Hamilton County Facilities

TEI

ADMIN – LOBBY DESK RELOCATION

12/07/07 – CRA sent contracts to BW on 11/29/07.

11/30/07 – The bids have been opened and although, TEI wasn’t at the bid opening, we believe HCG may have won the bid. CRA would have to confirm.

11/15/07 – CRA BW directed to prepare contracts for HGC.

11/12/07 – TTC and MH has sent out Addendum 01 through CRA. The bid opening is 11/15. Zach sent Addendum out for bidders. Addendum included information on relocating and interior light switch and alarm security panel by the EC while the owner has agreed to have the HVAC sensors moved by JCI or by their HVAC team.

10/30/07 – Pre-bid meeting held at C.A.B. first floor lobby at 1pm.

10/19/07 – Bid documents completed. Bid issuance date is 10/23/07.

09/25/07 – Cost estimate entered into Archibus.

09/14/07 – CRA received drawings from TEI. Drawings updated. Awaiting approval to complete and issue for permit.

08/28/07 – CRA issued DD drawings.

08/02/07 – Project being resurrected. Kickoff meeting was held.

ADMIN – LOBBY DESK RELOCATION Read More »

ADMIN -Auditor’s Office – 4th & 5th Floor Renovation

02/08/10 – Payapp has arrived. TEI finished the as-builts drawings. We are shipping the original record markup dwgs, cd’s and final payapp to Bert for closeout.

02/04/10 – Look i can’t take it any longer. This project has to be moved to the Archive. It is just too old. I will update the final QCE payapp when it arrives. It is being moved today.

01/28/09 – TEI contacted QCE but Cavanaugh is out. We have not received their final payapp. As-Builts are almost done with Cad markups by TEI.

12/31/09 -QCE turned in closeout documents today for approval to TEI. TTC received and approved. As-Builts will be updated in 2 weeks by TEI. We need a final payapp from Queen City still for approval which is coming next week according to Mike C. After that this job will be closed out.

09/22/09 – We have contacted Queen City several times about closeout and still have not received the documents.

08/20/09 – QCE payapp has been approved but we have not received their closeout documents yet.

07/29/09 – QCE reported today that they know the O&M’s are due but they have just been too busy on trying to get new work in today’s market to finish them up. TTC told them that they could bill for retainage on this project and leave the closeout document line item at 0% until they submit the O&M’s. Cavanaugh said he might do this but they will work on the closeout docs.

06/23/09 – The final EDI item is the revised sequence which TEI wrote and sent to Data Aire and EDI for approval. The sequence has been approved but TTC is waiting in equipment deadband from DA. This is not critical to finishing the sequence. TTC may just update and send final to Bert. All other project contractors are complete. Get an update on closeout from Bert on EDI, QCE, CDFP paperwork.

05/22/09 – Data Aire Unit is running as designed on both chilled water and DX cooling. The system is changing over quickly and keep the space cool. TEI to write final sequence for the project.

04/15/09 – CR Architecture and Design awaiting final punchlist items to be completed.

04/03/09 – All work and punchlist items have been completed by EDI on this project. O&M’s have been logged in. Final payapp has been received. The payapp #2 was on hold but has now been release to Bert. The CDFP closeout paperwork was signed and sent to Bert yesterday. Queen City still owes us final payapp and O&M’s on this project. EDI still has to use chillers in the building before we know everything works.

02/18/09 – A controls meeting is scheduled for Friday with EDI and Data Aire.

02/07/09 – TTC requested a revised payment from EDI for this project.

02/02/09 – Terry & Mike will be down for project punchlist on Feb 4 for final walk through. The new insulation worked perfect through the cold snap last week. Bert reported no condensation on the unit, even on the the through metal parts.

01/22/09 – EDI is at the site today installing the insulation inside the unit today. All interior surfaces.

12/20/08 – Problems with the Data Aire Unit still exist. Condensation is a real problem. The unit is not insulated. DA said they can fix this problem with insulation. The controls and the chilled water pump are still not interlocked. A JCI N2 card can help the situation. Duft said that would be the easiest to use. TTC said it was going to be provided at no cost from DA on this project.

11/25/08 – TEI is working feverishly with EDI and QCE for final change orders. Hours were spent trying to resolve QCE change order #3 today and it still wasn’t exactly right. Another $317 needs to be written for QCE. ThermalTech must complete final punchlist on this project.

11/24/08 – Project is 95% complete. Final Change Orders need to be in by 11/26. TEI is working on them today.

10/16/08 – Bert reports that Stewart will be making all final computer moves this weekend and by Monday all essential Auditor equipment will be on the 5th floor. Demo of the 4th could start shortly for all contractors. QCE has made more modifications to the plug strip on the server racks and disconnected the 4th floor rack to facilitate its move to the 5th floor. The project is finally making progress towards completion.

09/18/08 – Trying to setup TCO for next week.

09/17/08 – Server must be running by next Tuesday. Fan test not complete. Temporary route condensate to 4th floor hub drain. EDI ductwork not installed. Power outage has delayed final fabrication of ductwork.

09/04/08 – Elevator quote came into today for $3k. Work to be done next Monday with Thyssen Krupp and EDI.

08/2508 – TTC sent out the plumbing Bulletin drawings to Helmes plumbing et al.

08/22/08 – TTC visited the site today for floor drain relocation. UPS is in and being wired. Disconnects are installed. Fire protection is in 5th floor room.

08/08/08 – Const Mtg notes from today include

08/01/08 – GM located new locations for the bus plugs disconnects for the project. One on the 5th and one on the 4th. QCE will have to move an existing disconnect to make the new ones fit.

07/30/08 – Data Aire Unit ship date is August 20. It will arrive 3 or 4 days after that. Quick ship prices were given but overly costly to the project for the minimal gain.

07/17/08 – Const Mtg. We discussed project schedule for this project. Contractors reviewed progress. Demo found a stairwell pressurization fan in the new computer room that must remain as is. EDI will seal ductwork. Computer room unit delivery is 4 to 5 weeks.

05/30/08 – Pre Const Mtg complete. Equip 5 weeks out. Contractors to provide schedule for start of the project.

ADMIN -Auditor’s Office – 4th & 5th Floor Renovation Read More »

ADMINISTRATION 8TH Flr Planning Renovation

08/13/10 – The space looks great. Tenants say they are not used to the new work flow yet but will give it time.

07/23/10- -Work continues. BW is handling the Const Admin of the trades work on this project. No new questions or issues that TEI is aware of.

05/26/10 – TTC will check on progress while at the permit office on Thursday.

05/13/10 – City sent permit receipt to TEI for use on this project. All permits look to be approved at the City Web portal.

05/05/10 – Check on progress with Dave S and Bert W. IBI inspections for rough in are complete. Cindy office is under nightly construction.

04/26/10 – Work has begun. Phasing was taken over by Bert. We check the scale of the drawings on D size prints and it was right, check with Bert on Thursday to see what the issue is.

03/24/10 – Arch permit review is complete. The changes will take some time and we need updated specs from Speer. These should be permitted on Thursday/Friday.

03/23/10 – Permit drawings are being reviewed inside ThermalTech and at the Architects office. We should be acquiring permits by Wed or Thurs this week. We have incorporated all the client comments into the drawings and added specs to the job.

02/24/10 – We had the SD review meeting. Bert asked for a new SOSS for permitting the job and incorporating the changes and Archibus input. Smorey requested a new schedule. TTC will get that completed on Friday.

02/04/10 – We are still trying to get an SOSS worked out with Public Works for this job and Bert is assisting us in this attempt.

01/28/10 – TTC and Bert discussed a new SOSS for County Trades installation and TTC provided it. There is some doubt about how will do this work and how it will get design. TEI will wait for Facility guidance before proceeding.

12/21/09 – TTC, BW and Smorey met on site to go over the changes required in the renovation. TTC got drawings copied for Hamco and TEI and is preparing the SOSS. This project will require electrical, fire alarm, mechanical and general work to complete.

ADMINISTRATION 8TH Flr Planning Renovation Read More »

ADMINISTRATION – 7TH Flr Engr Furniture & Electrical

03/30/11 – Project is complete. Art Smith & TJ Williams invoices has been sent to Pat Day for final payment.

02/22/10 – The initial stage is complete. I believe I am waiting on the County to find some furniture pieces for us to use to fix up the remaining parts. I haven’t heard back from Judy on how well the repairs went.

01/24/11 – We have finished the first pass through on the furniture fix up. I need furniture pieces to have Art Smith fix up the remaining parts to get it as good as it gets for its age. I would like to move to next phase and replace the front counter after we get our contract and counter SOSS approved.

10/25/10 – TJ Williams bid was resent to Judith. Engr needed more information. Ginter has to update their bid and we will forward that along.

09/29/10 – Bids were collected and sent to Bert. The 2 day repair cost is under $2000.

07/28/10 – Need Judith contact info. George Mullins may have to design this project with Susan.

07/23/10 – ThermalTech attempted setup a design meeting for SD and Cost. Judy email bounced back so I need to find her new number.

05/26/10 – SOSS approved. We will setup fieldwork and kickoff next week.

04/26/10 – Schematic Drawing is complete. Fieldwork is complete for SD. We are working on cost estimate to send with SD.

03/23/10 – Project on hold.

01/26/10 – Bert contacted ThermalTech about permit requirements and was told the mechanical code would require a permit for the new ventilation calc required in a new conference room. Bert has the SOSS for this project.

12/31/09 – Bert contact TEI to work on this project and renovation. TEi owes Bert an SOSS based on the HamCo Scope of Work.

ADMINISTRATION – 7TH Flr Engr Furniture & Electrical Read More »

CAB – Access Control Project

09/22/10 – SOSS Approved. Review comments sent and received from Bert.

09/29/10 – Markups corrected from BW. QC check complete. TEI needs to pick up NV marks and send to Purchasing on 10/1.

10/28/10 – Contracts for ICS have been sent to Bert Watts for approval. Project is under budget. No allowance has been added because of a bonding issue.

01/24/11 – Bert and George decided a pre const mtg will be set next week to kick off this meeting.

02/22/10 – Paul Wilson has made good progress on this project. Wiring is ran on upper floors and they are working their way down to the dock.

03/30/11 – Paul Wilson submitted and change order to remedy the power supply issues on the tenth floor. REX needs to be changed so the door does not open at night when approached by security. GM said that the contractor can reprogram this feature. Project seems on track.

04/27/11 – Bert reports that installation is very nearly complete and the system is ready to begin use this week or next.

05/13/11 – Punch list was issued to IPS. Project should be wrapping up.

06/29/11 – IPS has submitted its main pay app, now we need to close out the rest of the project.

08/28/11 – New Signed change order came back. IPS should be doing this work soon, rest of project complete. We can request closeout at any time.

09/28/11 – All work to be completed has been put on hold per TTC.

10/24/11 – The certified payroll for IPS for the dates 10-2 through 10-9 was sent to Hamilton County and TEI.

11/15/11 – IPS requested final payment from Hamilton County in the amount of $4,984.22. TTC responded by saying all paperwork had been sent to Hamilton Co. and IPS should get paid per the Contract.

12/23/11 – This project will be archived for 2012.

CAB – Access Control Project Read More »

CAB – Sheriff’s Re-entry

01/20/12 – Mike B. spoke with Mr. Gaylord Poe, President and Chief Electrical Inspector for IBI regarding the CAB space. Mike explained that there is minimal electrical work being completed on the project, and that the electrical connections will be able to re-use the existing circuits that were removed from the systems furniture when it was disassembled. In order to get a permit, a plan exam is required with IBI. Gaylord and I discussed that the net electrical load on the space will be significantly lower than what was there previously. Gaylord said that if we draft up a letter, and submit it to him directly, he will approve that as a plans examination, and we will be able to then secure the permit. Mike has drafter the letter, and will run the letter with the permit fee to IBI asap. Actual plans, panelboard schedules, single line diagrams, etc will not be produced for this project.

01/30/12 – Mike walked through the electrical permit at IBI, and then dropped off paperwork to Steve Wessels. A final electrical inspection has been requested for Wednesday Feb. 1st. Upon verification of the inspection, Mike will send a follow up e-mail.

03/07/12- Walk-through permit was conducted by GBBN. Permit approved conditionally requiring Mechanical Permit to validate movement of existing linear diffusers to other side of new partition.

05/30/12- Bert Watts requests As-Built drawings to be completed. He indicates the Building Department has given final approval of construction.

CAB – Sheriff’s Re-entry Read More »

CAB – First Floor Security Cameras

02/22/12 – SOSS Approved. TEI and Hamco to have a kickoff meeting for the project on 02/23/12.
03/27/12 – On 03/09/12, ThermalTech issued drawings for County Review. Received comments from Bert Watts and Chris Neff, waiting on final comments from Rodney Lofland to complete project, and issue and ITB.

5/30/12 – ThermalTech submitted drawings and specifications to County for final review (with all county comments incorporated). Waiting on notification from county to proceed with issuing for bid.

6/26/12 – Project on hold until notified otherwise from BW.

CAB – First Floor Security Cameras Read More »

CAB- 7th Floor Engineering Office- Phase 2 Renovations

06/15/11 – SOSS delivered to Bert Watts.

07/08/11 – GBBN informed the County does not have the required funds to proceed with project at this time.

07/20/11- Meeting between design team and Owner/User Group.

03/20/12 – SOSS re-submitted to Bert Watts.

03/26/12- Bert Watts notifies GBBN that Judy Sellmeyer has retired. Her replacement is trying to get up to speed on projects.

CAB- 7th Floor Engineering Office- Phase 2 Renovations Read More »

CAB Beam Repair

Partner: THP

03/20/13 – THP met with County to review beam condition in the basement of the Administration building. Based on the initial visit an additional assessment needs to occur to determine the effect of the active deterioration on the beam. The assessment will determine the need to stabilize or repair the beam.

04/04/13 – THP and County reviewed available drawings.

04/17/13 – THP issued SOSS.

04/22/13 – County declined SOSS due to funding. THP published closeout email; answering County questions.

CAB Beam Repair Read More »

ADMIN Boiler Flue Phase 2

Partner Lead: TEI

09/26/13 – At Partner Meeting we discussed including as an Alternate to my rebid package, adding some additional tuck pointing. TTC to coordinate this with Tony Matre.

10/01/13 – THP issued SOSS.

10/09/13 – Hamilton issued executed SOSS for THP.

