patrol HQ – Parking Lot Security Read More »

PATROL HQ Grease Interceptor

Project Lead: ThermalTech

06/25/13 – Drawing complete

04/10/13 – TTC met Dan on site and walk the scope. TEI owes Bert the SOSS for the work to be done internally and permitted by TEI.

05/24/13 – Approved SOSS received. Design has begun.

08/19-13 – Permit is approved with comment. Blue Chip has sent an invoice to ThermalTech for payment which we will pay and reimburse. We may need to install a backwater valve between the interceptor and the main sanitary drain line in the Sheriff Patrol HQ. TTC to find elevations on site survey that he thinks he has from Tom Speer for this area and give to permit office.

09/26/13 – All permit questions answered. Permit approved. Stamped drawings provided to County for work.

10/15/13 – Dan says interceptor is ordered but will be installed next season.

06/20/14 – Multiple Record drawings created and stamped and dropped off to County for plumbing dept approval. We believe the interceptor is installed and working and approved by the County Plumbing Dept.

07/30/14 – Checked on permit status. City website says Permit not approved but final inspection

09/25/14 – Blue Chip contacted to initiate permit closeout. Additional fees requested and approved by TEI, BC says final permit closeout is started and should be finished in a week or two according to Kathy at Blue Chip.

10/23/14 – Project and Permit are both final and closed out. Website list permit as “Final”

PATROL HQ Grease Interceptor Read More »

PATROL HQ Kennel Project

Project Lead: GBBN

09/30/14- GBBN receives email invitation to visit Patrol Headquarters to investigate addition for a Kennel and to investigate an operable partition renovation to the Comm. Center.

10/07/14 – Met at site for field kickoff meeting. Got tentative layout from deputies on site. Two cost estimates are required. With and without Trades doing work.

10/07/14- GBBN receives email from Bert Watts about estimate project requests created in Archibus for estimating.

10/09/14- GBBN sends first iteration of Patrol Headquarters Kennel addition floor plan to Facilities and TEI for review.

10/14/14 – ThermalTech spoke with Hamilton County Plumbing Department and MSD to confirm no special plumbing requirements are necessary for the trench drain outlet at this project. A removable cover trench drain wit interior FD cap was requested by Plumbing Dept. ThermalTech to update estimate.

10/15/14- GBBN completes estimate for Patrol Headquarters Kennel addition.

10/16/14- GBBN receives comments and suggested floor plan revisions for the Patrol Headquarters Kennel estimate.

10/20/14- GBBN sends updated Patrol Headquarters Kennel floor plan to TEI and Facilities for review and estimating.

10/20/14 – Received updated Kennel drawing. Estimate needs to be updated in Archibus for both projects 1771 and 1772. We will need two Mitsubishi type units, one for the office and one for the main kennel area.

01/30/15 – Facilities Department requests GBBN and TEI revise preliminary plans based on Sheriff’s Department review comments and to update estimates in Archibus.

02/04/15 – GBBN and TEI notifies Facilities the preliminary plans and Archibus estimates have been revised and updated.

02/14/15 – Preliminary design costs sent to Facilities at their request.

03/25/15 – Project on hold.

04/07/15 – Project still on hold.

PATROL HQ Kennel Project Read More »

PATROL HQ Reznor Heater Replacement

Project Lead: TEI

10/17/13 – Met Jackson at site for fieldwork.

10/25/13 – Vendor provided one for one replacement and rooftop model for bidding Base Bid and Alternate.

10/31/13 – Review drawings to be delivered to County for bidding as small project.

01/24/14 – Final bids came in during November. Waiting on Tony Matre to decide if we are moving forward with this project.

03/26/14 – Project may be on hold or done later. Ameresco work is currently being done at SPHQ.

0/6/20/14 – Project still on hold.

11/18/14 – Project rebid per Tony request. New Bids due Nov 26.

11/26/14 – Bid extended to Dec 3.

12/03/14 – New bids received. PHB was the apparent low bidder this year.

12/11/14 – New contracted drafted and sent to Tony with all the attachments for Prosecutor approval.

01/27/15 – Comments returned by Kerry, updated by TTE and sent back for approval. We are awaiting Pre Const Mtg. Peck has already sent submittals.

03/23/15 – Submittals reviewed. Equipment matches specs, when we kickoff this building.

04/14/15 – Held kickoff meeting for project.

04/28/15 – ThermalTech distributed meeting minutes from kickoff meeting. Submittals have already been approved.

05/25/15 – Contact PHB about status of project and equipment delivery.

05/26/15 – Submittals reviewed by TTC and forwarded to Tony, Mike and Paul. TTE requested an updated project schedule for use on this project.

06/24/15 – TTC checked in on progress with PHB

07/15/15 – Peck met Jackson on site to start laying out new work.

07/28/15 – TTC gave Bert the Energy Impact Study for this project.

08/26/15 – Peck scheduled to do startup on this project this week.

09/18/15 – TTC checked out unit install while on site. Project looks good. Owner can closed out the project as soon as closeout paperwork is received.

10/08/15 – MCB checked out unit while on site. Ready to archive.

PATROL HQ Reznor Heater Replacement Read More »

PATROL HQ Heliport Windsock

Lead Partner: TTE

06/24/15 – TTE requested support for Heliport project and THP providing budget numbers for SOSS. ThermalTech updated SOSS to deliver at Partner Mtg on Thursday.

07/22/15 – Bert watts requests SOSS from TEI (with THP as sub) for relocation of existing fuel E-Stop which is in a bad location and makes take-off and landing difficult. Also want to relocate the windsock to a location that is more visible on approach for landing. Project pending approval of SOSS and PO.

02/23/16 – Revised SOSS submitted to Bert Watts this week for approval. Project pending approval of SOSS and PO.

03/29/16 – Project pending approval of SOSS and PO.

04/27/16 – Project PO and signed SOSS received. ThermalTech to provide drawings suitable for “Safety Inspection” for IBI inspection of work.

05/25/16 – TEI meets with Rocky Mullins at the Heliport to review work completed. TEI working to complete the plans for IBI review and approval.

06/27/16 – TEI sends BW for review and comments. ThermalTech receives BW’s TTU to proceed. TEI to coordinate with IBI and Sheriff’s staff for Safety Inspection.

08/23/16 – TEI, Rocky Mullins and IBI meet at project site for safety inspection. The inspector passed the inspection contingent on the relocation of the junction box inside the attic to eliminate the 8″ +/- of SO Cable inside of the building. Mike Barth communicated this information to John Nester – and John Nester initiated a work order to correct the issue. Project complete otherwise.

09/28/16 – Project ready to archive.

PATROL HQ Heliport Windsock Read More »

Sheriff Patrol HQ AHU-2 & RTU-6 Replacements

Building Operations Project

04/17/15 – Met on site this month to discuss with contractor, vendor and mfgr scenarios to replacing the existing condensing units. Sent email to Tony. R-22 not available any longer. Dual circuited condensers can’t be used unless the AHU are converted back. Replacing the existing condensing with a one for one does really help with unloading.

05/25/15 – Project will probably be submitted for cost for 2016 Project Cost Estimates.

06/24/15 – Project was submitted and priced by Terry Cannon of ThermalTech in 2016 Project Cost Estimates.

07/28/15 – Tony discussed moving forward with direct one for one replacement for CU-2 and CU-5. TTC to get small project quotes for Tony.

08/26/15 – Trane was out to do a compressor replacement on CU-2 again to try to fix the issues.

09/23/15 – Tony requested SOSS to replace RTU-2,5 and possibly RTU-6 as an alternate.