10/21/13 – Bid Package out for Bid.

10/31/13 – Pre-Bid schedule for 11/01/13.

01/21/14 – Tony said project is not scheduled to start yet. It is probably on hold.

ADMIN Boiler Flue Phase 2 Read More »

ADMIN Public Defenders Renovation 9/10

Partner Lead: GBBN

08/28/13 – GBBN and ThermalTech met with the Public Defenders about possible office relocation into the Admin bldg on the 9th or 10th floor. PDO indicated they preferred having two departments on separate floors; one for guardians and one for juvenile. On either option ThermalTech believes they can shrink the computer room down to a smaller footprint and make it work in either option. ThermalTech went back to the computer room and did a take-off of all existing equipment for a more complete layout the new computer room to schedule a meeting with HamCo CMS soon.

08/28/13 – TEI sends markups of Roof Top Equipment affected by scope of work.

08/30/13 – Facilities indicates the 10th Floor scope will not be approved.

08/31/13 – GBBN/IPM send floor plan layout indicating the 10th floor CLEAR and Community Development areas together would be suitable for receiving the GAL department to Facilities.

09/02/13 – Facilities contacts GBBN to inform that the 10th Floor scope will be reconsidered.

09/06/13 – Facilities requests a revised SOSS be submitted for the Tenth Floor relocation scope.

09/06/13 – GBBN submits revised SOSS to Bert Watts for processing.

09/10/13 – Diana Supe requests dates of availability for Kick-off meeting with Public Defenders Office and Facilities Department.

09/11/13 – GBBN received approved SOSS from Bert Watts.

09/17/13 – Re-kick-off Meeting held at 230 WHT Law Center with PDO, Facilities, GBBN, IPM and ThermalTech.

09/25/13 – Team met with PDO and Facilities to discuss computer room options in center of building and present initial cost estimates on all 3 options for 9th & 10th floor work. Everyone agreed to the computer room being built around the 4 communication racks, modifying the waiting area directly off the elevators, putting attorney offices on the west wall and leaving a growth area to the west of the computer room.

09/26/13 – At the partner meeting we learned that there may still be VAT tile remaining on the 10th floor CLEAR area and the 9th floor offices outside the computer room. GBBN will update the cost estimate for these options.

ADMIN Public Defenders Renovation 9/10 Read More »

ADMIN 610 DOC Room

Partner Lead: ThermalTech

03/04/13 – SOSS submitted to Bert.

04/24/13 – SOSS approved and PO issued to ThermalTech. ThermalTech to schedule Kickoff meeting with Bert Watts to establish schedule.

6/26/13 – TEI has sent drawings to HamCo for review. Need to discuss HamCo comments and issue for bids.

08/28/13 – Pre-Bid meeting conducted on 8/28/13. It was observed that (2) fiber optic data cables were already installed from the data rack in the closet by the freight elevator to the A/V cabinet in Room 610.

09/25/13 – Bids received, Phasor Electric is Low Bid. Contracts are into county for approval.

10/30/13 – Phasor to begin work week of November 4.

01/24/14 – Work completed. Phasor to submit final as-built drawings and project can be closed out.

02/25/14 – TEI reviewing as-built drawings. All other close out documents have been turned over to Hamilton County.

ADMIN 610 DOC Room Read More »

ADMIN Boiler Stack Removal

Partner Lead: ThermalTech

05/07/13 – Met Geiler on site to discuss steel stack issues.

05/21/13 – Met Van Packer & Geiler on site to discuss removal of the Van Packer stack vs the standard 1/4″ steel stack. We asked Geiler for a change order to remove the entire stack. Regardless of what we do with the existing stack we told Geiler that we wanted to do the EGEN exhaust stack work in this phase.

06/25/13 – Geiler cannot find a contractor willing to take down the stack. ThermalTech asked for a 2 week schedule to put the EGEN exhaust modification in for the base bid work. We will have to address the remaining funds as a deduct change order.

08/19/13 – We had Pinnacle check the EGEN stack and muffler for asbestos. All samples came back clean. Geiler required that report in writing. Tony Matre provided to contractor.

08/26/13 – Coredrills are complete. EGEN exhaust has been rerouted through outside wall. SS end cap and birdscreen is installed. 10″ sleeve is installed but needs to be trimmed back. Insulation needs to be reinstalled. ThermalTech instructed Geiler to get a change order price from R&P in Lexington to do the work. We will decide on a change order after Tony sees how much money is left in budget at end of fiscal year 2013.

09/26/13 – ThermalTech informed Geiler to wrap up EGEN work and provide a credit for the boiler stack work. This scope will be rebid this year.

10/01/13 – THP issued SOSS.

10/09/13 – Hamilton issued executed SOSS.

10/18/13 – THP issued drawings to TTE.

10/29/13 – TEI sent out back punchlist items to Geiler and asked for project closeout.

01/24/14 – TTC contacted Geiler for final closeout and gave them a deadline of 1/27 at 4pm for closeout documents.

02/24/14 – Project still not closed out. TTC will contact Geiler again.

03/21/14 – Geiler came down to finish the insulation and was held up by someone. Tony said it was the County that stopped them. TTC asked Doug to find out who stopped them but I have not heard back yet.

04/04/14 – Geiler has come back two more times to work on insulation and replace one sprinkler head. We are still waiting for final closeout and change order documents.

05/22/14 – Punchlist completed. Waiting on County approval to closeout.

06/02/14 – Geiler contacted again for closeout docs. Doug Weberding says it will be soon.

07/30/14 – Geiler sent closeout docs to Tony but Payapp and change order are both wrong. TTC sent revised Payapp and new change order to Geiler for signatures.

08/15/14 – Geiler inquired about final payment. TTC forwarded to Tony.

ADMIN Boiler Stack Removal Read More »

ADMIN Energy Star 2014

Project Lead: TTE

09/23/14 – SOSS approved. TTE to setup verification field trip with Rich.

11/28/14 – The EPA sent several questions in about the Data Center and TTC answered them immediately with pictures, graphs and charts explaining the validity of this data center.

12/12/14 – Building still listed as “Under Review”.

12/18/14 – Energy Star was awarded to this building.

ADMIN Energy Star 2014 Read More »

ADMIN Facade Repairs

Partner Lead: THP

08/29/13 – County requested SOSS to provide repairs to the Terracotta at the first and second floors.

09/09/13 – THP met with Mike Florimonte to discuss scope and review the conditions.

09/13/13 – THP issued SOSS and Tony Matre verbally authorized work to begin.

09/23/13 – THP completed field survey.

09/25/13 – THP completed rappelling survey.

10/02/13 – THP issued Owner Review documents.

10/10/13 – Bid Documents Issued.

10/18/13 – Prebid Conference.

10/24/13 – Addendum #1 Issued.

10/30/13 – Bid Opening completed with five contractors under the budget. County reviewing bid proposals.

11/05/13 – ZSR Construction was the low bidder.

11/11/13 – THP sent AIA contracts to the County for review.

02/20/14 – County returned marked up Contract to THP for final publication.

02/21/14 – THP sent updated Contract to ZSR.

02/25/14 – ZSR sent completed contract and forms to THP.

02/25/14 – THP sent final contract documents to County for execution.

03/27/14 – ZSR has received an executed contract. ZSR and County need to schedule the start up.

04/01/14 – ZSR submitted submittals to THP.

04/07/14 – THP returned submittals to ZSR.

04/10/14 – ZSR submitted a construction schedule. Mobilization and work is planned to start 6/2/14.

05/29/14 – Waiting on project to start.

06/16/14 – ZSR started work. Terra cotta and concrete repairs in progress on West and South elevations. Work is occurring at night to keep entrances open and minimize noise and dust interruptions. Expected completion date is end of July.

07/31/14 – ZSR completed all repair work. ZSR working on coating work.

08/15/14 – Construction is complete.

08/18/14 – Pay Applications 1 and 2 delivered to Tony Matre.

08/19/14 – Concrete patch included paint to match surrounding area. THP rejected the patch application as not matching. ZSR completed a second paint application and Tim Bennett noted the match was acceptable to THP. THP recommend, County review the color match prior to accepting the coating color.

09/25/14 – ZSR completed all repair work. THP awaiting warranty/closeout paper work and final pay application.

10/13/14 – ZSR submitted all closeout warranty paper work and final pay applications to THP. THP forwarded approved closeout paper work to the County.

10/16/14 – Closeout paper work and final pay application submitted.

01/29/15 – Project complete.

ADMIN Facade Repairs Read More »

ADMIN Recorder’s Storage Room

Partner Lead: GBBN

01/24/14 – Project Scope meeting scheduled for 01/28/14.

02/03/14 – THP – GBBN requested possible structural analysis of storage relocation project and THP provided an hourly estimate for THP services.

02/25/14 – GBBN and TEI met with Bert Watts to investigate the possibility of relocating the file storage to the CAB 10th Floor CLEAR area. GBBN generates a preliminary sketch indicating the files will fit into the area designated at the meeting. Bert Watts indicated General Services will be used to generate a Schematic Design and Opinion of Probable Cost for this scheme.

02/26/14 – GBBN confirms a second access door will be provided into the File Storage and the adjacent workstation will be removed to allow for the door placement. Revised cost estimate is due this Friday to Bert. ThermalTech believes this work can be done without an additional Liebert cooling unit given the HVAC design and CFM’s currently in place in this space.

03/12/14 – GBBN issues SOSS to Bert Watts involving change to 9th Floor Relocation in the existing CLEAR offices.

04/23/14 – GBBN, ThermalTech and Bert kicked off the design of this project today. Design drawings are due June 26 partner meeting. Work to begin after CLEAR moves before December.

03/13/14 – THP noted to GBBN an initial analysis of installing shelving on the ninth floor is possible and a full study will be needed to confirm the proposed final loading. THP based the recommendation on an earlier study in 2012 for a proposed shelving arrangement.

04/24/14 – THP – GBBN approved the full analysis.

05/19/14 – GBBN receives dead load figures from Republic Storage for the existing newer shelving units. This information is forwarded to THP for their load analysis.

05/27/14 – THP completed the analysis of the proposed shelving solution on the ninth floor. THP does not recommend the proposed loading configuration, based on the current information and proposed arrangement. The 2014 shelving arrangement substantially increased the loading from 2012 arrangement. To allow shelving to be moved to the ninth floor, THP recommends either spreading load over additional bays or investigate the slab to determine the slabs reinforcing.

05/27/14 – THP forwards Load Analysis report to GBBN indicating the existing floor loading capacity will not support the current layout for relocating the existing file storage. ThermalTech started design and created floor plans, put on hold for load analysis.

06/10/14 – THP – Terracon completed scans of floor to determine bar sizes.

06/14/14 – THP – Terracon published report to THP.

06/24/14 – THP – THP completed an analysis based on the Terracon report and published a letter to the County for review.

07/31/14 – THP study complete. Bert says project funds are being reallocated, this project pseudo on hold.

08/28/14 – THP – Correction to 7/31/14 entry. THP portion of study complete.

ADMIN Recorder’s Storage Room Read More »

ADMIN Heroin Task Force

Partner Lead: GBBN

04/08/15 – Kick-off Meeting with Bert Watts to review site and discuss scope.

04/08/15 – AFSS scope clarified with ThermalTech related to placement of new wall related to existing sprinkler heads.

04/10/15 – GBBN sends door hardware schedule to Facilities for purchase of door and frame. GBBN coordinates electrical scope for door hardware access control with ThermalTech.

04/15/15 – GBBN and ThermalTech provided notes and code interpretations for the owner to self-perform work on the existing spaces to fast occupancy. We will continue to support the owner as permit and construction questions arise.

04/17/15 – Drawings were issued for permit which include General Architectural and Electrical Drawings. GBBN attempts a walk-through permit. Minor door hardware corrections requested related to access control code section 1008.1.4.4.

04/21/15 – GBBN revises drawings and resubmits to City of Cincinnati Buildings and Inspections. Plans Examiner requires change to owner requested pull station for access control hardware.

04/22/15 – GBBN revises drawings and resubmits to City of Cincinnati Buildings and Inspections and obtains Building Permit during walk-through inspection. Building Permit delivered to Facilities Department. Building Permit #2015P02980.

05/26/15 – TEI picked up and dropped off to Facilities Department the Electrical Permit from IBI, permit Number CIC1501884.

07/22/15 – Install substantially complete, and TEI drafted a letter to John Nester with electrical loading information outlining the field changes that occurred and the effects that the field changes had on the service calculations. John Nester stated that trades electricians will submit to IBI on final inspection.

08/27/15 – JCI extending relay to door in space for fire alarm interface.

09/24/15 – At Partner Meeting, we said project was pretty much complete. Is it ready to archive?

10/28/15 – Project read to archive?

ADMIN Heroin Task Force Read More »

ADMIN Re-Entry to CLEAR Space

Partner Lead: TEI

01/07/15 – Bert Watts contacts GBBN about Kick-off Meeting.

01/13/15 – GBBN and TEI visit site with Bert Watts for kick-off meeting. After meeting both firms send SOSS to Facilities Department.

01/14/15 – GBBN sends updated schematic design drawings to Bert Watts and TEI for review. TEI initiates Mechanical scope drawings to each.

01/23/15 – GBBN requested by Facilities Department to revise drawings for the Auditor proposed relocation to CAB First Floor.

01/27/15 – GBBN, issues revised preliminary floor plan of Auditor’s proposed relocation to CAB First Floor. Facilities sends to Auditor for review.

03/18/15 – ThermalTech sent in revised SOSS for Architectural and Engineering estimates for approval. We kept the AE fees under $50,000 but that makes the contingency left on this project lower. The amount of system furniture that can be used and is in storage is in question.

04/07/15 – Project is sort of on hold. Some work is being done as a basic necessity now but as the final details are flushed out the partners are on hold.

04/30/15 – BW requested new SOSS for moving Sheriff Reentry to 10th floor in much the same configuration as 9th. GBBN to have TTE under their SOSS, meet with Reentry program and try to save Facilities storage space on the same floor.

05/19/15 – GBBN requests clarification of scope for original SOSS.

05/27/15 – Bert Watts requests SOSS be revised in scope to only included Schematic Design and Estimate.

06/25/15 – Bert said that CLEAR moved out this week and this project will probably start in July or August.

08/10/15 – GBBN requests clarifications from Facilities on scope of work. Facilities responds with associated answers. Facilities issues Archibus Pop-up Project Request Number for estimating input.

08/19/15 – GBBN completes Architectural scope estimate in Archibus.

08/20/15 – TEI completes Mechanical and Fire Protection scope estimate in Archibus.

08/25/15 – TEI completes Electrical scope estimate in Archibus.

10/27/15 – GBBN sends revised floor plan to Bert Watts for review.

10/28/15 – Bert Watts indicates the revisions are acceptable. He will submit to Re-Entry for approval.

ADMIN Re-Entry to CLEAR Space Read More »

ADMIN Sheriff’s Fugitive Detective Relocation to 9/10

Partner Lead: GBBN

10/13/16 – GBBN, ThermalTech and Facilities Department meet to propose a new SOSS for two options for relocating the Sheriffs’ Fugitive Department to the CAB 9th or 10th floors. Facilities provides sketches for each option.

10/13/16 – ThermalTech sends preliminary labor costs to GBBN for the SOSS.

10/17/16 – GBBN contacts IPM about the project and obtains estimates for labor related to systems furniture and move services.

12/28/16 – GBBN finishes estimates and checks in with ThermalTech for progress. TTC for finish fist couple of days of 2017 after everyone returns to work.

01/23/17 – All cost estimates are updated in Archibus and were sent to Commissioners by Bert for funding determination for Option #1. Option #2 was removed because of the Halon cost associated with project.

ADMIN Sheriff’s Fugitive Detective Relocation to 9/10 Read More »

ADMIN – Lobby Lighting/Finishes/Auto Title Door

Partner Lead: GBBN/IPM

07/23/15 – Bert Watts contacts GBBN about Kick-off Meeting. GBBN reviews attached documents and requests clarifications.

10/28/15 – GBBN and IPM meet with King Lighting to review scope of work at site.

11/03/15 – GBBN and IPM meet with King Lighting to place sample light fixtures on columns at site. Summary of discussions and decisions sent to Facilities.

11/04/15 – Cost Estimate for Auto Title Door project sent to Facilities.

11/05/15 – GBBN consults Facilities about lighting level issues at north elevator bank verses south elevator bank.

12/07/15 – King Lighting sends final cost estimate and fixture cuts to IPM for lighting upgrade recommendations.

12/07/15 – GBBN contacts directory vendor for estimates on directories for Elevator Lobbies.

12/08/15 – ThermalTech delivered cost estimate for installing extra power and installation for new light fixtures.

12/09/15 – GBBN and IPM to meet to discuss rendering views required and all cost estimate data received.

04/07/16 – Facilities requests GBBN author an AIA Change Order to KFI for the secured employee entrance inside the BMV vestibule.

04/27/16 – GBBN authors Change Order for new Secured Employee Entrance.

05/13/16 – GBBN receives authorized copy of Change Order.

ADMIN – Lobby Lighting/Finishes/Auto Title Door Read More »

ADMIN – 6th Floor Chief of Staff Renovation

Partner Lead: GBBN

11/30/16 – GBBN issues SOSS to Facilities.

12/15/16 – GBBN receives approved SOSS from Facilities.

12/6/16 – GBBN visits site with Facilities and photos and takes measurements for field verification.

12/14/16 – Drawings issued for permitting.

12/15/16 – GBBN completes drawings for owner review. GBBN receives drawings and Mechanical Permit application from TEI. GBBN performs new City of Cincinnati Building Department Same Day Permit Walk Through processes. Permit and approved permit is delivered to Facilities.

12/27/16 – Terry and John meet on site to discuss extra sprinkler location. TTC states that sprinkler is not need given the actual wall layout, it is exactly 7′-6″ from interior wall. This should save some money. If city requires and ECO, TTE and GBBN will take care of this at final inspection.

01/25/17 – IBI final electrical inspection passed, and tag placed on serving panelboard.

01/27/17 – Project is complete, waiting on the closeout documents from everyone. Ready to due as-builts.

02/01/17 – Revised energy impact study sent to Bert Watts for review. Small savings but ThermalTech used HAP to generate the savings and it matched the original estimate.

02/23/17 – John to send ThermalTech as-built markups for this job.

ADMIN – 6th Floor Chief of Staff Renovation Read More »

ADMIN – 5th Floor Roof Access Hatch

Partner Lead: THP

09/07/16 – Hamilton County requested THP review a proposal to add an access hatch and railings to the 5th Floor mechanical space.

09/26/16 – THP and County setup planning meeting to review conditions and proposal.

10/27/16 – THP reaching out to LGB to develop a proposal.

12/05/16 – LJB provided fall protection design services to THP.

12/06/16 – Draft SOSS provided for review. Hamilton County placed SOSS on hold.

03/10/17 – Tony Matre calls GBBN to discuss permitting issues and logistics concerning Safety Railing products used at Alms and Doepke Roofing Restoration project.

ADMIN – 5th Floor Roof Access Hatch Read More »

County Administration – BMV Cooling Issues

08/03/16 – TTC was on site with John Gilbert yesterday troubleshooting the BMV area. It looks like its fed from AH-1 not AH-3 as originally thought. County to investigate and get back to TEI. Airflow on CV box was also locked in at 20% and several boxes were set to 0%, I would assume due to overcooling.

09/25/17 – No movement on this project. TTC sent an email to Tony about this project and helping if needed.

County Administration – BMV Cooling Issues Read More »

CAB Heroin Task Force Security System

Partner Lead: TEI

08/16/16 – TEI meets with Lt. F of the Heroin Task force, and walks the project to develop scope of the project. TEI submits SOSS to HamCo facilities department. Project pending SOSS approval and PO.

09/28/16 – Project pending SOSS approval and PO.

10/25/16 – project pending SOSS approval and PO – per facilities, pending grant to be issued after first of the year.

01/25/17 – Project pending SOSS approval and PO.

02/22/17 – Project pending SOSS approval and PO.

03/22/17 – Project pending SOSS approval and PO.

04/26/17 – Project pending SOSS approval and PO

05/22/17 – Project pending SOSS approval and PO.

06/27/17 – Project pending SOSS approval and PO.

07/25/17 – Project pending SOSS approval and PO.

08/28/17 – Project pending SOSS approval and PO.

09/26/17 – Project pending SOSS approval and PO.

10/25/17 – Project pending SOSS approval and PO.

11/29/17 – Project pending SOSS approval and PO.

CAB Heroin Task Force Security System Read More »

2020 AUBURN – BUILDING ASSESSMENT

05/03/07 – Hard copy report is finished and being delivered to Mark Donnelly.

04/26/07 – TTC told Mark that he would incorporate Don Benbow’s mark up and update the website and give him 6 new hard copies.

04/18/07 – The only comments that we have received are from Don Benbow. We will update the report for the items we are willing to concede and update and send down final copies to Mark Donnelly if he is okay with this approach.

04/13/07 – Issues in disagreement are being worked out.

04/04/07 – Matre forwarded some comments from Don Benbow. TE may incorporate his suggestions into the report. We however disagree with some of them.

03/30/07 – Email copy has been delivered to Mark Donnelly for markup. TEI will provide 6 hard copies upon receipt of HamCo comments.

03/23/07 – Awaiting notification to provide hard copy of report.

03/20/07 – TTC to input report on Wednesday. Report has been input to Archibus. Review set to be hand delivered on Thursday.

03/14/07 – NR created project journal and filled in back data from previous meetings. Report completed, information to be inputted into Archibus on 03/12/07. Hard copy will be delivered during the week of 03/12/07.

2020 AUBURN – BUILDING ASSESSMENT Read More »

2020 Boiler Replacement

01/24/11 – All punchlist and closeout documents have been sent to Bert for this project. Receptacle was moved by Ginter on water softener.

10/1/10 – All work is complete. Seco has not turned in final closeout paperwork yet.

09/22/10 – Peck has scheduled change order work to start at the end of September. ThermalTech has provided answers to the PHB questions on the Change Order work.

08/13/10 – Peck submittals are approved on water heater and all other change order work. Seco change order was sent out for signing. Seco payapps sent to Bert for payment. Siemens payapps sent to Bert for payment.

07/23/10 – Peck change orders are approved. Folck is working on Seco closeout documents and change order forms. Peck is to schedule change order work starting next week. Bert is trying to get PO for water softener.

06/02/10 – Siemens has provided pricing for OM-1 Actuator Option to convert 2-position valves to modulating. Isolation valves will need to be modulating to avoid damaging system shock.

05/28/10 – Boiler installation has been approved by IBI. There are a few minor issues which Seco will complete next week. PH+B has provided pricing to install blank off orifice plates to convert (3) 3″ flanged 3 way bypass valves to 2-way valves for AHU-1,2,3. Blank off plates are 1/16″ thick with a 1/4″ hole in the center for relief and will be installed between the existing valve gaskets and flanges. CB BLR-3 and BLR-4 have been successfully fired and will continue commissioning by Siemens next week.

05/26/10 – Boiler installation has been approved by the State/City and is ready for startup with CB Thursday and Friday (5/27-5/28).

05/24/10 – We had a construction meeting today for the project. All mechanical and electrical work has been completed. Siemens will be on-site all week to install control wiring and begin controls startup / commissioning. Boiler inspections are scheduled for Wednesday (5/26 – State/City) and Thursday (5/27 – Electrical). Boiler startup with CB is scheduled for Thursday and Friday (5/27-5/28).

05/21/10 – HWS/HWR and NG piping have been completed. Condensate drain line and relief valves will be installed Monday (5/24). Combustion air intake has been modified to eliminate 45 degree elbow around conduit rack. All electrical work has been completed including VFD’s, pump, and boiler feeds. Current transformer has been fixed temporarily until new transformer is installed on Monday (5/24). Control panel has been installed and conduit for control wiring was run to boilers and pumps. CC will be on-site all next week (5/24-5/28) to install control wiring, thermal wells, and begin programming with Chris Neff.

05/18/10 – Combustion air and exhaust have been installed for Boiler #3 & #4. (1) 45 degree elbow was used on intake air to avoid conduit rack. TTE recommends (2) 90 degree elbows vs (1) 45 degree elbow for a more appealing installation. To avoid compromising the security bars and make installation more simple, combustion air intake was not installed thru existing louvers. Boiler piping has been started and will be completed by Monday (5/24). Balancing valves or triple duty valves will not be used for this installation. Copper was considered for condensate drain lines to avoid damage by foot traffic, but is not an option due to possible erosion from acidic condensate. If problems occur in the future, condensate drain lines could be changed to sch 80 pvc or stainless steel. Electrician has moved (2) of (4) VFD’s near pumps and will complete installation Wednesday (5/19). Siemens will be on-site Thursday (5/20) for controls.

05/14/10 – Project schedule was updated and meeting notes were sent out from construction meeting on Monday (5/10). All demo has been completed for boiler #2. New Boiler #3 & #4 are currently in the assembly process and will be completed on Monday (5/17). Included boiler legs have been shortened 5″ to accommodate overhead clearance requirements. Boiler #3 & #4 have been positioned on existing concrete pad as shown on TTE drawings. Included boiler exhaust was installed opposite of drawings by factory and will be changed to match TTE drawings. Boiler piping will now be routed between boilers as approved by TTE. HWS valve has been relocated near existing HWS tie-in. TTE considering the addition of balancing valves or triple duty valves for Boiler #3 & #4. Boiler combustion air, exhaust, and piping will be installed next week (5/17-5/21). Electricians will be moving VFD’s near pumps on Tuesday (5/18) to satisfy line of site concerns. Replacement transformer is scheduled to arrive Wednesday (5/19).

05/10/10 – We had a construction meeting today for the project. Peck will begin demolition on Tuesday. Controls and Electricians will be reported next week to start their next phase of work. TTE will work on schedule and meeting notes this week.

05/07/10 – We setup a const mtg for next week on Monday to kick off the demolition on this job and to coordinate the construction issues. The permit has been approved by IBI and City. The real work begins.

04/29/10 – We continue to work on schedule with Peck. PHB came on Wednesday to begin coredrilling for the new vents. The city has the permit held up on 3 issues that TEI sent responses down for reconciliation. The electricians and Siemens are working on a disconnect issue with the VFD’s. Boiler is scheduled to be demolished on May 10 which has been approved by Don Benbow.

03/24/10 – Siemens payapp has been received but the schedule of values is not acceptable. TTC will contact Siemens. Peck payapp has been approved.

03/23/10 – All submittals have been received. All submittals have been returned. We clarified an issue with the boiler vent piping. It can be single wall with personnel protection on this job. A controls meeting is scheduled next week to work on sequences with 2020 and the Siemens. Gary Davies will attend for TEI.

02/22/10 – No word on Siemens. TEI created permit drawings sets for the contractors, as soon as they are stamped and signed, we will give to contractors. Small modifications to venting per the 02/12 visit.

02/12/10 – Met with Peck on site and reviewed project with Foreman. Contact all contractors for submittals. Neff said he could call Siemens for me to find out where their subs are.

01/19/10 – The preconstruction meeting was held on site. TEI has approved the boiler submittals but wants better paperwork. Siemens did not attend the precosnt meeting. PHB and Seco were in attendance and are working on submittals as TEI works on permit drawings for the project.

12/31/09 – Contracts are signed but the BOCC have to approve them before we start. Siemens state term contract is ready. Peck asked for and received an extension on the project completion date. Ballinger informed us through Peck that boiler prices will increase in 2010 if we don’t order in 2009. That is a problem since the contract won’t be approved because of winter hours for the BOCC.

10/19/09 – Bid came in for the project. Peck appears to be the lowest bidder. I confirmed the prices with Bernie. His labor looks low but they are willing to do the project for the price. I know have to look at the LCC for the boilers and see which is best and look at lead times on the equipment.

09/18/09 – Final bid documents were sent to Purchasing and Queen City. The Bid Opening is October 19th. The Prebid is Oct 1. Chris Neff called and wants to go over some drawing details. The controls contract will be given to Siemens under a state term contract. TEi turned over the pdf’s to Siemens but we have not heard any comments from the CC yet. Gary is in the office this week so we need to organize the final details.

08/25/09 – Control schemes are finished. SOSS is approved. TEI is working on design. We need to go back and do more fieldwork for verification and start the design on paper. We are bidding 3 alternates for boilers: Clearfire, Fulton, Sync.

07/28/09 – TTC & TZ visited the site and did the preliminary field work. TTC created and sent Tony an SOSS for the project. TTC will hand deliver the SOSS to Bert at the County Partnering Meeting.