10/08/15 – ThermalTech was onsite performing more fieldwork for design.

10/27/15 – Project issued for bidding.

11/24/15 – Bids were opened today. County has several awardable projects. Base Bid and Alternate #2 seem to be solid bids.

12/08/15 – TEI sent Matre a Triton contract for Base Bid and Alternate #2 work. Project total is $141,000 which includes a $4100 allowance. Carrier equipment is listed as the manufacturer for this job.

01/26/16 – Contracts are at Prosecutors office for final approval. Waiting on vendors signatures to begin.

02/08/16 – Contracts are still being approved for Triton on this job. TTC inquired about status.

02/26/16 – Contract is awaiting approval.

03/22/16 – Submittals approved and sent back to vendor for ordering. Project schedule approved and sent to owner for use on this project. Fencing change order sent in for owner record. Schedule of Values approved.

03/30/16 – Permit office called and requested structural note from THP. Jackson requested fans in Detective Area during outage. Triton agreed that would be no problem.

04/15/16 – This week was spent coordinate the THP structural work for the plans examiner and the integration between the CC and the Vendor of the RTU. Lots of coordination work.

04/26/16 – Triton on site and starting work. Phone conference worked out several details with Doug from Triton and schedule of work at site. Triton to check on bldg permit today.

05/25/16 – Contractors are working out structural steel issues at SPHQ on RTU-6. AHU-2 and RTU-6 replacement to begin in earnest on June 1, 2016. Triton will provide fans and crane that day for work. county to coordinate parking needs and communication with Sheriff.

06/10/16 – TTC on site to check construction and take photos of ductwork supports.

06/29/16 – TTC on site to check installation of RF-1 in return ductwork and examine safety concerns of ductwork support system.

07/09/16 – Jackson sends new photos of RF-1 with concerns of attachment to ductwork and sealant issues.

07/21/16 – ThermalTech rejected the steel structural supports on the ductwork for this project after THP provided recommendation last weeks. TTC had long conversation with Triton about the rework scope of the project and modifying the change order submitted for the work. Doug Emery is working on reworking picking up punchlist items, dropping ductwork down tot 6ft above grade, modifying elbows, putting light back where it was originally installed, redoing insulation on ductwork, modifying condensate drain and grading the landscape will be done at end of project. Triton asked that ThermalTech and owner release a detailed drawing on what would be considered an acceptable support system for the ductwork.

07/27/16 – ThermalTech and Triton discussed the rework at great length. TEI to release itemized drawing for new ductwork support, this is about 50% done. We have to do a new section and a duct support details dwg for Triton.

08/03/16 – ThermalTech released Bulletin #1 drawing outlining changes in structural duct supports for Triton to rectify work in field and checked up on some other punchlist issues. 08/15/16 – Remote monitoring devices installed at SPHQ for temperatures. https://www.imonnit.com un: thermaltech_hamco pw: Engineer5721

08/04/16 – Triton contacted for change order cost update for RTU-5 on next email.

08/17/16 – Triton sent in revised change orders,

08/18/16 – ThermalTech sent back a list of questions and clarifications on the cost.

08/19/16 – Triton sent back answers and a change order usages.

08/22/16 – ThermalTech asked Triton if there was anyway to get this work completed with only allowance money.

08/23/16 – ThermalTech sends changes to Tony Matre for discussions.

09/01/16 – There is not enough space to fully explain everything going on at SPHQ. Triton turned in several change orders to redo duct supports. In the end they were all using allowance monies to finish the job. Tony rejected them all. TEI has drafted an official ASI instructing Triton to put the duct supports in as design and noted on the bid drawings. Work should start next week hopefully. Air balancer is calling to balance units for closeout on this job. Tony said that RTU-5 may be a go for design this year.

09/08/16 – Tony gave ThermalTech direction to send out official ASI instructing Triton to install the ducts as designed.

09/23/16 – Triton has installed the new supports and is working on remaining closeout items.

09/28/16 – ThermalTech visited the site twice since the rework started. Rain has slowed progress. TEI has asked for updates from Triton but have not received any updates as of this date. ThermalTech contact THP to assist with RTU-5 work and new SOSS requested by Tony.

10/24/16 – ThermalTech contacted Dave Deger and expressed our extreme dissatisfaction with progress on closing this project out. And asked for him to get an update to us ASAP. TTC also spoke to Mike Jackson at some length about bidding out the RTU-5 vs Change Order and what the scope of work will be for the rebid (boiler, safety rails, etc).

10/25/16 – Doug Habegger replied via email with a controls update at SPHQ. They will be on site 10/31 to make changes. Here is a transcript of that email: All – Regarding the SPHQ project, Rick Wiener (Habegger) & Steve Schinkal (Alpha) met on-site earlier this week. Per my conversations with them, the factory-installed RTU Open controller (Part # OPN-RTUM2) apparently communicates and controls just fine with the Johnson DDC system via BACnet. However, there are several issues with RTU BACnet feedback:
ISSUE #1: The economizer is controlled by a stand-alone Honeywell JADE controller that came with the economizer package, and thus isn’t monitored via BACnet. ThermalTech would like the economizer to be monitored by the DDC system.
SOLUTION: The RTU Open model has the capability of controlling the economizer. Habegger will remove the JADE economizer module, change the existing economizer actuator to a 2-10VDC actuator and wire the new actuator back to the RTU Open module. The DDC system will then be able to monitor economizer position, and adjust the minimum economizer position. Rick Wiener will be on-site Monday Oct 31 (weather pending) to install and wire the actuator.
ISSUE #2: Space CO2 should be monitored for Demand Control Ventilation and visible through DDC. Currently the DDC system cannot read the CO2 level.

SOLUTION: Habegger will replace the RTU Open’s existing wall-mtd. temp sensor with a combination Temp/CO2 sensor. Both sensors only require 4 wires so no physical wiring adjustment is necessary. Once the sensor is replaced the CO2 level can be monitored by the DDC system. Rick will change out this sensor on Monday as well.
ISSUE #3: The unit includes two-speed fan control. The VFD speed signal is not wired up the RTU Open controller, so the fan speed is not monitored via BACnet. The RTU Open does not control the fan speed, the unit automatically increases fan speed from 66% to 100% when the unit enters 1st or 2nd stage heat or 2nd stage cool. ThermalTech would like VFD speed feedback to be read from the DDC system.
SOLUTION: Alpha will connect one of the free inputs on their system to the VFD to monitor fan speed (per my conversation with Steve earlier today).

10/26/16 – ThermalTech updated the team with the latest changes and updates to closing out this project.

11/10/16 – We are working on controls, closeout, payapps and punchlist.

11/26/16 – Triton sent the painting CO#7 to ThermalTech which was forwarded to Matre and Jackson for approval.

12/07/16 – Triton approved for painting the steel with allowance money, updating the final pay application and closing out the job.

12/29/16 – TTC sent final paperwork, O&M’s, updated warranties and such to Tony Matre for closeout on this job.

Sheriff Patrol HQ AHU-2 & RTU-6 Replacements Read More »

SPHQ Roadway Signage

Lead Partner: ThermalTech

04/26/17 – TEI and facilities meeting on site on 04/27/17 for SOSS kickoff meeting at 2:30 PM.

05/22/17 – Project pending SOSS approval and PO.

07/25/17 – Project pending SOSS approval and PO.

08/28/17 – Project pending approval of SOSS and PO. Project on hold.

10/25/17 – Project on hold.

11/29/17 – Project on hold.

SPHQ Roadway Signage Read More »

Parkhaus Garage Repairs

Current Comments (10/26/2011)
October 26, 2011 Update – Contractor noted they are waiting on Joint and several warranty from the manufacturer, which is anticipated later this week.

Past Comments

All pay requests minus retainage approved; waiting on warranty and closeout paperwork.

August 31, 2011 Substantial letter completion letter issued; along with final deduct change order due to liquidated damages.

All work complete as of early August.

July 22, 2011 RAM issued via email that the new hand rail embed should be fabricated and on site at the end of the week of July 25.

July 12, 2011 THP issued new hand rail embed replacement details to RAM. RAM submitted details for embeds to be fabricated.

July 7, 2011 THP approved and forwarded to Hamilton County, RAM request for payment, Pay Application No 4, in the amount of $20,617.20.

July 6, 2011 THP noted, RAM damaged some existing handrail embeds when removing existing handrail. THP to review conditions and issued repair details.

July 5, 2011 RAM re-mobilized on site to begin replacement of the handrails at the NW stair and liquidated damages begin.

June 9, 2011 THP approved and forwarded to Hamilton County, RAM request for payment, Pay Application No 3, in the amount of $29,794.20.

May 26, 2011 THP approved, with exceptions noted, the steel hand rail shop drawings for NW stair tower.

May 23, 2011 RAM demobilized from the project site so Hamilton County has full use of the garage facility. RAM will re-mobilize on site once the steel handrail shop drawings and fabrication are complete. Per liquidated damages letter RAM is scheduled to return for installation of the steel hand rail on July 5, 2011.

May 25, 2011 steel hand rail shop drawings for NW stair tower received.

May 23, 2011 substantial completion date but RAM has not satisfied the substantial completion date requirements. No steel hand rail shop drawings submitted for NW stair tower. Liquidated damages letter pertaining to steel hand rail to be issued by THP per Bert Watts (Hamilton County) direction and approval. Steel hand rail shop drawings and fabrication were never weather dependent work items.

May 23, 2011 THP issued Field Report No 05 for Phase 2 (final) membrane strip installation.

Weekend of May 20, 2011, RAM completed vault slab placement over anodes, and remaining Phase 2 membrane strip installations. Inclement weather postponed this phase of membrane installation till this date.

May 17, 2011 Anode testing report by Bushman and Associated issued.

May 13, 2011 THP issued Field Report No 04 for completion of Phase 1 membrane strip installation. THP also approved and forwarded to Hamilton County, RAM request for payment, Pay Application No 2 in the amount of $54,344.40.

May 10, 2011 Membrane manufacturer (Neogard) letter pertaining to exposed membrane aggregate being compromised was issued.

May 6, 2011 THP issued Field Report No 03 for Phase 1 membrane installation. Inclement weather prevented completion of all of Phase 1 membrane strip installation areas.

May 6, 2011 Final T&M tickets submitted by RAM for anode relocation.

April 29, 2011 Change Order No 01 work items approved by all parties for a deduct to the projects Cash Allowance in the amount of $8,735.00. Total project budget remains unchanged.

April 26, 2011 THP issued Change Order No 01 to reflect Bulletin No 01 pricing so RAM may begin the additional work. This Change Order added two weeks to the substantial completion date. New substantial completion date is May 23, 2011.

April 25, 2011 Hamilton County accepted Bulletin No 01 pricing which was within the projects original Cash Allowance.

April 25, 2011 RAM submitted Bulletin No 01 pricing.

April 21, 2011 RAM began membrane work on Levels 2 through 5.

Week of April 18, 2011 Anode placement began in the vaults.

April 15, 2011 THP issued Bulletin No 01 to RAM for pricing for additional concrete and waterproofing repairs.

April 13, 2011 Progress Meeting.

April 8, 2011, THP issued Field Report No 02.

April 7, 2011 RAM completed construction joint sealant replacement on Levels 2 through 5.

As of March 24, 2011 RAM has not submitted steel shop drawings for hand rail.

March 18, 2011 THP approved RAM’s Pay Application No 1, in the amount of $40,194.80, and forwarded to Hamilton County.

March 3, 2011, THP issued Field Report No 01.

Anode installation scheduled to begin week of April 4.

Weather conditions for this weekend appear favorable, so RAM may perform sealant replacement April 1 weekend.

January 6, 2011 preconstruction meeting completed. Work to scheduled to begin February 7 to allow for weather.

THP has all submittals except cathodic protections.

Contract approved.

County commissioners reviewing contract.

Contract signed by Ram reported to be returned to County.

September 27, 2010 THP sent updated contract for County review.

September 9, 2010 THP sent draft contract for County review.

Bids received and Ram Construction apparent low bidder.

Bids due August 18, 2010.

Pre-bid meeting scheduled for August 4, 2010 at 10:00 a.m.

Project out to bid on July 23, 2010.

Project Documents sent to County for review on July 19, 2010.

THP and Jim Bushman accessed vaults to confirm conditions for implementing corrosion protection system on June 23, 2010.

THP is coordinating work with corrosion consultant.

Parkhaus SOSS approved May 14, 2010.

SOSS submitted 3/3/10.

THP anticipates SOSS delivery by 3/5/2010. (2/24/10

Kickoff meeting complete.

THP needs to schedule a kickoff meeting.

THP working with subcontractor to develop proposal.

Parkhaus Garage Repairs Read More »

PARKHAUS Garage Sink Hole Study

Lead Partner: THP

03/28/12 – SOSS submitted; waiting on approval3/29/12 Initial review of pipe is blocked, but damage to the pipe was not observed. THP getting quotes to clean the pipe; with an anticipated reinspection.

03/29/12 – Initial review of pipe is blocked, but damage to the pipe was not observed. THP getting quotes to clean the pipe; with an anticipated reinspection.

04/28/12 – SWS Environmental schedule to clean blocked line and re-scope line.

04/28/12 SWS Environmental schedule to clean blocked line and re-scope line.

04/28/12 SES Environmental cleaned and scoped the lines. Lines are in good condition and not causing the sink hole.

05/24/12 THP summary report to Anthony Matre recommending further geotechnical investigation.
06/4/12 THP submitted SOSS F34A for further geotechnical investigation of the sink hole.

2. 06/11/12 SOSS F34A Executed.

3. 07/11/12 Geotechnical Phase Two investigation kick off meeting completed. Investigation planned for July 28th to accommodate resurfacing project.
Phase Two investigation tentatively shifted to August 4th, due to resurfacing project shifting because of weather delays.
08/11/12 Terracon completed a limited excavation to try to determine the source of the sink hole directly north of the Parkhaus garage. After the excavation was completed, the hole was filled with a light weight concrete.
08/13/12 Terracon completed an asphalt patch at the excavation area.
THP/Terracon completing final summary report.

1. 10/26/12 THP published final Terracon report. Investigation work complete.

1. Project to be archived.

PARKHAUS Garage Sink Hole Study Read More »

PARKHAUS 2012 Garage Restoration

Lead Partner: THP

05/09/12 – Bid documents issued.

05/17/12 – Prebid meeting occurred.

05/24/12 – Addendum 01 issued.

05/30/12 – Bid opening occurred. The apparent low bidder is within budget including the alternate work. THP to review bid and make recommendation. Architectural Maintenance under contract with the County.

07/31/12 – Preconstruction meeting scheduled.

07/31/12 – Preconstruction meeting complete.

08/28/12 – Submittals received from the contractor

08/29/12 – Reviewed submittals returned to the contractor. No exceptions were taken on any submittals. Construction is scheduled to begin 9/4/2012. Awaiting schedule from the contractor incorporating revised membrane installation dates.