2020 Boiler Replacement Read More »

2020 – Boiler Replacement Phase 2

08/13/10 – We are waiting on an approved SOSS to proceed.

09/24/10 – Project was bid out as scheduled. Bid opening scheduled for Oct 14.

10/25/10 – Contract for Peck has been sent to Tony for approval. Tony said he was going to pay for Boiler #1 repair this year and install the new boilers in Spring 2011.

01/24/11 – Contracts are in approval stages. Waiting for pre const mtg. Labor will start after heating season, March 2011.

02/22/10 – Pre Const Mtg Complete. Mtg notes being sent to contractors. PHB has submitted boiler paperwork for approval. The original rain caps have been removed on the boiler stacks to prevent ice puddling below the stacks. PHB is looking at installing thimble caps on all new vents. New venting and project schedule must be approved.

03/30/11 – Peck is working on boiler order and delivery. Boiler submittals and electrical submittals have been returned to Peck. We are currently trying to work out a change order on the control valves, actuators and flow meter. The project will begin in May-June 2011. We should be finished by the time summer is over.

05/12/11 – Peck is working on new background checks. All change orders have been sent through. Boilers are ordered.

06/07/11 – Boilers are at PHB and the flues should be there in a few weeks. PHB still needs to get background checks back from the State before they proceed.

06/20/11 – PHB is ready to start some sheet metal demo in the boiler room next week, also finalizing the project schedule for this job.

Item #2 – There are a couple of issues with the control equipment that we need to discuss. The acuator and valve by Keystone apparently is out of stock. They have offered a replacement that we can get, it is slightly bigger than the one we specified. The problem is TTC can’t find this model on their website. Asked Chris who they contacted locally for prices and model #’s.

Item #3 – TTC asked if Siemens or someone else preferred make the paddles wheel flow meter needed. Bernie was looking for a local manufacturer that sells the Badger flow meter, but was not aware of any yet. Did Siemens offer the one we get easily?

07/07/11 – Peck is on site performing demo. Chris has been sharing controls and wiring with the Peck for purchase through Seco.

07/21/11 – Pipefitters are complete with their work. Sheet metal guys are waiting for a fitting for the flues, and will continue as soon as they get the rest of their materials. SECO Electric will be on site Monday 7/25. Start up is scheduled for August 12th, that will give enough time to get everything complete and the boilers inspected. ThermalTech has to provide a punchlist and discuss controls with Chris Neff.

08/05/11 – TTC sent out an email punchlist to Peck from a site visit last week. Bernie said they can get this done.

08/08/11 – Peck submitted payapp #1 but the change order paperwork is not signed yet. TEI asked them to modify their payapp so they can bill more quickly on this project.

08/25/11 – All work is complete except for metal pans on louvers. Boiler alarms not part of new boilers, Bill is working on a separate change order for that. Ready to closeout. Chris is writing sequences now.

09/28/11 – Pay App #1 was resubmitted by PH&B. Approved by TTC 3 copies were sent to Tony Matre on this date.

09/30/11 – We resolved Payapp #1 issues and asked PHB for closeout documents. Tony paid the $102,600 invoice already so we voided the later invoice and asked for a #2 for closeout. The change order was signed on May 13.

10/24/11 – Payapp 2 (labeled 3) arrive and was paid. Payapp 3 (retainer arrived and was held for closeout docs). TTC advised PHB the closeout documents are due before final payment can be made.

12/23/11 – This project will be archived for 2012.

02/22/12 – Chris reports all boilers are working great but there is still some programming left for him to change or update. This project is ready to be archived. All closeout and pay applications have been sent to Tony.

2020 – Boiler Replacement Phase 2 Read More »

2020 Entry Soil Stabilization

Lead Partner: THP

08/29/13 – County requested SOSS to provide repairs to the Terracotta at the first and second floors.

09/09/13 – THP surveyed the site to determine scope of work and possible solutions.

09/13/13 – THP met with Tony Matre to discuss scope of work and SOSS.
10/31/13 – THP issued Owner review documents.

11/01/13 – Jeffrey Allen Corporation was the apparent low bidder.

11/11/13 – THP sent AIA contracts to the County for review.

02/27/14 – Project on hold.

03/27/14 – Project on hold.

04/24/14 – Project on hold.

05/29/14 – Project on hold.

2020 Entry Soil Stabilization Read More »

2020 Masonry Investigation

Partner Lead: THP

02/03/16 – County staff reported masonry cracking throughout the building, and requested THP investigate.

02/25/16 – THP visited the site, confirmed the conditions, and is developing a SOSS.

03/24/16 – THP provided an SOSS for review.

04/04/16 – County approved the SOSS.

05/26/16 – THP completed field investigation of the facility. THP developing analysis and final recommendations.

09/09/16 – THP published draft report. County provided draft comments the same day.

09/28/16 – THP anticipates publishing final document 9/30/16.

10/11/16 – Final report published.

2020 Masonry Investigation Read More »

2020 – Cooling System Questions and Upgrades

05/19/16 – ThermalTech met with Bill Scholl and review the CT installation.

05/25/16 – TEI recommended to Tony to rebuild the towers and add an equalizer line for more efficient operation.

06/23/16 – Spoke with Bill Scholl and confirmed he is correct that the off chiller needs to be isolated from the chilled water system or else there are large inefficiencies in the chilled water system and a blending of cooling water return temperatures.

06/27/16 – Sent drawings to Tony and Bill for possible ECM project.

02/01/17 – Project on hold as far as I know.

2020 – Cooling System Questions and Upgrades Read More »

2020 Matrix Security System Upgrade

Partner Lead: TEI

09/28/13 – Mike Barth met with Bill Scholl about scope of upgrading the security system which may include the locks, cameras and maybe master clock systems. Currently developing the SOSS for Tony.

02/24/16 – Tony inquired about resurrecting this project today. Debra Kuempel provided a new estimate for replacing some parts of the head end.

03/29/16 – ThermalTech reviewed the estimate from DK and authored a letter to Tony Matre to describe what DK had included in their bid versus what was included in the Archibus complete system replacement. Tony to provide ThermalTech with direction to move forward. Project on hold pending direction from Tony.

04/27/16 – Project pending direction from HamCo. BW said this is on hold as it is part of a larger budget appropriations for this building. It may be incorporated into a larger project at the 2020.

05/25/16 – SOSS Submitted to Bert Watts – Pending approval and PO.

06/27/16 – SOSS approved and PO Issued. ThermalTech conducted Kick-off meeting on site with Facilities and building staff. ThermalTech provided field work to document the existing conditions. ThermalTech meeting with Vicon industries on 06/29/16 to discuss options and capabilities.

07/27/16 – ThermalTech met with Vicon to address issues with new system and to get answers for 2020 questions. ThermalTech scheduled a design progress meeting with the 2020 staff, meeting scheduled for Friday August 5th when 2020 IT department staff returns from vacation.

08/23/16 – TEI attended Design meeting at 2020. Final Design review meeting scheduled for 08/31/16, and scheduled to be issued for bidding on or before 9/9/16.

09/28/16 – Drawing package issued for Bids on 09/09/16. Pre-bid meeting occurred on 09/20/16. Addendum #1 has been issued with Pre-bid meeting notes and sign in sheet. Bid opening scheduled for 10/06/16 at 11:00 AM at the purchasing department.

10/25/16 – Bids received, opened, and qualified. TE drafts contract and is at the prosecutors office for review and comments.

01/25/17 – Debra Kuempel was awarded the contract. Shop Drawings were submitted and have all been returned. DK began construction on 01/17/17 and next const meeting is 1/31/17.

02/22/17 – Work is proceeding on the project. The new NVRs, Kollectors (encoders), and Matrix Computers are installed in new rack and are running (burn in period). Comtec scheduled to be on site for change over to new system beginning week of March 20, 2017.

03/22/17 – Work continues to progress on the project. Com-tec on site programming the PLCs and installing 4 work station in the second floor control room. Spare DVR (DVR4) installed and running as Archive DVR.

04/26/17 – Project nearing completion. All work on original bid complete, and DK indicated that the the changes (allowance usages) will be completed approx end of first week or two of May. DK was told to deliver close out docs and as-builts to ThermalTech. POE pricing to be determined, possibly paid through the allowance.

05/22/17 – ThermalTech completed Punchlist on 05/23/17. There are minor issues to complete project, and (4) additional cameras being priced by DK in the intake area of the building that has no camera coverage at this time.

06/27/17 – DK Completed punchlist and email to John Nester and ThermalTech. A few final glitches in the system to get worked out and project closeout pending closeout documents from DK.

07/25/17 – DK and Vicon conducted training on the system on 07/18. TEI received final pricing for allowances, and authored Change Order #1 (deduct change order) or unused portion of allowance. TEI delivers Training videos to Hamilton County Facilities.

08/28/17 – Project complete, pending final closeout documentation from DK.

2020 Matrix Security System Upgrade Read More »

800 LEED EB+OM Certification

Project Lead: GBBN

05/25/10 – Bert Watts requested SOSS to be prepared. This is second SOSS for overall project. This second SOSS is to await results of Phase 1 Planning Study SOSS to determine complete scope of work for project.

05/26/10 – GBBN requested estimate for consulting services from ThermalTech.

06/24/10 – SOSS submitted to Bert Watts at monthly Partner Meeting.

04/28/11 – SOSS reconfiguration discussed at monthly partnering meeting.

01/25/12 – County and partners completed a planning meeting and established project goals and schedule. Project recording period to end October 31, 2012. Three month recording period August 1 to October 31. County review period for credits June 1 to July 3Design team project meeting schedule for May 10th with County review period of credits starting June 1. THP reviewing credits for use of park across of street from the building. Design team project meeting schedule for May 10th with County review period of credits starting June 1. THP submitted policy’s on June 4th for County review. County in the process of reviewing credits.

05/10/12 – Design Team Status Meeting at GBBN.

05/11/12 – Bert Watts responds to Design Team questions developed in Design Team Meeting.

05/26/11 – GBBN/TEI/THP to discuss options for reconfiguring the scope and services for each firm to perform the Certification process.

06/09/11 – Final SOSS due from each firm. GBBN delivers SOSS F017A Revised to Bert Watts.

07/11/11 – SOSS received approved from Bert Watts.

07/13/11 – Confirmed all three Partners have received approved SOSS.

08/32/11 – Kick-off Meeting to be held with THP and ThermalTech at GBBN offices.

08/03/11 – All partners held a kick-off meeting to discuss logistics and timetables.

09/22/11 – The design team, minus THP, and Bert Watts meet to discuss project schedule generated by TEI and project registration. A meeting with THP is to be held in future.

09/28/11 – Tony Yunker sends invitation to project team members to register on the USGBC Online site.

05/24/12 – Tony Yunker completes preliminary new County Procedures for Owner Review. THP has also completed the sample Procedure Documents.

06/06/12 – TEI discusses refrigerant conversion strategy with Ralph Linne.

06/13/12 – Conference call with all three partners to discuss Procedure strategy for delivery to Facilities Department. THP forwards Murray Monroe summaries and procedures. John Millar yet to complete procedures. Tony Yunker updates spread sheet with performance period.

06/22/12 – County notifies Murray Monroe of their lack of desire to converting parking spaces at east or rear of building to green space for SS Credit 5.

06/25/12 – ThermalTech completed its Preliminary Reviews for County approval. ThermalTech indicates IEQc1.3 is to be removed from possible point list.

09/26/12 – GBBN/THP/TEI hold conference call to discuss delays in receiving procedure review comments back from owner.

09/27/12 – Bert Watts leaves voice mail concerning results of review meeting with Ralph Linne. Bert is to review existing procedure templates for overlaps. Solid Waste Stream Audit may need to be revisited.

01/27/13 – GBBN/THP/TEI agree to establish the final three month credit performance period for May 30, 2013 to August 31,2013. This information passed along to Bert Watts that agreed to these dates.

04/22/13 – County requested THP coordinate Bayer Becker surveyor .

04/05/13 – GBBN, TEI and THP hold design team meeting to discuss scheduling and replacement of Tony Yunker as Administrator.

04/24/13 – GBBN held an internal meeting to get staff onboard with the project in preparation for the County to deliver the required procedure updates. The County is to deliver the updated procedures by the first week of May.

04/26/13 – In4 helped to calculate the building occupant load based on the CAFM data in Archibus.

05/07/13 – GBBN contacts Darnell Edwards, Building Manager, to inform him of the impending presence of Bayer Becker surveyors and their need to open doors for elevation shots of the landings inside the building.

05/30/13 – Bayer Becker completed survey and anticipated providing drawings by the end of the week. ThermalTech finished a couple more water surveys. The building probably qualifies for the higher water conservation level point.

06/06/13 – THP forwards an electronic copy of the final survey by BBE.

06/06/13 – THP issued Bayer Becker survey.

06/13/13 – GBBN inquires about County delays in transmitting revised procedures to Design Team. More revisions are necessary and the Director and Assistant Director must review the proposed changes before transmitting them.

08/06/13 – Design Team met to discuss Procedures returned from Owner and input requirements.

08/07/13 – Emails sent to Darnell Edwards to request meeting to discuss Procedure implementation and forms necessary.

08/26/13 – Bert Watts and Tony Matre confirm Darnell has been on vacation henceforth no response to GBBN emails.

08/28/13 – TTC started the Building Report. TTC and Amy Crousey will be inputting data and forms this week and next for the Sept 5 meeting at GBBN.

09/05/13 – GBBN cancels design team meeting due to inability to contact owner to arrange owner meeting.

09/06/13 – GBBN receives request from Facilities concerning possible meeting date with Building Manager. Meeting is set for 09/12/13.

09/12/13 – GBBN meets with Facilities and Building Manager to discuss implementation issues and necessity for compliance documentation forms.

09/26/13 – TEI input several credits this month in the EA and WE divisions. The County provided some additional PM information and TTC uploaded to update the credit.

10/15/13 – TEI uploaded schedule for PM.

11/15/13 – TEI Updated Credits for water.

12/15/13 – TEI updated credits for EA, IAQ.

01/30/14 – Bert asked for a definitive answer about final submission to USGBC by 1/31 plus an explanation about not meeting the 12/31 deadline.

02/24/14 – ThermalTech entered most WE credits and EA credits. County provided and approved paperwork in these credits for upload. A&M on site creating trends for use with IAQ credits and commissioning credits.