08/30/12 – Submittals completed.

09/10/12 – Work started.

10/30/12 – Roughly 80% of work complete. Complete date projected to be early November.

11/14/12 – Work complete and THP issued punch list. Punch list complete.

11/26/12 – Punch list complete and final pay application minus retainage.

01/30/13 – Architectural Maintenance working on warranties and coordinating with manufacturers.

02/13/13 – Architectural Maintenance submitted warranty paper work. THP reviewed and corrections are required. THP working with Architectural Maintenance.

03/06/13 – Joe Feldkamp reported a leak related membrane work completed during the 2012 project.

03/07/13 – THP reviewed the condition over multiple days during rain and snow. A number of condition exist that may be contributing to a leak. THP to review with County.

03/28/13 – Project Update THP reviewing updated warranty paper work and final pay application. 04/11/13 – THP issued new drain sketch for pricing to Architectural Maintenance.

04/16/13 – THP issued proposal from Architectural Maintenance to install the new drawing to the County for review.

04/23/13 – THP issued Change Order #002 to install a drain and repair damaged grout at the elevator door jamb on sixth level.

05/30/13 – Drain and lines installed from CO #002. Minor sealant to be installed then work complete.

06/25/13 – THP issued a small punch list to Architectural Maintenance for work related to change order #2.

PARKHAUS 2012 Garage Restoration Read More »

PARKHAUS GARAGE 2012 Garage Restoration

Partner Lead: THP

04/13/12 – THP issue review drawings.

04/24/12 – County returned review drawings with comments.THP working on final bid documents.

05/09/12 – Bid documents issued.

05/17/12 – Prebid meeting occurred.

05/24/12 – Addendum 01 issued.

05/30/12 – Bid opening occurred. The apparent low bidder is within budget including the alternate work. THP to review bid and make recommendation. Architectural Maintenance under contract with the County.

07/31/12 – Preconstruction meeting scheduled.

07/31/12 – Preconstruction meeting complete.

08/30/12 – Submittals completed.

09/10/12 – Work started.

10/30/12 – Roughly 80% of work complete. Complete date projected to be early November.

11/14/12 – Work complete and THP issued punch list. Punch list complete.

11/26/12 – Punch list complete and final pay application minus retainage.

01/3013 – Architectural Maintenance working on warranties and coordinating with manufacturers.

02/13/13 – Architectural Maintenance submitted warranty paper work. THP reviewed and corrections are required. THP working with Architectural Maintenance.

03/06/13 – Joe Feldkamp reported a leak related membrane work completed during the 2012 project.

03/07/13 to 3/20/13 – THP reviewed the condition over multiple days during rain and snow. A number of condition exist that may be contributing to a leak. THP to review with County.

03/28/13 – Project Update – THP reviewing updated warranty paper work and final pay application.

04/11/13 – THP issued new drain sketch for pricing to Architectural Maintenance.

04/16/13 – THP issued proposal from Architectural Maintenance to install the new drawing to the County for review.

04/23/13 – THP issued Change Order #002 to install a drain and repair damaged grout at the elevator door jamb on sixth level.

05/30/13 – Drain and lines installed from CO #002. Minor sealant to be installed then work complete.

06/25/13 – THP issued a small punch list to Architectural Maintenance for work related to change order #2.

08/29/13 – Project complete.

PARKHAUS GARAGE 2012 Garage Restoration Read More »

Memorial Hall – Asbestos Study

10/20/11- Kick-off Meeting with Pinnacle and Facilities Department

11/04/11- Facilities Department sens list of buildings to be included in Asbestos Abatement Reporting.

3/30/12- Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

4/05/12- Meeting with GBBN and Facilities to discuss drawing format.

4/05/12- Pinnacle requests drawing files from GBBN.

4/05/12- GBBN sends pdf drawing files to Pinnacle Engineering.

5/10/12- Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

6/11/12- GBBN set up conference call meeting with Facilities CAFM Department and CAFM Partner to be held July 3, 2012.

9/6/12- Bulk drawings received from Pinnacle.

9/24/12- GBBN completes bulk drawings and forwards to Pinnacle for use in final reports. GBBN requests final inventory drawing spreadsheets to allow completion of inventory drawings.

10/27/12- Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

02/26/13- GBBN inquires with Pinnacle for status of remaining documents to be sent to GBBN.

02/27/13- Pinnacle reports back that progress has been made and further timetable for receipt will be coming 2/28/13

Memorial Hall – Asbestos Study Read More »

Memorial Hall – Window and Flooring Restoration

05/04/11-Bert Watts notified GBBN of prospective project via email. GBBN requested to provide a budgetary estimate of scope and services. GBBN indicated the historic nature and requirements will require some research to determine scope of services.

05/09/11- GBBN spoke by telephone to Larry Harris of the City of Cincinnati Historic Conservation Department. Larry promise to perform preliminary research and call GBBN back the next day with input.

05/12/11- GBBN let voice mail with Larry Harris

05/15/12- GBBN contacts Beth Sullebarger about consulting on project with GBBN.

05/19/11- GBBN let voice mail with Larry Harris

05/24/11- GBBN let voice mail with Larry Harris

05/25/11- GBBN received call from Larry Harris. Memorial Hall is individually listed on the National Register for Historic Buildings. He was not certain if it is located in Historic District. Replacement of the windows is not advised but would require a like-match. Repair is recommended. Interior storm windows are allowed. The flooring is recommended to be refinished and not replaced. Tax credit financing will determine the direction of the County and the City for review and comment.

06/01/12- GBBN delivers hard copies of SOSS to Bert Watts.

06/21/12- GBBN meets with Pater Architectural to discuss their capabilities to replicate existing windows.

06/27/12- Beth Sullebarger reports results of personal visit to Pater Architectural manufacturing location.

07/23/12- GBBN assigns staff for project to Project Manager.

09/07/12- GBBN visits Pater Architectural to review historic window production for a similar project. Pater has similar project for a Courthouse window replacement in production in their shop.

Memorial Hall – Window and Flooring Restoration Read More »

HC General Structural Services

Current Comments (4/27/2011)
THP completed billing of $5,000 allow for general services. Funds lasted 10 months from July 2010 to April 2011. THP directed to submit new SOSS, refer to F24.

April 15, 2010 THP requested to review possible leak and stone condition of 800 Broadway Bld. THP and County scheduling site visit.

Past Comments

THP completed site review of 800 Broadway wood deck. THP completing analysis and letter report.

THP submitted four names for badges. County review approval policy.

THP reviewed Hillcrest cracked walls. Walls are cracked and further investigation is necessary. Cracks are not a life/safety concern and cracks do not appear to be a warranty issue from settlement.

February 17, 2011 County requested THP review floor condition at Alms Doepke. Work may be part GBBN floor project, if not THP will notify the County on how it thinks we should be proceed.

February 14, 2011 THP reviewed cabin with cracked walls as requested by the County. As a follow-up THP does not think the cracks are a life-safety concern or warranty related to previous work. THP will follow up with a summary letter.

January 27, 2011 County requested partners submit employees names for background check and badges. Future access to County facilities will be limited to people with badges or escorted by badge person.

January 27, 2011 County distributed HC Safety specification section to added to all facility projects. Partners to determine location with front end documents.

January 27, 2011 THP requested to evaluate 800 Broadway interior wood deck structure for loading capacity. THP to evaluate and if work is minimal work will occur within General Service number, if work is more involved THP to discuss separate SOSS.

THP has $3,200 remaining in the hourly allowance.

Septermber 29, 2010 THP to review MDD North side structure for possible work with GBBN.

County approved updated proposal.

County reviewing initial proposal.

THP provided preliminary pricing of the building envelope assessment of Memorial Hall on 8/17/10.

County requested preliminary pricing for building envelope assessment of Memorial Hall building.

County reviewing SOSS.THP Issued SOSS F9A for an additional $5,000 on July 2, 2010.

Roughly $1500 remaining in general fund.

THP used roughly $2,800 of the $5,000 fee.

THP tracking 800 Broadway storage area floor capacity survey to general fund. (2/24/10)

THP tracking additional Masonry work from Hillcrest project to general fund. (2/24/10)

OSS approved 2/3/2010.

THP submitted SOSS on 2/1/2010.

THP needs to submit SOSS.

HC General Structural Services Read More »

Hillcrest Training School Dining Hall Loading Dock Restoration

July 27, ,2011 THP issued AIA Substantial Completion Letter.

July 19, 2011 A&M confirmed (via email) punchlist items completed.

July 12, 2011 A&M submitted final Pay Application for retainage. THP notified A&M that retainage monies will not be approved until all warranty paperwork has been submitted and approved.

July 8, 2011 THP issued (via email) punchlist items to be completed by A&M.

July 8, 2011 loading dock sealant installed.

July 7 & July 27, 2011 THP requested A&M to submit warranty paperwork.

July 7, 2011 new galvanized handrail system installed and THP approved and forwarded to Hamilton County, A&M request for payment, Pay Application No 2 in the amount of $10,070.00.

June 30, 2011 THP issued Change Order Deduct to the contract, in the amount of $3,778.00. The new contract sum is $51,132.00.

June 30, 2011 sealant scheduled to be installed and THP will punch-out the project.

New loading dock handrail system fabrication completed and A&M installed new handrail system week of June 20, 2011.

A&M completed loading dock bumper installation and installed temporary handrail system on May 27, 2011. Hillcrest facility began using loading dock May 30, 2011.

THP issued email on May 24, 2011 for A&M to install temporary handrail system once loading dock bumpers are installed. A&M to be completed with installation of loading dock bumper and temporary hand rail by May 27, 2011, so loading dock may be used by Hillcrest facility on May 30, 2011.

On May 23, 2011, THP approved and forwarded to Hamilton County, A&M request for payment, Pay Application No 1 in the amount of $38,068.24.

Hand Rail steel shop drawings approved (with exceptions noted) for fabrication on May 12, 2011. A&M expects for fabrication and installation of hand rail week of June 13, 2011.

Field Report No 002 issued on May 9, 2011.

Loading dock slab placement took place on May 6, 2011 with THP personnel on site to witness placement. Weather delayed the original April 28, 2011 placement.

New louver and new loading dock bumper approved to be purchased and installed out of project Cash Allowance via Change Order No 1, dated April 20, 2011, in the amount of $1,222.00. Total project budget remains unchanged.

Hamilton County requested price quote from A&M for a new louver and loading dock bumper, instead of reconditioning these existing items as part of the original scope. Pricing came in within the projects original Cash Allowance which Hamilton County chose to accept. THP issued Change Order No 01 on April 20, 2011 reflecting this modification.

The loading dock slab placement is estimated to take place on April 28, 2011. Weather pending.

April 13, 2011 A&M formed and placed concrete for the loading dock steps. THP reviewed the steel and formwork prior to concrete placement.

April 6, 2011 A&M formed and placed concrete for the loading dock walls. THP reviewed steel and formwork prior to concrete placement and issued Field Report No 01 for both concrete placements.

Submittals not complete as of April 25, 2011. Waiting on resubmittal of galvanized steel hand railing for loading dock.

April 1, 2011 A&M completed loading dock demo while maintaining emergency egress.

March 30, 2011 A&M mobilized on site and began project work.

March 23, 2011 THP held a pre-construction meeting on site with Hamilton County and A&M Contracting.

March 23, 2010 preconstruction meeting occurred. Demolition of loading dock to begin March 31 and closure of the dock will last 6 weeks.

February, 22 2011 A&M Contractors passed background checks and work can proceed. Bert has requested a schedule and submittals to be finalized.

January 27, 2011 A&M Contracting had a number of employees not pass the background check. Work cannot proceed until A&M Contracting project team has passed the background check.

Need to determine if project will occur in Spring or this Winter. If work occurs this winter a change order for heating will be required.

Submittals continue to arrive and be returned; last submittal return on December 7, 2010. THP has requested a number of additional items to be submitted.

October 26, 2010 THP returned initial submittals and requested preconstruction meeting.

October 20, 2010 Contract was approved and PO issued.

County reviewing contract for final approval and execution.

September 16, 2010 THP provided updated draft AIA contract per comments from County.

September 2, 2010 THP provided draft AIA contract.

County reviewed project bid.

August 10, 2010 THP recommended A&M Contracting Ink. based on the submitted bid. THP has no experience with A&M Contracting.

Bids received August 5, 2010. A&M Contracting Ink. submitted only bid. Bid was within 10% of published estimate.

Bids are due August 5, 2010.

THP plans to issue final addendum by July 29, 2010.

Pre-bid meeting held July 20, 2010.

THP updated documents and issued documents for bid on July 12, 2010.

County Responded with minor ITB comments THP to update documents.

THP Issued updated ITB documents on June 7, 2010 for review.

THP anticipates finalizing and sending Updated ITB documents to the County on June 1, 2010.

County finalized review of ITB documents and sent comments to THP on May 21, 2010.

THP finalizing bid set; anticipate release 4/5/2010.

THP complete design review meeting with County on 3/12/2010

Project anticipated for summer of 2010. (2/24/10)

Waiting on Owner comments to complete final documents. (2/24/10)

THP submitted owner review documents on 12/21/09

THP provided plans for an emergency deck for loading dock access on October 22, 2009.

THP submitted an SOSS for approval on October 23.

THP completed initial site visit with County and recommended closure of loading dock.

Hillcrest Training School Dining Hall Loading Dock Restoration Read More »

Hillcrest Training School Cottage Slab Review

Project complete and closed out.
Past Comments

L&T submitted closeout paper work. THP & L&T revising warranty language in submitted warranties; all other paper work acceptable.
L& T completing final project closeout paper work. (2/24/10)
L&T requested a project closeout, so additional grading work will not be accepted.(2/24/10)
All punch list work including additional interior repointing at interior/exterior wall joints reported to be complete. THP to review next week. (2/24/10)
All work complete except punch list. Punch list published and all work except grading except grading expected to be complete by February 19.
Contract was coordinated with the prosecutor’s office and final copies were sent to Hamilton County for review by the commissioners on September 14.
August 17 THP recommended Langenheim.
Bids received August 14 and Langenheim & Thomson was low bidder within the project budget.
Project in bid process with pre-bid meeting completed on July 28, 2009. Bid due August 11th.
Design development documents anticipated to County 6/26.
Partial front end specification sent to County for review on 6/22.
Kick off meeting completed and field survey’s complete.

Hillcrest Training School Cottage Slab Review Read More »

Hillcrest – Modular Building / Addition

08/08/05- C+R sent a preliminary project report to Hillcrest. TE to review and comment and provide updates to Spencer for inclusion.

06/16/05 – C+R, TE and HCDF had a follow up meeting at site to discuss layout issues. Spencer distributed possible floor plans for review. TE went over utilities that were underground and reported that electric, gas and water are all near the expansion area.

01/19/05 – Second Field trip to discuss cost and scope.

11/11/04: Zeiser Pay Application #6 to Sharon via Courier.