02/26/14 – GBBN sent revised 11.0 Sustainability Purchasing- Facility Alterations Tracking Form back to Bert Watts. Master completion matrix updated, we can uses at partner meeting to track status. Performance Period should be finalized from about June 2012 through either February or March 2014.

03/14/14 – GBBN transfers floor plans, site boundary plan and project photographs to other partners for uploading into the project website.

03/27/14 – Shift Preliminary Submission date to April 7, 2014. Setup meeting with Ralph and Bert.

04/16/14 – Owner Signatory Meeting with Ralph Linne and Bert Watts. Credits and Pre-Requisites requiring owner approvals/signatures were reviewed and modified.

04/21/14 – Bert Watts forwards Consumable and Light Bulb materials to GBBN.

04/24/14 – THP found some more owner checklist items and they will update these after milestone goes without response. Reported to Tony Matre via telephone call.

07/24/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

08/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

08/27/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

02/24/14 – GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/WebCentral is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14 – GBBN sends another email and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

08/28/14 – TEI updated two credit points so far. We have edited about four others. The OA prerequisite is the major one we are working on this week, GBBN has finished updating all the rebuttal questions, THP has some questions about the green cleaning policy for maintenance log.

09/05/14 – TEI updated all WE credits this week. TEI Update all EA credits this week. TEI is working on IEQ credits and outdoor air requirements..

09/12/14 – All partners are updated with LEED input except TEI is working on IEQ input which may require an air balance report on the exhaust fan system. TTC requested time with Darnell to do this work.

09/19/14 – TEI updated all credits but IEQp1 which doesn’t meet minimum standards yet. Final submission date reset to 10/1/14. More work needed in building and programming changes required on AHU’s to meet this prereq.

09/24/14 – Refer to GBBN updated.

09/25/14 – ThermalTech completed the remaining points for USGBC response including all fieldwork for IEQp1 credits yesterday. The tables have been updated. We are now updating the credit and uploading our final forms for final submission on 10/1/2014.

10/22/24 – Two clarifications came back from USGBC in regards to the IEQp1 and EAp2 prerequisites. These are both on the ThermalTech realm to answer. TTC posted two response questions to the website asking for clarification. ThermalTech is currently uploading the 800 Energy Star forms for 2014 for the 88 score. Answers are due back to USGBC by 11/5/14 on these clarifications. ThermalTech should have both answers uploaded prior to that. It is possible to submit EAp2 as a “No Recent Labels” but that seems counterintuitive to what we are trying to accomplish at 800. Our score is up 2 points, we are hopeful the will wait until the certification goes through to give us our final certification.

09/24/14 – Refer to GBBN updated.

10/23/14 – LEED team receives Mid-Review Clarification letter via email. TEI indicates both requests related to their credits.

10/24/14 – TEI sends response back to USGBC.

11/05/14 – Mid Level Review responses due to USGBC for EAp2 and IEQp1. ThermalTech request extension after 3 clarifications for each prereq are still in the process of revision with USGBC.

11/19/14 – TEI sends Final Mid-Level responses back to USGBC concerning prereq credits EAp2 and IEQp1. After about one weeks worth of work at ThermalTech the revised prereq clarifications were sent back to USGBC.

11/28/14 – The LEED Team recommended the County accept the Certified level offered by USGBC given the cost, work, time and efforts involved in any Formal Inquiries about additional points that my be available. The chances are low that this building could reach Silver Level without significant capital cost involved in additional upgrades. HamCo accepts Certified Level, GBBN reports this decision to USGBC and the project is formally Certified Level at 43 points. Final Scorecard: Attempted | Awarded | Final Report. Congratulations to the entire team!!!

800 LEED EB+OM Certification Read More »

800 Asbestos Study

Project Lead: GBBN

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sent a list of buildings to be included in Asbestos Abatement Reporting.

04/04/12 – Pinnacle Engineering requested drawing files for the purpose of documenting findings.

04/05/12 – GBBN sent drawing files to Pinnacle Engineering in PDF form.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

04/06/12 – Meeting with Building Manager and Pinnacle to kick-off Field Investigation.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

05/31/12 – Draft Report completed.

06/01/12 – Received note from Mark Hesselschwerdt describing final step for process of entering data into Archibus

06/11/12 – GBBN set up conference call meeting with Facilities CAFM Department and CAFM Partner to be held July 3, 2012.

09/06/12 – Bulk drawings received from Pinnacle.

09/24/12 – GBBN completes bulk drawings and forwards to Pinnacle for use in final reports. GBBN requests final inventory drawing spreadsheets to allow completion of inventory drawings.

10/27/12 – Inquiries to Pinnacle Engineering about identification of ACM designation clarification for Archibus entries. All other Inventory Drawing and spreadsheet work completed.

01/26/13 – BRG confirms entry of ACM data into Archibus is completed.

01/28/13 – GBBN conducts spot review and confirms data entry is accurate.

02/26/13 – GBBN inquires with Pinnacle for status of remaining documents to be sent to GBBN.

02/27/13 – Pinnacle reports back that progress has been made and further timetable for receipt will be coming 2/28/13

04/25/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

05/29/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

06/26/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule. ThermalTech modified and sent new scope to GBBN.

08/21/13 – GBBN re-submitted SOSS to Bert Watts.

08/29/13 – Bert reports he has to confirm with the Judge about scope and cost for the latest work. SOSS is signed and we are ready to go but Bert says we have to wait until the Judge gives us her approval to release us to begin.

06/26/14 – Project on hold pending litigation.

08/29/14- Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications to finalize the remaining invoices to close out these projects.

800 Asbestos Study Read More »

800 – 12th Floor Renovation Project

10/13/05 – Ben sent out some status notes trying to get Arrow to finalize. We are awaiting further direction for our part of the completed work.

09/29/05 – Arrow said they would address the additional items noted at 800 Broadway.

09/29/05 – Additional items were noticed from at 800 Broadway, “This is an F.Y.I. for you regarding the Judge’s bathroom. We had to call the maintenance folks because we ‘heard’ a funny sound coming inside the little access panel on the outside wall of the bathroom located in our kitchen area. When I opened the panel, water was spurting out from two sides of a pipe. The guys came up and turned off the water, I think. Not sure what comes next. However…they mentioned to the Judge that her bathroom sink faucets are on ‘backwards’. You might want to add these situations to your ‘punch list’?? Thanks.

09/27/05 – Arrow responded to punchlist items. PDF

09/23/05 – GBBN issued a revised punchlist with photographs and a directive to Arrow. PDF

09/22/05 – Meeting / Punchlist. GBBN is typing up additional punchlist items, including past unfinished ones, for Arrow to respond to by 09/26/05. At that time it will be decided whether to let Arrow finish, or proceed with hiring another contractor to finish.

09/13/05 – Meeting / Punchlist was cancelled for today. Diana went over to Job Site and is still displeased with Arrow’s Tile work.

09/09/05 – GBBN has scheduled a meeting at the site for 09/13/05 at 7:45 am

09/06/05 – Debbie Poland informed ThermalTech of Judge Grady’s choice of fixtures, and ThermalTech relayed the information to Arrow.

09/02/05 – ThermalTech contacted Arrow and mentioned Pat Murphy at Select Spec Sales, as a possible vendor to obtain a solid toilet seat.

09/02/05 – GBBN informed ThermalTech that the light fixture for over the Mirror has been discontinued, and to specify another one.

09/02/05 – ThermalTech had GBBN forward the following to Arrow: The cleanout and floor drain should be level with the tile and grouted in closely. It should be almost a perfect fit when done right and have a brass cover plate that should look relatively nice. Arrow should adjust the floor flange on the cleanout and floor drain so they are level, if they still can. They may have to bust out the floor and adjust it and then pour a patch around it.

09/02/05 – Judge Grady has made the following requests: Raise the top of the plumbing clean-out to align with the top of the tile. Install a solid toilet seat cover in leiu of the “open” toilet seat currently installed. Install the second coat hook. Install the over – cabinet light fixture. Replace the cracked tile at the “clean-out”. Patch up the plaster adjacent to the sink and cabinet (at door). Provide a finish on the kick-plate of the millwork. Provide shelf in wall cabinet per sheet A201.

08/29/05 – Architectural and Mechanical Punchlist was completed.

08/08/05 – Project meeting postponed for one week.

08/01/05 – Exhaust Fan is not installed yet but is on order. Plumbing is roughed into the wall through the floor space. Electric is roughed into the walls and ready for inspection, insulation and the gyp board. Progress is slow from the MEP side but is going forward.

06/16/05 – GBBN and Arrow are working to resolve a toilet outlet issue. There is a beam below the slab that is interfering with the toilet outlet. GBBN called today to say that they can use a 4-inch filler space to move a wall and thus give the plumber enough room to route the new sanitary line. TE approved this shift in the plumbing.

06/10/05 – TE received insulation, plumbing fixtures and electrical. TE will send out comments on Monday.

06/07/05 – TE sent out submittals on EF, DWV Piping and Vent, Ball Valves and Hangers.

05/10/05 – GBBN setup preconstruction meeting for project on May 24th.

04/19/05 – It was agreed that since Arrow won every part of the bid that GBBN would write an inclusive contract the entailed all items on this project. TE thinks this is great idea and removes all coordination issues between contractors since we will have only one contractor on this job doing all phases of work.

04/15/05 – Bid Evaluation was released. PDF.

04/06/05 – Add01 was released by GBBN and TE. Add01

03/22/05 – Prebid meeting complete. Reupert was only mechanical at Prebid. Sam filled out permit application for HVAC and sent to Brady. GBBN already has all the books and drawings with our stamp. As usual we cannot stamp plumbing drawings because we don’t hold a Master Plumbers license.

03/14/05 – Client review meeting. TTC coordinate with Brady on plumbing items to state the 3-5/8″ wall is fine for our tank type water closet and countertop lavatory.

03/08/05 – TE asked Facilities for direction on copper vs. no-hub cast iron for the sanitary lines on this project in the even they ever entertain waterless urinal systems.

02/25/05 – TE has begun design the MEP on this project. Layout and specs are being compiled.

02/22/05 – TE provided a price of $100 for the gooseneck faucet and $150 for the additional light above the vanity mirror pursuant to the email from the County today.

02/11/05 – DEW advised TE to write the SOSS for this project and submit it to the County for Approval. TE finished and put in the mail on Monday.

01/31/05 – GBBN assembled a complete cost estimate for this project and turned over to the County. We are awaiting further direction from the County. TE noted that GBBN had $3500 too much because TE had front end cost in the estimate and it isn’t required.

01/11/05 – ThermalTech has conducted all fieldwork and assembled a probably cost estimate based on our understanding of the scope of work. We are awaiting a meeting time or notice to proceed. Estimate includes new fixtures, exhaust fan, ductwork, plumbing and electrical work for anticipated scope.

800 – 12th Floor Renovation Project Read More »

800 – Florida Room Renovation

12/26/06 – TTC has decided to close this project and archive it. This project was never contracted or awarded and the work was never done. We believe it was included in another project.

10/14/05 – TE received word that this project is still a “go”, however we have not received any news about the contract status.

10/03/05 – Contracts are turned into the prosecutor. We are awaiting word from the County about proceeding with this project or canceling this project in lieu of a revised EMU project.

09/22/05 – TTC dropped off the revised contacts to Wayne Trent today and gave one copy to Michael Evans at GBBN. All contracts were hand delivered. The County facility group got to meet Kandy today because we stopped in

08/29/05 – Addendum 01 PDF was issued with the new bid form. Job is set to open on September 1st.

800 – Florida Room Renovation Read More »

800 Broadway Electrical Device Identification

11/16/06 – NR visited the site to verify the panel names for the Arc Flash Study. All panels are verified and the single line is complete. The Arc Flash Label information is currently being inputted into EDSA and the labels are being generated. This portion of the project should be completed within the next 3-4 weeks.

09/27/06 – The final drawings were sent out to Queen City to be delivered to Bert Watts so that he could distribute them to the appropriate people. Areas on the 4th and 5th floor will be updated when the Adult Probation Renovation project is completed and ThermalTech receives the as-built drawings. The panel schedule binders were delivered at an earlier date. All other work on this project is complete.

06/27/06 – The close-out meeting was held on location. There were no open issues. Ginter Electric provided (2) CD’s with the panel schedules on them. I will have the drawings together within the next couple of weeks. TE will have (3) full sized sets delivered to Hamilton County Facilities (Attn: Bert Watts, Jim Eby, Darnell Edwards). TE will make (3) binders of the panel schedules and deliver them to Hamilton County Facilities (Attn: Bert Watts, Jim Eby, Darnell Edwards) .

06/21/06 – Spoke with Darnell Edwards about the EMU area. He informed me that the devices were marked and that he is satisfied with the work performed. Close-out meeting has been schedule for June 27 at 9:00am.

11/15/05 – Contracts have been submitted.

800 Broadway Electrical Device Identification Read More »

800 – JV ISSUE DESK REMODEL

03/20/07 – Check CRA website for closeout documents. Project is ready for archiving.

02/19/07 – Coordinate with CRA for final details. Project is nearly complete.

01/22/07 – Permit drawings have been submitted to the IBI

01/02/07 – TTC and Spencer discussed the project today and TA and TTC will kickoff the project internally on 01/03/07 and push it towards compeltion.

11/10/06 – They installed the desk. Flooring will be installed in the next several weeks.

09/08/06 – Preconstruction meeting held. Things went as planned.

04/05/06 – Review meeting is scheduled for this Friday. Cost estimates have been given to the client. No HVAC or Plumbing work on this job.

03/08/06- Mike Stiles met with the architect on this project for kickoff.

800 – JV ISSUE DESK REMODEL Read More »

800-York Control Panel Replacement

04/26/07 – This project is complete and ready to be archived per the County Partnering Meeting.

01/05/07 – TTC has given the County everything they need to get the PO for this work and it will be done in house on this project. York has provided all the paperwork for sole source and quotes.

10/25/06 – Prebid Mtg today. DK showed up for prebid. TTC built the quotewire package and sent it to purchasing for bidding out just the purchase. TE has to send out an Addendum for bidding changes.

06/27/06 – Tony stated for us to get the electrical requirements together for the trades so they can do the work. TTC said he would get with TA and get this done.