11/04/04: Zeiser Change Order #4 for Punchlist items 1.19 and 1.20, new door hardware, in the amount of 690.00 typed and courier.

LaForce went to site today to complete punchlist items hardware repairs. However, Chris was unable due to audit, to show them location. Chris could you please coordinate with Zeiser to a date you would be available to show them locations.

Cottages grandmaster key – Contractors are working on resolution to be presented.

Post caps for doors stops are in and ready to be installed.

Indrolect

ICS to complete punchlist including rewiring system. Please update us to the progress.

12-07-04 – New master keys are on site for cottages. Zeiser to coordinate work with Hillcrest

01-04-05 – Zeiser and Laforce to complete cottage level master rekeying. Work to start on 01-05-04.

04-19-05 – Cottage level master rekeying complete. School has accepted suggested solution for fixing the bathroom keys. Laforce has install the proposed fix and is returning to make repairs.

04-2-05 – Bathroom rekey complete however one issue still exists. Dining hall locks have a total of four cylinders and only two where replaced. The second set can be defeted but according to Dave Jones with LaForce this is not possible because of the type of lock. They proposed replacing the sets and provided pricing accordingly. County review cost and felt that it was not their responsibility because this proposed fix was only a compromise that remedy the situation. Upon conference call with Diana, Mike, Jeff, Chris and Dave fix was agreed upon. Dave with LaForce to complete week by 05/06/05.

Hillcrest – Modular Building / Addition Read More »

Hillcrest – Fire Alarm Replacement

12/26/06 – Project has been archived by TTC.

11/09/06 – Final permit was accepted

11/03/06 – TEI is working on closeout documentation. Final devices have been installed. Final approval has been obtained from Hamilton County Building Department.

10/27/06 – Final devices have been installed. Ginter to set up to get final approval

09/29/06 – Waiting on approval of revision from Hamilton County Building Department

09/22/06 – We have passed and approved (signed off and everything!) on 21 buildings out of the 22. Each building was permitted separately. The one building (grounds keeping) is on hold until the inspector sees the 501 model number heat detectors installed in the or we submit an engineering change that corrects the permit drawings with the 503 model number. They are in the process of getting the paper work together and will forward it to you. As far as the grounds building we are not being told that we can not use the building. Also we don’t believe they occupy it all day, mainly just storage and prep for the grounds care equipment.

9/12/06 – 21 buildings passed fire alarm inspection grounds keeping building approval on hold until heat detector issue is resolved.

9/6/06 – IPS adjust strobes in cottages that were coming back with a trouble condition. They were set to the wrong setting. Ginter adjusted devices.
8/30/06 – Hillcrest performed a drill test and a few troubles came back on the system. Chris and I contact IPS and Ginter to get trouble condition resolved.
8/25/06 – Hillcrest will be unable to have the cottage door delay egress maglocks repaired prior to the 8/29 test date. Test is rescheduled for 9/12
8/21/06 – Complete rewiring of audible devices in cottages so the do not sound when fire alarm system is in alarm.

04/06/06 – Mike Stiles has requested a change in the meeting schedule for 04/10 as he is out of the office on that day.

03/06/06 – Ginter email TEI that the county was requiring separate permits for each building. TEI call the Building department and clarified the situation. The county required 22 permit applications and 6 drawings. The minimum fee per permit is 257 dollars. Ginter indicated that they did not have an amount this large covered in there bid. TEI requested that Ginter submit a total for all cost so far in the project: Some of the additional fire alarm cable, additional permit fees and deletion of 10 in-ground boxes.

03/03/06 – Ginter Electric provided submittals, TEI approved submittals.

02/28/06 – Construction meeting #1, Please see attached.

02/03/06 – Ginter submitted pay application #1, TEI approved.

01/20/06 – Preconstruction at Hillcrest.

12/16/05 – County reported that this project has been approved. Wayne Trent will be project manager on this job and therefore the project is being moved to his task sheet.

02/01/06 – Ginter Electric started field investigation.

12/01/05 – Contract was approved.

11/01/05 – TEI prepared contract for Ginter Electric, Alternate #5 was accepted.

10/31/05 – Bid opening held, apparent low bidder was Ginter Electric.

10/24/05 – Issue addendum which delayed bid opening to October 31st. Addendum was the same form Re-bid.

10/14/05 – The rebid II prebid was held. No contractors showed up for the rebid. This might be expected because everyone has already been on site for 2 prebids already on this job. There can still be and will most likely be bidders on this project.

10/13/05 – The rebid has been rejected due to bond issues again and estimate tolerances. The second rebid is on the street with a revised bid opening of 10/25/05. MS has all the revised documents on the street. The prebid is 10/14/05 at 10a.m. MS will attend for TE.

10/11/05 – Project was issued for rebid.

10/05/05 – Bid was rejected by the prosecutors for basebid plus alternate because the awarding contractor complete the bid bond for only the base bid amount. TEI advise that alternate 7, which was cabling in the ground in conduit plus a spare, was very important. Since the contractor filled in the bid bond purchasing would only allow base bid. The next lowest contractor was reviewed and but there base bid plus the alternate was greater than 10% of the advertise amount. The county decided to rebid the project.

9/02/05 – Contract completed for AC Electric, base bid plus alternate 7. Submitted to Diana for approval.

08/25/05 – Bid opening held, apparent low bidder was AC Electric.

08/10/05 – Project prebid was conducted.

08/3/05 – Project was issued for Re-Bid.

07/01/05 – Diana, Gerald and TEI decided to hold off on rebiding project to gain more interest. MS contacted several contractors to find out marked conditions. The consensus was that the school at released a lot of work to be complete by the beginning of school and the contractors where very busy. It was also determined that breaking the project into several alternates would be required to make sure the project can be complete within budget.

06/28/05 – TTC and MS discussed the bids. A clarification on the addendum split up the labor versus the equipment. The bid is not over the original estimate of 298,000 however it is over the revised estimate. TE has to discuss with Diana when she returns our call. MS believes that this project should be rebid as the bids are simply too high for this type of project.

06/24/05 – Diana emailed TE today to say that the bids came in over 10% of the budget. TTC and MS to discuss with DES on Monday in a phone call.

05/19/05 – I spoke with Andy Boyd at IPS about the project. I discussed the three state term options with him which are: A) Purchasing material only and bidding out the installation to an electrical. IPS (or competitor) would be subcontractor.B) Purchasing material and IPS to set up the system and bid out electrical labor for the installation.C) Purchasing the entire project from IPS.Option C has changed because Purchasing indicated that they can only do the project if they do not use any subcontractors. I presented this to IPS and they gracefully turn this option down because they do not have the resources to complete a project of this size on there own. Option B was discussed. I ask the question, what advantage is it to the county to proceed. IPS indicated the main advantage was for them and that the cost under state term and bid day would be about the same. IPS and I agreed that this was not the best option for the county. Option A was discussed and believed to be the best solution. This makes the bidding process cleaner and only has one contractor to manage. The above is a recommendation but if you have any comments or suggestions please let me know. I would be happy to proceed the manner you prefer.

05/12/05 – TEI contact JoAnn with purchasing to discuss doing the project under state term. She indicated that IPS could not have an electrical subcontractor because the amount of the contract was to much and must be bid out publicly. Prepurchasing material was acceptable.