05/05/06 – Mike D and TTC discussed recent information provided by York. Additional scope items and more electrical work that would have to subbed out on the job. TTC talked to service tech’s about doing this work and is trying to formulate a complete scope for the project.

04/26/06 – TTC reviewed the project scope with Tony, Mike Denton, Darnell Edwards, Bill Scholl and Tony Martini. Tony need further proof that this project should not be outsourced because o requirements on County Efficiency Committee.

800-York Control Panel Replacement Read More »

800 – Security Camera Upgrade

Journal:

11/29/07 – Bert reported today that final pay application has been submitted for. This project could officially be closed out at this point. Bert has confirmed that the County has received the O&M’s and As-Builts sent by TTC at TEI.

11/16/07 – Lori contact TEI today about past due notices. TTC collected information and sent to Nor-Com saying that TEI would do as-builts and write deduct change order of $2000 for the job and Nor-Com has to provide a full warranty letter to HamCo. TEI finished the as-built and made a CD of the dwg. TEI finished the change order for a $2000 deduct. TEI sent both to Nor-Com to return to Bert Watts with the final warranty letter. TEI finished the as-builts and change and mailed to Nor-Com and the County. We are finished with this project.

10/18/07 – TTC opened and sign payapps 3 & 4 and sent final closeout paperwork to Bert for processing. This packet arrived sometime after 09/07 with the wrong zip code. All the certified payroll, closeout documents and payapps appear to be correct. TTC emailed everyone and said the job is ready to close.

06/07/07 – Lori from Nor-Com checked on status of payapps. I emailed back #1 show paid, #2 i need 3 originals and #3 i do not have a copy of.

05/31/07 – Closeout documents have not been sent. They were waiting to use the allowance money. MD directed Nor-com to close the job in an email and TTC forwarded that email to Mike Rolf.

05/30/07 – TEI does not believe they have received close out documents yet for this project. TTC contacted Mike Rolf.

03/30/07 – Punchlist is complete. There are no items from TEI or the owner at this point.

03/23/07 – TTC was on site today and took down punchlist items for Nor-Com. Currently there are no punchlist items for Nor-Com to correct.

03/15/07 – Nor-Com reported that cable work has begun in the space and that unit operation training is complete. 18 people attended including Phil Lambing from TE. Nor-Com will provide a more concrete completion date early next week.

03/14/07 – Nor-com was scheduled to begin work today and Vicom held their master training session for County employees this afternoon.

02/19/07 – Nor-Com is sending a new CD for submittal review on this project. TTC could not find the original.

02/08/07 – TE distributed Const Mtg notes for the pre construction and Const Mtg 01. TTC did not make the meeting in person but attended via a conference call.

02/01/07 – TTC sent MWH dwgs of the space for his use.

12/28/06 – TTC discussed kickoff meeting for this project and sent out another date because all previous dates have conflicts. We are now trying to have a kickoff meeting on Jan 4 at 9am at the 800 BWAY building. Norcomm has already sent in RFI’s on this project and proposed a solution to a DVR problem by downsized the 900 GB harddisk to allow for multiplexing of the signal to the DVR. This will have to be discussed at the kickoff meeting.

12/26/06 – TTC created project journal and filled in back data from previous meetings.

800 – Security Camera Upgrade Read More »

800 – ADULT PROBATION RENOVATION PROJECT

Journal:

11/16/07 – TEI received a hard copy of the approved QCE change order in the mail today. TTC filed it for archiving with the project folder. Mike Cavanaugh called to inquire about payment of this invoice and TTC referred him to Bert Watts because all invoices should be paid on this job by this point. TTC is ready to archive this project.

11/06/07 – CRA forwarded Change Order #2 to Bert Watts.

10/30/07 – CRA issued Change Order #2 to delete the allowance balance and forwarded to Kramer & Feldman.

10/26/07 – CRA received final closeout documents.

10/18/07 – MD sent back final change order for signatures on 3 originals. TEI printed and sent 3 new originals to QCE for signing.

10/04/07 – TTC and LKV revised CO4 and sent it to QCE for signing. The new amounts were gleaned from the previous emails and signed change orders.

10/01/07 – TTC received, reviewed and signed payapps #5 and #6 from QCE for this project. I read through all the email correspondences and believe these final two payapps to be correct. Assuming that the change orders that the owner had in hand were signed and correct, the amounts of these pay applications should correspond to requested amounts by the Owner. TEI will mail them to Bert Watts for processing today.

09/28/07 – Awaiting final closeout documents. CRA needs As-built drawings.

09/04/07 – Items mentioned in previous entry were sent to QCE this morning.

08/31/07 – Pay application #05 and #06 need to be updated to show CO#04 instead of CO #05 in the work description (there were only 4 CO’s); the dollar amounts shown are accurate. TEI will correct the dollar amounts shown on CO#04 and send 3 originals to QCE for their signature. TEI will also send 3 original copies of allowance clarification #01 for the entire allowance ($2500) to QCE for their signature. When QCE has received and signed all 6 documents they will send them along with the updated pay application #05 and #06 to TEI. All of the above mention documents will be reviewed, sorted, and sent to HCFD. The documents will be sent to QCE on Tuesday, September 4.

08/23/07 – TEI printed 3 more originals for Change Order #5, signed them, and sent them to QCE with instruction to sign them and forward them to HCFD. TEI also sent the O&M manuals along with the final pay application and closeout documents to HCFD Attn: Bert Watts.

08/17/07 – TEI is awaiting the O&M manuals from QCE in order to close this project out. NR contacted Greg at QCE on August 16, 2007 in order to locate these binders. Greg said he sent them to TEI already but we have no record of receiving them. NR will contact QCE today and have them send another copy.

07/31/07 – TTC approved Change Order and PayApp # 5 for this project but asked for backup data for the change order and requested

07/30/07 – QCE is not responsible for completing the ceiling patch work. The remaining ceiling patch work is going to be completed by the Hamilton County trades department. QCE has completed their portion of work. TEI is awaiting the resubmitted final pay application and close out documents in order to close this project out. TTC emailed the County and QCE for closeout documents on this project and approved their last payapp and told CRA the same info.

07/09/07 – TE still awaiting modified change order from QCE.

06/29/07 – QCE has been informed that they will not be paid for the ceiling and wall patching. TE is awaiting a revised change order and final paperwork from QCE.

06/15/07 – Still awaiting response from QCE.

06/15/07 – TE placed call to Queen City Electric about inaccurate Change Order #04. Awaiting response from QCE.

06/08/07 – Change Order #04 was sent to Hamilton County Facilities Department but had inaccurate information. The change order did not reflect the three previous dollar amounts. The paperwork was given to TA of TE in order to straighten the numbers out.

06/01/07 – TE is still awaiting response from contractors about the punch list. New contract dollar amounts between the contractor and Hamilton County Facilities Department are being clarified. This should be resolved in the next couple of weeks.

05/25/07 – TE issued punch list. Awaiting response from contractors stating that all items have been completed.

05/21/07 – TE completed punch list. Issues with lamps have been corrected. Punch list will be issued early this week.

04/27/07 – Fixtures are 99% (one recessed can yet to be installed). TE has visited site on 2 occasions this week. Project is expected to be complete and TE finish their punch list by the end of next week, May 4 of 2007.

04/20/07 – Project is moving along as expected.

04/13/07 – Light fixtures are currently being installed. Project should be complete by the end of the week of April 20 of 2007.

04/09/07 – Phil stopped down at the site on Thursday and resolved some clarification issues on the type of lights the supplier purchased for this job. TE instructed them to send them back and get the correct cuts for remodel 5″ cans to fit into the drywall soffit.

04/05/07 – QCE has begun installing the fixtures into the space and then we can close this job out.

03/30/07 – Fixtures are scheduled to be installed next Wednesday, April 4 of 2007.

03/23/07 – Project progressing as expected.

03/20/07 – Lights are scheduled to arrive next week and be installed next week by Queen City.

02/19/07 – TEI is waiting for Mindy to get back for funding approval but lighting changes are happening now. Check CRA website for details.

01/10/07 – Const Mtg was held but TEI wasn’t in attendance. Project updates are available on the CRA website.

12/26/06 – TTC moved project over to Mark Donnelly and will get an update from Phil and Spencer this week.

02/06/06 – Spencer submitted a revised floor plan with a new sink location in the back corner of the building. TTC and SBO will pipe up the sink and drain while PEL finishes the electric work. We are shooting to have this job on the street by the end of February 20th for this job.

08/04/05 – Had design meeting today. Discussed schedule and typical workstation layouts, phasing of the project and construction times. C+R will issue official meeting notes for the job. They are talking about moving in around November so design documents have to be collected pretty quickly.

06/24/05 – TTC and Spencer visited the site today to look at the lighting and ceiling heights. TTC brought pictures back for Phil.

06/16/05 – Cost estimates were given to client and we are awaiting direction from the County and C+R before proceeding. TE hasn’t heard anything since 03/21 on moving forward with this project. NO HVAC or Plumbing were included in the cost estimate to the client.

03/01/05 – SOSS Written. TA to approve and send to DES.

800 – ADULT PROBATION RENOVATION PROJECT Read More »

800 – VACUUM PUMP UPGRADE

07/09/08 – TTC stopped by the site today and review the project progress with Process. There were several issues with the installation of the equipment that we resolved. Size, location, pipe runs, housekeeping pad, inlets.

12/04/07 – We received a schedule of values today that TTC marked up and sent back to Process. Insulation submittals were received today in the mail. LKV is logging them in for this project and will give them to TTC to review.

11/29/07 – Joe Doxsey and Terry Cannon discussed project schedule and submittals today by phone. Process is going to send their background checks to Willie at the County and are currently working on the submittals. They have not worked on submittals or project schedule yet according to Joe but will get them done now and into the system as discussed with TEI today.

11/16/07 – We held the pre construction meeting with Process and discussed changed scope and timetable for the project. Bert provided an email with the PO attached yesterday. TTC asked for the submittals on the vacuum pumps for the job and saw Rick Huff today and asked him if they were ready. He had no idea about them being asked for so Process must not have told him yet. Laurie finished typing the meeting notes and TTC has to review them and send them out. Process is going to provide a project schedule and SOV for our approval and ThermalTech has printed out and is sending 9 sets of stamped permit drawings (6 for city, 3 for IBI) for Process use on this job. TEI also emailed Process a copy of the spec and the dwgs for their personal use and printing.

08/02/07 – TTC sent out Addendum 02 for the project today PDF. Addendum 01 extended the bid opening to August 7 by Purchasing.

07/31/07 – Bernie and Roger replied with Addendum 01 items for this project. A&M stated that their cost would be about $4500 for this work even though we are adding about 8 points and picking up alarms for the system. Bernie added that the 3″ line sizes were all he needed from the dwgs.

07/30/07 – Purchasing issued Addendum 01 for this project extending the Bid Opening and Due Date to August 7, 2007. TTC will issue Addendum 2 with pipe sizes, control notes and spec revisions.

07/16/07 – TTC sent the same data to Queen City to hold for bidders this morning. TTC has to contact Gina about the advertised price for this project since he changed it after talking to Tony Matre.

07/13/07 – TTC sent the project out for bidding with a bid opening date of July 31, 2007. Rod, Jim and Michael helped complete the project and send it to Gina by 4pm.

06/26/07 – TTC and Rod are going to finish the mechanical design on this project. Michael Huntwork is going to finish the electrical work on the project and TTC has to get project number from Purchasing for this project.

05/30/07 – TTC selected pumps and is finalizing the dwgs and specs for bidding. TTC asked to add the dampers to the back of the combustion air intake while A&M was doing the control work on this job.

05/14/07 – TTC and NR worked on CAD layout and background drawings. TTC will try to have something to review by this Friday. TTC talked to Tony today about using 2 full size vacuum pumps instead of 3 separate pumps. If this works, Tony did not seem to have a problem with the new design.

05/03/07 – TTC visited the site for field work and equipment locations. Meeting notes were distributed to Owner.

04/13/07 – We had second Design Mtg. 3 vendors were selected. We filled out the BOD and DID for the project.

03/15/07 – Tony said the SOSS is approved but TE has not seen it yet.

800 – VACUUM PUMP UPGRADE Read More »

800 – BOILER REPLACEMENT PROJECT

01/22/09 – After making it most of the winter with little problem, the boilers started performing badly last Friday. ThermalTech was on site with the Duke employees to monitor the situation. TTC asked Stoermer and Duke to provide solutions, TTC believes our two options are a new regulator in the boiler room for 14″ or modified regulators at the boilers to handle the boiler pressure better.

03/09/08 – Duke installed a new regulator and it worked good until last Wednesday when there were three low pressure alarms and flame outs on Boilers 2 & 3. TTC sent an email to Duke and SA explaining the latest problems and asked to bring in another expert to look over the entire system.

02/29/08 – Duke installed the 461-S regulator this week and if this works, they will install a larger vent for the regulator to use. We will monitor the boilers over the next few weeks and see if this is the answer.

02/06/08 – Duke Energy replaced the regulator yesterday with the new CL-38-2 but did not use the pilot line. The regulator seems to work okay and settles down in about 2 seconds of a boiler start. TTC sent an email to everyone outlining the results and asked SA to program the boilers one more time with the new regulator in place. The residual static is now up at 47″ with a running static of 27.6″wc. TTC witnessed a dip in pressure down to 17″wc with the new regulator but it recovered quickly and evened out as the boilers started.

02/01/08 – We had a conference call with Duke Energy today. They are willing to try a new gas regulator and meter at the building. We are going to try a CL-38-2 regulator with the new meter next Tuesday at 9am when Duke comes out to install the new meter set. Darnell will coordinate the visit and TTC will stop by to check on progress around noon. They think this meter with the external sensing line and 1.25″ orifice will do the trick.

01/24/08 – Boiler #3 went out on a flame failure last night at 10:30pm. John Gilbert came in to reset the boiler and it has been working fine since then. TTC had emails with Duke & Stoermer to try to get these final issues resolved.