05/10/05 – TEI presented final drawings and Edwards material pricing. TEI indicated that the material price provided by Edwards was in budget with all the options requested but not with alternates. TEI indicated that Alternates should remain to insure the budget. TEI indicated that there where 3 way to bid the project: 1) Prepurchase material and bid out the installation. 2) Prepurchase material and ESI setup of system, bid out electrical labor to install system. 3) Purchase entire project under state term. Hillcrest indicated that they where interested in purchasing the entire project though state term because of the difficulty of trenching on the site and the responsibility to the electrical contractor.04/18/05 – TEI present near complete drawings written around a full system replacement of any manufacturer. Hillcrest review vendor options and indicated that the two favorites where Simplex and Edwards. Overall Edwards offered a security solution that could handle the need of the fire alarm system and replace the antiquated access control system. State term options was discussed and Hillcrest indicated the we receive compare the price for Edwards with almost all requested options and compare to original budget. Items to be included is: Voice System, Access control panel for each cottage, Access control software, Data base software, Computer based graphics package. Alternates for the project shall be: Voice system in lue of Tone system, Additional access control module for each cottage, Access control module for gates and upgrade spare conduit in ground with honeycomb type.3/30/05 – Vendor presentations.

03/29/05 – Vendor presentations.

03/09/05 – TEI complete field take off and composed 4 options with associated cost estimates to proceed with project. Cost estimate #1 was to completely remove existing system and replace with a new tone system of any manufacturer. Cost estimate #2 was to completely remove existing system and replace with new voice system of any manufacturer. Cost estimate #3 was to upgrade existing system Fire Alarm Control Panel with the same manufacturer, add additional devices as required per NFPA and replace all existing wiring. Cost estimate #4 was to upgrade the Fire Alarm Control Panel with the same manufacturer, add additional devices as required per NFPA and replace some of the existing wiring. Hillcrest to review options and requested vendor presentations be conducted to aid the school in there decision. TEI to continue with drawings as far as possible until decision is complete.

02/22/05 – Project Kick Off meeting. TEI to start field take off and review options. Original cost estimate presented was for a complete system replacement. TEI suggested reviewing the existing system and look at possible options.

Hillcrest – Fire Alarm Replacement Read More »

HILLCREST – Electrical Upgrade Phase II

03/29/07 – TTE received final pay application and the ‘CONSENT OF SURETY COMPANY TO FINAL PAYMENT’ form from QC Electric. All of the final documentation will be forwarded to Hamilton County Facilities the second week in April of 2007. There are no open issues on this project.

03/23/07 – Closeout meeting was held on site today. There are no open issues for this project. Final documentation (O&M’s, As-Built, Final Pay App., Close Out Documentation) have been turned over to TTE. An Allowance Clarification letter needs to be written and signed before the final pay application can be processed. This letter will be sent to Queen City on Monday, March 26, 2007. When TE receives the signed letter back from QC all of

these materials will be turned over to Hamilton County Facilities. Dick Kuhn, Mark Donnelly, Bert Watts, Chris Hohmeister, Phil Lambing and Nick Richmond attended this meeting.

03/20/07 – Closeout meeting is scheduled for this Friday. Project is paid out except for retainage.

03/15/07 – I believe this project is ready for closeout. TTC to confer with PL and wrap this project up.

02/19/07 – Project is complete. TEI is starting closeout phase on this project. TEI will coordinate with Mike Jackson on closeout on this project.

11/10/06 – Concrete pads have been poured. ID studies and receptacle installations have been started in cottages. Project is still on schedule for December 1 shutdown.

10/27/06 – Contracts released, and preconstruction meeting was held. The schedule was approved. Coordination meeting with Duke Energy occurred 10/25/06.

09/22/06 – Still waiting for contracts.

09/15/06 – Bert called back to say contracts have not been received yet. Contracts are in review stage. QCE will not be on site next week but TE will coordinate a const mtg as soon as the paperwork is in place.

09/15/06 – Construction to start next week.

09/15/06 – Bert Watts said Contracts were released, ThermalTech has not yet received them.

09/08/06 – County reviewing contracts and insurance.

HILLCREST – Electrical Upgrade Phase II Read More »

HILLCREST – SECURITY BUILDING

01/28/08 – This project was added late because it started before the website. After 4 years of futility, the County and ThermalTech finally agreed on a solution to the cooling and heating problems in the Security Building. Tony bought the new computer room ductless split system and County trades installed the unit. It is currently up and running and the space is doing great! EDI came to the site on Monday, Tuesday & Wednesday to install the AC unit. We had some unit problems as we received an AC unit and not a heat pump. Jeff did a great job returning the unit and getting the heat pump for us which amazingly was in stock at Habegger. We installed a 4-ton fan unit and 3.5 ton heat pump so that I could ensure full flow into the building since the ductwork sizing has always been a problem. The new unit and heat pack are up and running from the Carrier thermostat on the wall and the space has been 72, 74 and 77F when called to check on. Mike Jackson and I discussed the cold feet issues today and he is comfortable with the unit providing enough heat and said the space was 1000% better. I will recommend some radiant heating solutions to Hillcrest for their feet but I don’t believe that TE should have to pay for those. I believe this project could finally be complete.

HILLCREST – SECURITY BUILDING Read More »

HILLCREST – ELECTRIC PANEL UPGRADE PHASE III

04/23/08 – QCE had to fix the same AHU unit again when they cleaned up some of the school panel wiring. Project is nearing completion.

04/11/08 – MAH released the Const Mtg 05 Notes to the project partners.

03/13/08 – (3) full size sets of drawings and a letter stating that no loads were being added and that the feeders and panels are of sufficient size were delivered to IBI today. QCE should be able to obtain a permit with these actions.

03/06/08 – Today’s construction meeting has been rescheduled to 03/17 at 2pm. We also discussed the revised schedule for the project which I updated in a pseudo meeting minute memo in PDF format. TEI will process the IBI letter for no load increases during this job for QCE to give to IBI to get permit squared away. Bert also asked for a revised scheduled update which we have included in the memo.

02/26/08 – QCE called today to tell us that IBI denied our permits for this job. They now instead want TEI to provide a letter saying no loads have been changed or will change during this project and we are doing a direct panel for panel replacement. A shutdown is going to be scheduled in late March for school panelboard replacement(22 or 23).

01/09/08 – Today we decided that the pre const meeting notes were correct and the project completion date for this project is March 1, 2008. QCE will do and update project schedule with delivery details for TEI to approve and give to the owner very soon.

01/07/08 – MAH released the Const Mtg 02 Notes to the project partners.

11/28/07 – QCE provided an update to Mark Donnelly today with the following information: The ID portion of the project is going well. The (4) cottages are complete. Chapel, John Morrow building, Goundskeeping building, & Pole Barn are completed also with the ID. We still have to change locks and install the new locks on certain panels. Administration building is approximately 75% completed, the School is approximately 50% completed. Some work has been done in the Dining building, Rec building, & Gym. We have not been in Security yet. The transformer pad for the school transformer was poured 11/27/07. All Panels have been measured & verified. The order has been placed, but I don’t have delivery dates yet. As soon as I have the delivery dates I will put a schedule together and ask for a meeting to go thru what has to happen for the shutdowns & installation of the panels. TTC setup a const mtg for 12/10 at 2:30pm to follow up with panel order and schedule.

11/12/07 – TTC released the Pre Const Mtg Notes to the project partners.

08/31/07 – TEI still awaiting word from HCFD. This project remains in the Contract Phase.

08/17/07 – TEI awaiting word from HCFD in order to move forward with this project.

08/10/07 – TEI spoke with QCE about their bid. They were comfortable with the bid so TEI wrote the contract and forwarded to the Hamilton County Facilities Department. TEI awaiting word on signed contract so this project can move into the construction phase.