01/23/08 – On 01/18 SA and Duke met on site to work and reset the boilers. What we discovered was that Duke was not comfortable with having the pressure under 1psig because we were testing the boilers at 24 psig and 20 psig. At these pressure the boilers worked pretty well but there are still concerns with Duke regulator. Because of this TTC talked AKM into paying PHB to come on on Sa 01/19 to install a 1″ weld-o-let and valve so that Duke could move the sensing line downstream about 20ft. On 01/21 TTC met Duke back on site and they piped up the regulator sensing line. The regulator is still surging. The boilers are however running great. TTC check the pressure at the inlet to the boilers and it is bouncing around between 19 psig and 29 psig every second. The burnertip pressure however is stead between 7.8 & 8.0 inches. I believe the biggest change in the boilers is that TTC talked SA into changing the low pressure setpoint down to 13″wc and not 19″wc so the boilers are not going out on low gas pressure as much any more. The Sellers regulators seems to be able to handle the incoming gas variations very well and the boilers are firing very smoothly.

01/15/08 – Darnell Edwards called yesterday to say they were having more trouble with the boilers. I met Duke Energy on site today because they responded immediately to a request to test the gas pressure at 15″ wc. It turns out that the boilers can’t be run at the pressure because the low limit on the boilers are set to 19″wc for some reason. Duke set the regulator down to 24″wc incoming for now and the boilers seem to run fine during the day. I am waiting to see how they operate overnight and tomorrow morning. I have talked to Tom Schmidt and Joachim at Duke about this situation too. We are currently trying to schedule Duke and SA back out at the building at the same time to adjust the incoming gas pressure to 20″ wc which should put us right in the middle of the operating range for this boiler. I am also trying to get some chart recorders to log the gas pressure in the main and at the boiler burnertips for testing purposes. When we watched the pressure after the regulators today they were steady at 7.5″wc on BLR-1 and 7.9″wc on BLR-2. BLR-3 is having some startup issues and according to Tony Martini there is sooting on the fire tip inside the boiler. When the boiler cools down, he will clean it off and then it should be back in server as well. I am trying to coordinate a meeting for Friday morning at the 800 Broadway building between TEI, Duke and Stoermer. I am also trying to get chart recorders for history recordings of gas pressures.

01/07/08 – The County called last week with more boiler problems. TTC investigated and found that on November 9, 2007 that the boiler were setup for 37″ of gas pressure on Jan 3, 2008 during our first cold snap the boilers were not running properly and going out on alarm settings. The owner could not keep a boiler running. TTC visited the building on 01/03, 01/04, 01/05 & 01/07 to check on the boilers and the pressures in the main gas line. According to all the readings that TTC took while onsite there is no gas pressure issue with the natural gas piping or Duke regulator. During all test the natural gas system delivered 30″ of pressure to the boilers all the time. At startup or when both boilers were starting at the same time a dip down to 24″ could be seen for a fraction of a second but nothing that could be thought to effect the way in which the boilers are running. TTC, John Gilbert & Will check the boilers at Boiler #1 and at the main building entrance. There is no appreciable loss in the piping system in gas pressure. The new Duke meter seems to be controlling pressure well. Today the temperature was back up to 60 degrees and TTC tested the natural gas pressure with no boilers running and it was found to be at 30″ with both of the domestic water heaters running. Later after they both shutdown the pressure slowly rose to 37″ just like the Duke representative Mike Hoffer said it would. The regulator used back pressure from the high pressure main to ensure positive shutdown of the valve. This means the residual pressure in the gas main is 37″ when no equipment is running and 30″ when anything is on. This correlates exactly to what to Ron Eaton told us by phone last week. The next step is for Sellers to provide a new regulator on one boiler sized for 30″ of static pressure when the boilers are running. This regulator should be able to handle pressures up to 40″ of gas and down to 28″ nominal and even down to 20″ under heavy load conditions or even better if it can go down to 14″, that is what I will make them provide. In my opinion, this is absolutely a boiler regulator issue and not a Duke Energy gas issue. We can hopefully get a new regulator in this week and have ONE of the boiler retrofitted before the next cold snap but your also stand a great chance of the boilers working well right now since they have been adjusted down from 37″ of pressure to 30″ (I think that is just a misunderstanding on Stoermer’s part about what they have at your building).

11/09/07 – Tom Schmidt called today to say that the boilers could not be adjusted so that all 3 boilers run at once. TTC sent an email to the County and Tom stating that all 3 boilers can’t run at the same time. The design is to have one boiler running at a time, at 0 degrees a second boiler can come out to help out but it doesn’t have too. The third boiler does not come on until -20F which really means never because the 6″ gas main isn’t sized for (3) 125 HP boilers to operate simultaneously. TEI had Tom Schmidt come in to discuss the problems and talked to Ron Eaton after he got to the building today about inlet pressures. On Nov 9 the pressure was 37″ and the boiler were adjusted for that pressure. Today the pressure is 29″ and this changes the inlet pressure to the boiler after the Siemens gas train from 8.5″ to 7″ which causes the boiler to run way to lean. Gary and Todd are helping me figure out how to solve these problems for the County. TEI has a conference call with the boiler mfgr at 2pm to work on this some more.

05/19/07 – Duke Energy replaced the gas regulator to the building with the new model specially designed for our load with a tighter tolerance to the outlet pressure.

05/02/06 – Tony called today about flame failure on the boilers at the end of the last season. TTC recapped what has transpired since the 3-22-06 call. TTC has talked to both Stoermer and Cinergy about this problem and it appears to be rooted in the fluctuations of gas pressure not the absence of gas pressure. The building has at least 1 psig of gas pressure which is twice as much as the boilers require but when boilers are running with the water heaters and various units shutdown, there are flame failures in the system. Apparently, the fluctuation of gas pressure on the high side is causing gas delivery problems to the boilers. TEI may recommend having the water heaters moved ahead of the boilers or changing the control sequence so that 3 boilers are never online at any one time. TEI will contact Stoermer, Cinergy and Automation to make sure this problem is resolved going into next heating season. We might need a meeting between TE, Cinergy, Stoermer and A&M to resolve this issue.

03/22/06 – County called about Boilers 1 & 3 going out on flame failure last Thursday and Boiler 2 going out on Saturday.

10/28/05 – County called about erratic boiler controls for gas usage. SA worked on setting the boilers up again with Cinergy regulators.

06/14/05 – TE received and sent out all final paperwork to complete this project for County and PHB.

06/09/05 – TE and PHB discussed final paperwork requirements on this project. TE received a final invoice in January 2005. The final paperwork was received in January also. Now, TE has all the final paperwork in house but can’t find the final application # 5, so PHB is sending over a new original. TE will submit these final documents to County as soon as they are received, copies and signed.

05/03/05 – A&M straightened out the program and released some unpronounced overrides. The provided a little more training for the operators and building manager. The plant appears to be working properly.

05/02/05 – 800 reported some anomalous behavior from the boiler plant. TTC called A&M for dial in assistance and TTC will stop down at building on Tuesday morning to investigate.

04/27/05 – TTC and Tony Martini witnessed the laptop working remotely today. Dennis set it up for home use and left it for Tony to take home for use. TTC observed the entire system while the Free Cooling system was offline because of a condenser water pump rebuild. I found many things in the “override” position. This certainly happens upon occasion but overrides should be release to allow the automatic controls to handle the building most of the time. TTC pointed out that with the boilers overridden off at the DDC through their enable point that this does not disable the feedwater pumps so we actually had 0 boilers running but 3 feedwater pumps running just using up energy. TTC stated that a better way to control the boiler plant “off” would be to lower its enable setpoint below the current OA temperature. The same goes for the Chiller plant which can also be run at lower temperatures when the FREE cooling is disabled to keep temperatures in the building from overheating the space as they were beginning to do today.

04/26/05 – TTC could not get the laptop working from home. TTC delivered to Dennis Brown. A&M called to report the laptop is working and will be dropped off to 800 on Wed morning with training. TTC will stop by to supervise this training. Does the County want Tony Martini and Glenn Wilhoit to attend this laptop training and can they be there at 8:15 a.m.?

04/22/05 – TTC to work on laptop for DDC access. PHB is complete on job. Ron Eaton with Stoermer Anderson made some boiler adjustments today. Cinergy increased building pressure to 2 psig at the meter and in the building. SA said boilers are working fine and building staff is happy with performance at this time. SA also said that PHB had a regeneration line from the water softener to a floor drain that still has to be piped. Everything else appears to be complete.

04/18/05 – TE contacted A&M about 800 boiler items that need to be worked on such as Laptop control from remote location, outdoor air sensor is not calibrated and 2nd floor ventilation CFM issues. TE dispatched SBO to assist in troubleshooting the airflows on the second floor. Sam recommended a change in airflow deflection and balancing and further suggested relocating one of the airflow devices away from the center. Watch changes made and notify TE if you would like to proceed further. A&M will schedule onsite time with John Noyes to work on OA sensor and laptop programming.

03/24/05 – Tom Schmidt reported that all devices are up and running with the Boiler system. Ron reported that a setting was changed on the softener system and that is now running also. This should make all items complete for the 800 Broadway Project.

03/11/05 – PHB delivered the O&M’s to ThermalTech for this project. TE will review and turn into the County for record keeping.

03/07/05 – TTC contacted all contractors to resolve issues at the 800 Broadway Building. (1) Trap on boiler # 1, (2) Sample Cooler on Boilers, (3) Low Fire control on boiler, (4) Draft controls on boilers.

03/01/05 – Tom Schmidt reported that 2 of the 3 draft controls are upgraded and working. The third one has a bad magnahelic. It will take one week to get a replacement mag from the vendor. SA will return to install the final automatic draft control components at that time. PHB will have a pipe fitter to pipe in the replacement sample cooler within a week according to PHB.

02/25/05 – PHB will have a pipe fitter down to install the sample cooler and remove the outlet drain valve within a week. TTC is trying to find out the status of the draft controls upgrade.

02/15/05 – O’Shea patches the concrete yesterday. SA is supposed to be installing the draft controls today.

02/11/05 – Stoermer dropped off the sample cooler yesterday. TTC will contact Peck about installing it. TTC will have Automation setup training next week and upgrade Tony Martini’s Laptop. TTC contacted SA about a $300 service ticket for the water softener as we believe this is only

02/10/05 – Stoermer reported today that the boiler draft controls will be installed on 2/14 or 2/15 with Ron Eaton. Tom Schmidt will personally be delivering a new sample cooler today to the building and he also stated that this type of failure is normally associated with the cooling water to the cooler not being turned on quick enough and an over-pressurization occurs in the shell vessel. This may have been what happened here? Who knows. To be safe, I would advise opening the drain first, then the cooling valve and the test water valve last? I am sure Tony Martini already does it this way anyways, but just in case, I thought I should report what was given to me.

02/02/05 – 800 reported today that the new softener cannot keep up with the water load into the CR tank. TE is investigating this situation and will advise soon.

02/01/05 – TE request updates from contractors for these issues: Water Sampling Station, Draft Controls, Steam Leak at Flange (up high & extra charge) and Concrete Repair.

01/26/05 – TE faxed request for final documents to the attention of Amy Reeves of Peck Hannaford & Briggs. TE coordinated with PHB on fixing concrete flooring in boiler room. TE to discuss with County painters about re-epoxying the floor to match existing red floor previously installed.

01/19/05 – TE faxed back seal pump replacement quotes to Tony for Chiller Room.

01/18/05 – TE talked to Stoermer Anderson about wiring the drafts controls and we still haven’t received new wiring schematics. Tom Schmidt convinced them that just wiring schematics isn’t what we need, so they are sending new internals to the site for installation with new operator manuals that will be up to date and correct so that in the future the wiring schematic will match what is inside the draft control boxes. This work, however, won’t happen until next week at the soonest.

01/03/05 – TE trying to finalized punchlist and get control system backed up on CD format for County. PHB to begin final punchlist work and SA to retrofit draft controls this week according to Tom Schmidt.

12/13/04 – 800 called today because unit heater was not running in electric room and the space was cold. TE advised that the heater should come on anytime the sensor on the interior wall reached 45 degrees. Also, there is no graphic for this heater or control over this heater from Metasys. TE will stop down to check on situation today and help out.

12/10/04 – TE confirmed that SA should be on site on 12/14 or 12/15 to fix the water softener and the draft controls for the boilers. TTC told the building staff that the OA setpoint for the boilers can be used to adjust the start temperature of the plant at anytime. 800 reset the temperature up to 55 degree F.

12/02/04 – TTC stopped at building today and observed that boiler 2 is not running well. He sent emails to contractors for repairs. TTC noted punchlist items that need to be completed and contacted PHB about schedule to finish.

12/01/04 – Automation made final control changes at the site today to fix runtime accumulation modules, labeling the DX-9100 modules and verify the operator control points for lead and lag boiler start. TE forwarded the email received in response to that visit. A&M will update the sequences and get as-builts drawings to TE for inclusion in the final O&M’s for the County soon.

11/26/04 – TTC stopped at the building on Wed (11-24) and Fri (11-26) to verify and watch operation. The boiler plant is running in complete automatic operation at this time and ran appropriately over the Thanksgiving holiday. On Friday, the building was warm and there were no critical alarms on the boiler plant or any manual resets required at either the boiler of the condensate receiver. Todd Zurweller provided the final piping punchlist that will be converted to as-builts drawings that will be turned over to GBBN for inclusion into the CAFM sets. TE will follow up with Peck and Stoermer on the completion of punchlist items within two weeks and TTC will follow up on some control issues and boiler ops issues that he would like to see defined a little more clearly. SA completed the replacement of the solenoids valves, additional strainers in the feedwater system, HOA switch on Boiler #2, and new overloads on the all 3 boilers to prevent nuisance inrush tripping. SA still has to repair the water softener control plate assembly and replace the internals to the draft controllers for all 3 boilers. TE to expedite the remaining items. Remaining items to complete on this project (to TE’s understanding) are: CR water temperature at 150 degrees F (design calls for 190 degree F (SA shall adjust control valve to preheat the feedwater to meet spec), water softener repair, draft control replacement, sump lid replacement, seal replacement on vacuum pumps, seal replacement on cooling plant pumps, concrete repair in boiler room, A&M has to fix the runtime hours display, A&M has to label the DX’s inside the panels for points, A&M has to provide updated as-builts for controls (TE reviewed preliminary submissions with Roger Corbett on 11-24), Peck must install breeching cover must be installed, Peck has to replace or fix the trap on B-3 as it blows by when in normal operation. Glen Wilhoit found a bypass valve open on the condensate receiver, which when closed, fix the steam blow by problem into the floor drain behind the CR unit and stabilized the water level inside the CR immensely, TZ commented that the trap on the CR unit overflow meets the 12″ dwg requirement but TE prefers this trap to be as deep as possible as this is what provides the non-mechanical seal on the CR tank to keep any steam from escaping (we will check back at end of project to see about allowance monies left to increase depth). Peck shall have insulator finish up all insulation on project (lots of insulation work left to do). TE instructed SA to disable the high water level alarm on the CR tank because of nuisance tripping (this alarm is for notification only and requires no user input to fix anything so we just turned it off – the staff reported that the old tank would have high water conditions too but never had an alarm so we will just match the old operation, the tank itself is sized for 4 boilers condensate return so it is of ample size for this plant per Todd Zurweller. The water TDS from the sample coolers has been reading like this this week: at the CR 600-900 micro siemens (this makes sense, city water is about 300-600 normally), the boiler samples have shown 3.6 milli siemens or 3600 micro siemens which is also right in line with what we would want (i think 2500 – 4000 is okay, anything in the 6000 or higher would tend to lead to carryover) and lastly, TTC adjusted the gate valves on the outlet of the boilers to about one hands width of stem showing in an attempt to calm down the surging of the boiler sight glasses, this seems to let the water level stay more consistent and allows the make-up water to keep up with the boil off rate at all conditions, the closure of these valves may be changed when the boiler plant is under heavy load if needed.