07/31/07 – TEI has obtained a copy of the bid package and is reviewing the information. Dick Kuhn of Queen City put together the bid; he will be back in his office on Wednesday, August 1. NR will contact him in the morning to discuss the bid.

07/27/07 – Today was the bid opening. NR attended for TEI. QCE and Ginter are the low bidders. QCE was at $138,000 for this project. TEI will check the bid to make sure everything is covered.

06/29/07 – No change.

06/22/07 – TEI obtained an ITB #099-07. This project is set to be issued on June 26, 2007. The pre-bid meeting is scheduled for July 3, 2007.

06/15/07 – TEI conducted a site visit on June 13, 2007. The final design strategies have been discussed and this project is moving into its final stages before being issued for bid. TE plans to issue this project for bid by next Friday, June 22 of 2007.

06/08/07 – This project was reviewed in a meeting between TEI and Mark Donnelly. There will be a set of drawings and a cost estimate delivered to Hamilton County Facilities Department this afternoon (June 8, 2007). A meeting will be held on site next week to review final conditions and then will go out for bid.

06/01/07 – NR will have a review set of drawings, specifications and a cost estimate ready for Mark Donnelly to review by the end of next week (June 8, 2007).

05/25/07 – Project is moving along as expected.

05/22/07 – Project review meeting was held today. Various points were discussed as described in the meeting notes. TEI is moving forward with this project while keeping the points discussed in today’s meeting in mind.

05/21/07 – TE has completed all field work. Drawings are 98% complete. A meeting to discuss the status of this project is scheduled for May 22, 2007 with Mark Donnelly.

04/07/07 – TEI has completed the device identification portion of this project and are currently inputting the data into CAD. The panel replacement portion of this project is moving along as expected.

04/20/07 – TEI has been on site working on the device identification portion of the project. The only areas left to complete are north and south wings of the School Building. TEI will be on site today, April 20 2007, to work on the panel replacement portion of this project.

04/13/07 – TEI will be on site beginning next week to work on the electrical device identification portion of this project. Design for panel replacement is moving along as expected.

04/06/07 – Project moving along as expected.

03/28/07 – Kick-off meeting held on site. Buildings to be included in the Device Identification portion of this phase are Administration, School, Chapel, Security, Maintenance, Storage, Dining & Recreation and Gym & Pool. Efforts are aiming for August of 2007 for the shut-down and transformer pad replacement to coincide with the week that school is out of session. Attendees of this meeting include: Mark Donnelly, Bert Watts, Chris Hohmeister, Phil Lambing, Nick Richmond and Ron from Facilities. The next meeting is scheduled for May 2nd at 10:00 on location.

03/23/07 – Design meeting to be held the last week of March 07.

03/20/07 – TE to assist in deciding scope on this project and settle on which buildings are left to do on this site.

03/15/07 – SOSS received and posted to the website. A kickoff meeting will soon be scheduled.

03/14-07 – NR created project journal and filled in back data from previous meetings. Project awaiting signed SOSS to be returned to TE.

HILLCREST – ELECTRIC PANEL UPGRADE PHASE III Read More »

HILLCREST – KITCHEN HOOD UPGRADE

03/13/08 – TEI awaiting scheduling of suppression system test. Will witness on request.

03/09/08 – TTC sent closeout paperwork to DK and request for Credit on project.

03/05/08 – DK tested the electrical portion of the system successfully today. All relays operated as required. A test of the fire suppression system will now be scheduled by FES. This will need to be done when no cooking is occurring under the hood. A tank of ordinary air will be connected to simulate the suppressant.

02/26/08 – DK reported that this project is complete and ready for final fire alarm test. This is being coordinated through Hillcrest and MJ. TE may attend this final fire alarm test.

01/28/08 – We have received Payapp 2, O&M’s and an approved permit for this job from DK. MJ requested and TTC asked DK to setup a FA test showing the working components of the system. MH has the O&M’s to approve for this job.

01/08/07 – Earl Moon approved the project yesterday and TTC spoke to Kevin Broxterman today about the allowance usage and remaining allowance monies on this job. TEI will schedule a punchlist visit to the site and close out this project. TTC tried to contact Huntwork to do the punchlist today while he is on site with another job. TTC instructed DK to do as-builts and give them back to TEI for inclusion into the CAFM system. TEI will send an email outlining all the closeout procedure documents for this job. MD has requested closeout before next Monday. TEI finished the punchlist today and distributed this to everyone.

12/12/07 – MAH talked to Kevin Broxterman and the disconnects are scheduled to be installed on Friday. He asked if there had been any discussion about his using some of the allowance for this work. I directed him to Bert Watts while Mark D is out.

11/30/07 – The electrical inspector has an issue with the disconnect location because of access to the them over the equipment. MH went to the site today to review and find a new location based on our discussions with Kevin B at DK and Mark D at the County. We want to find a new location on the first floor for the disconnects. MH located a space behind the wall of the existing equipment. We will have to relocated the existing fire extinguishers, sign and fire blanket so everything can share the space but it appears very do-able. TEI is sketching up the photo right now for changes. The inspectors wanted the disconnects in the basement but the owner does not. DK submitted their first pay app on the job and TTC approved it for $8941.60.

11/13/07 – Debra-Kuempel has reported updates as well as Mike Jackson from Facilities. Debra says they should finish tie-ins this Thursday. Greg will schedule with IBI and IPS for inspections and fire alarm tie-ins for the end of this week or early next week. Greg of DK reported that they had no problems or questions at this time. MJ reported that the tie-in in the basement Rec Ares is complete. Also that the new disconnects for the steamer and the oven are complete. DK scheduled a shutdown last Friday on 11/09/07 and all went well. DK has not been above the ceiling in the crawl space yet nor are they on site on today. To TEI, this project seems to be going well. TTC will check progress with MH at TEI to make sure we are on target for this job and possibly schedule a field trip this week to check on progress. This field trip may be combined with meeting EDI at the site to discuss the AC installation and also for TEI to review the computer room installation that Facilities is currently working on.

11/12/07 – TTC checked in with Kevin Broxterman. Equipment is ordered and DK will be on site this week not last week to do the work per the schedule agreed to with County Facilities.

10/12/07 – Pre Const Mtg held and meeting notes distributed to all attendees. Super timeline crunch has been averted by Facilities passing the accreditation testing with the understanding that this hood system is being upgraded right now. DK will order parts and scheduled work very soon.

08/13/07 – TTC interviewed Debra Kuempel and confirmed their bid price was good. TEI wrote the contact and TTC marked it up. It will be in County hands on Tuesday for approval. The PO can be acquired at the same time. TEI will apply for the IBI permit on Tuesday as well.

08/10/07 – This project was sent out to bid on August 2, 2007. A mandatory pre-bid meeting was held on site on August 3, 2007. This project opens for bid on September 3, 2007 and is to be completed by September 15, 2007.

07/27/07 – This week TTC & MH began working on the final design this week. MH visited the site for fieldwork and created the construction drawings. TTC is hoping that

05/14/07 – SOSS has been received and logged. TEI asked for a kickoff meeting around 05/28-05/31. We will await MD direction on this.

04/27/07 – TEI awaiting signed SOSS.

04/17/07 – MJ called to say that fan belts were replaced and airflow in the hoods is up significantly. One motor has been replaced previously. TTC is writing the SOSS for the report.

04/13/07 – TTC & TA met MD & BW at the site for a walk through and looked at existing conditions of the kitchen hood and electrical requirements. TTC found that the EF did not have any nameplate date on them. Airflow to hoods seemed low. MD requested traversing the hoods to confirm airflow.

HILLCREST – KITCHEN HOOD UPGRADE Read More »