11/23/04 – TTC watched boilers all day last Friday. The water controls are such that the boiler plant is too finicky to leave in total automatic operation without expecting nuisance alarms from either low water at the boilers, high and low water at the condensate receiver or overfilling of the boiler vessels through the solenoid valves. SA reports that all components replacements are scheduled for Tuesday except for the draft controls which will be done ASAP. TZ is sick so the TTC & TZ field trip has be rescheduled until Wed at 2:30 p.m. If Glen Wilhoit has any questions please have him call TTC at the office. TTC discovered that the solenoids are letting water bleed past even with a pump on all the time and not the check valves as the water level stayed the same all afternoon with the feedwater valves blocked. In addition the traps on the boilers only drain the boiler vessel when there is a positive pressure inside the vessel, once in a vacuum they are not draining enough water to keep the boiler from overfilling on this day.

11/22/04 – TTC talked to Glen today and we discussed looking at these issues: slope of main steam header towards traps, conduit cover on Boiler # 03, Vent on receiver tank. TE will investigate these issues on Wednesday at the TZ walk through.

11/18/04 – Boiler #1 is overfilling with water. Last time this was due to dirt in the feedwater line blocking the solenoid valve. When the new valves and strainer are installed by SA, this problem should be eliminated. 800 could try to run Boiler #3 instead of #1 to alleviate this problem.

11/16/04 – The boilers are carrying over on startup and shutting down on low water forcing the electric overloads to cut out. SA has to replace the overloads on each boiler to correct this problem, replace the HOA on boiler #2, upgrade the draft controls and install cycle timers into the boilers. This work should be done in one week. All 3 boilers are available for use. At morning startup, Tony Martini may want to turn 2 boilers on and back down the gate valves to 30% of so to allow the plant to come up to working temperature to smooth out this hiccup. Very soon, the boilers can be left on full time. TE is worried about the surging in the CR unit and boiler. The water levels are bouncing around more than we would expect. TE to investigate more.

11/12/04 – All contractors and TE were on site to finish up the project. TE hired Geiler directly to replace the Condensate #4 pump seals because Peck could not meet the schedule. Upon disassembly we discovered that both seals needed to be replaced along with one motor bearing and one motor winding. TE authorized this work to be completed so that the plant can be ran in full automatic on Friday 11-12, Peck service was on site to replaced six sets of seals on condensate pumps CR-1, CR-2 and CR-3, Peck was only able to replace one seal on CR-2 (this work was being done at T&M, TE recommends that we re-evaluate having Peck do all the pumps as we don’t believe there will be enough money left in the allowance to pay 2 days of T&M for each of the 5 remaining pumps, we bought all the seals already which cost $1200, Peck and Cinergy upgraded the gas supply line to 1psig pressure, tested it, installed new regulators and put the system into service. 800 now has a new regulator for the water heaters and for AH-43 on the roof. After purging the system, all the equipment was back in service and burning properly by the end of the day on Friday. We permanently disconnected the garage AH unit that was abandoned, the County CANNOT use this unit unless another regulator is put in the gas supply line (this shouldn’t be an issue since this unit hasn’t been used in 10 years – the gas line has been capped. Stoermer Anderson (SA) finished wiring the draft controls and adjusted all the burners to spec. The draft controls need some different components in the upcoming week as they only work in the wide open position right now. The water softener needs to still be replaced since the Crown Engineering unit was damaged in shipping. The sparge tube and control valve were installed by Peck and adjusted by SA. The unit heater was installed by Peck, wired by Glenwood, and wired by Automation for controls. The unit heater and the exhaust fan worked per spec. The punchlist was commissioned by TTC and will be sent in a separate email where TTC will document remaining items including training which should be given Mon, Tue or Wed of the upcoming week.

11/10/04 – Glenwood will finish up the electrical work on Thursday. Final inspection scheduled for Monday. Please make the accommodations to allow the inspector into the building. All contractors are scheduled for work on Thursday as well. TTC will call automation when enough of the boiler is complete to allow control system to take over control of the boiler plant. Final commissioning and punchlist will happen in afternoon on Thursday.

11/08/04 – All gas pressure work is scheduled for Thursday 11-11-04. The building will be shutdown for Veteran’s Day. Peck, Stoermer, Automation and Cinergy will all be onsite connecting and verifying all final workings of the boiler plant. Terry Cannon will also be onsite to assist in the last minute details. Water softener and unit heater are on site ready for installation (softener has ctrl panel issue). Stoermer has sparge tube in town and hoping control valve will arrive on Tuesday. Stoermer needs to finish wiring the remaining local controls on the boilers. Today’s onsite work proved that one boiler and both water heaters cannot run at the same time without the boiler going out on low gas pressure. PHB assured us that the boiler room door will be installed on 11-09-04. The vacuum pump seals were ordered for overnight shipment and should arrive on Tuesday to Peck. Geiler will be in at 7:30 a.m. on Tuesday to install the seals on the Condensate Pump-4 in the chiller room (ttc coordinated with Geiler and Martini for this work). Outdoor louver needs to be installed. Final insulation needs to be installed. Final control programming needs to be implemented. Training for Tony Martini needs to be provided by Automation (ensure the whole system is demonstrated, optimized control of cooling towers, free cooling, boiler sequences, etc).

11/03/04 – TE confirmed today that the Seller’s boilers can handle and are built for 10 psig inlet gas pressure, at worse case a spring needs to be changed in the regulator and SA will provide that service at no charge. TE instructed PHB to buy two regulators at this point: (1) for the water heaters sized for 2 x 199,000 btuh, 1 inch, 1 psig to 9″ w.c. and (1) for the AH-43, 1 x 160,000 btuh (5″ w.c. nominal, 14″ w.c. max), 1 psig to 9″ w.c. Emergency pressure at inlet to be protected up to 10 psig. As soon as we get the new regulators in we will schedule the work and the shutdown and as TE understands it at this time, Tony Matre has instructed PHB to do this work after normal hours or on a Saturday.

11/02/04 – Remaining project items: insulation, water softener, sample coolers, door installation, damper controls, large louver for combustion air, unit heater, sparge tube, boiler #1 falsely enabled, new regulators for water heater, coordinate pressure test, adjust fuel air mixture, sump lid, chain link fence, seal barometric damper, seals on vacuum pumps, reinstall exit sign. Be complete by November 12 including controls.

11/01/04 – PHB coordinated with TE today on boiler requirements for new venting. Sizing requirements are 17,258,000 btuh connected load (5,620,000 each boiler, 199,000 each water heater, 1 psig inlet pressure (with an emergency inlet pressure of 10 psig), 15 inch w.c. outlet, if a 2″ regulator can meet our flow demands, we won’t need a separate relief valve for the regulator (provided it uses rubber seats), Dead End Lock Up Model type, Main burner and pilot applications, static pressures will be allowed to rise slightly above setpoint, an additional regulator will need to be installed for the water heaters in the 1″ line. We will discuss more at Tuesday construction meeting.

10/27/04 – PHB reported today that boiler breechings are welded in. One louver is installed, the other will be installed shortly, the blank off plate on the other pipe space will be installed next. The new water softener shipped 10/26. Then unit heater should be shipped very soon. Controls are supposed to be ready to go but TE and PHB will confirm. TE would like to meet on Thursday morning at the site and call Cinergy for the gas pressure issues and begin the resolution process.

10/21/04 – Door will be installed on Monday. Stoermer Anderson will be onsite on Friday. Automation will be on site on Friday. Boiler #1 will be in automatic operation on Friday 10/22/04. PHB will have flues welded in by Wednesday 10/27/04. Boiler # 2 & # 3 should be ready to fire for Cinergy test on 10/28 or 10/29. Please make accommodations for everyone to be onsite Thursday 10/28 for this work. Water softener should ship today or tomorrow for installation.

10/18/04 – Stoermer Anderson reported that gas pressure was very low for the boilers at the site. Boilers require 10 inches. Today’s readings showed 7 inches available. TE is investigating how to solve this problem.

10/18/04 – PHB submitted a price of $4106 to reroute the PVC vents from the domestic water heaters. Do you want to do this work or should we keep things as is and let the trades do the work in the future if it becomes absolutely necessary?

10/15/04 – One boiler successfully started today right on schedule. On Monday SA will verify gas pressure in building as it appeared to be low today. SA is on site preparing boiler for startup. Draft control damper is installed. The door to the boiler room will arrive on Wednesday of next week and will be installed on Wed-Thur-Fri. The insulator will be installing 2″ fiberglass on the steam header to match the 2″ piping shoes, the entire breeching will be replaced with new insulation, A&M is on site downloading the new boiler control program this morning, the CR-1 unit comes factory equipped with a low water cutout switch that turns the pumps off on low CR-1 conditions. TE has the DDC system programmed such that it will stay enabled if a feedwater pump goes into alarm so that when the CR-1 unit comes out of alarm the pumps plant will be standing ready to re-engage. Alarms will be issued on the front end documenting the history. The exhaust fan is being installed today. For future maintenance on the new exhaust the facility group will be able to remove the louver and the fan but they will need a lift to access the fan just like the old one. The fan is not removable from the alley (TE doesn’t want vandals being able to mess with the fan)

10/14/04 – Boiler inspector approved ALL boilers for use today. PHB, TE A&M and SA were all on-site for an impromptu construction meeting when we really were meeting to discuss the installation of the sparge tube in the DA tank. Final decision was to move the vent over to the middle 3″ connection and put a vertical then horizontal sparge tube utilizing a double bushing into the open 3″ connection. SA will do much of the work for this and the temperature sensor for the steam control valve and PHB will provide the final connections to these steam heating points. PHB is finalizing piping and B-1 will be started up on friday towards the very end of the day. B-1 will be put into test service on Monday October 18 where 800 can keep an eye on it during its maiden day of work.

10/12/04 – Mike Martini the boiler inspector will be onsite on Thursday at 10:00a.m. ThermalTech, Peck and Stoermer Anderson would also like to be on site that morning about 8:30 a.m. PHB is trying to get all equipment on site and the boilers ready to fire by the 15th as promised.

10/08/04 – Obtained field data on Chilled Water Pumps, in order to get price quote for replacing seals.

09/03/04 – Date Answered: 09/03/04. Question: The Drip Pan Elbows for the boiler relief vents are shown as 3 inch RV’s. The DPL are being supplied as 3.5″ how should we handle? Response: TE instructed PHB that however the DPL’s are delivered to provide a reducer/increaser to 3″ and run the RV’s as 3″ as they are shown on the P&ID. We believe that the 3.5″ might be the OD listing for the 3″ pipe anyways and may be a non-issue.

09/30/04 – Control equipment is on site except for unit heater control valve. Programming will begin at A&M offices on Oct 3. TE has asked contractors to have one boiler online Oct 8 if possible.

09/29/04 – TTC stopped down and told PHB that they can reuse the existing cond header up to the union, TE prefers that the new boiler stack connections be round to round with a saddle at the breeching connection (remove the long skinny rectangular existing connections, TE wants PHB to provide an allowance price to reroute the domestic water heater PVC exhaust vents to the same window outlet as the gas vents are using (TE will provide a sketch to PHB to price), Boiler #2 should be located to miss the existing pit lid, the EOM traps are correctly sized at 3/4″ so bushings from 2″ to 3/4″ are acceptable, one of the intake louvers appears to be 59″ x 59″ the other window will have the EF in it and the vent lines: PHB can build a painted steel or aluminum blank off plate to surround the vents in the remainder of the window – it has to be water tight to prevent rainwater from entering the space (TE to review CA req’s on remaining louver), TE and PHB reviewed CR-1 inlets and agreed where everything goes, Boiler #4 breeching should just be capped as-is, TE told Tony Martini that existing plant is supplied with combustion air without aid of mechanical combustion air: if 4th boiler is ever added, the County can add a forced combustion air fan, increase existing louver size, or provide another opening in the outside air wall (the existing plant CA req’s are sized on 3 boilers connected load per code req’s)

09/24/04 – Glenwood submitted additional cost based on TE request for strobe relocation and alarm conduit relocation of $214.00 and $427.00. Approved by AKM via phone call.

09/23/04 – Boiler are in the rigger’s yard. Peck will deliver them to 800 on October 2. County, please make appropriations to allow PHB in the building for this work.

09/13/04 – Weekend work was exceptional and the large steel tanks was also removed from the premises.

09/08/04 – PHB Advised that first boiler will be delivered and existing boilers will be demolished on 09/11/04 at 7:00 a.m.

09/03/04 – Control submittals have been received.

09/01/04 – TE approved allowances 01, 02 for PHB shown below.

09/01/04 – TE sent a letter to city explaining boiler plant sizing. We sent email with attachment showing fax.

08/31/04 – PHB has submitted door and louver equipment for approval on 08/24/04 – Returned approved. EF needs to be 203V/3Ph version when ordered.

08/27/04 – TE is trying to get final pricing and ok on water softener package for project from PHB and SA.

08/25/04 – Boiler removal and installation scheduled for September 11, 2004.

08/25/04 – CIS will be removing asbestos in the interim.

08/25/04 – Quick ship boiler scheduled to ship on August 31.

08/25/04 – Condensate Water Return system also scheduled to ship on August 31.

08/25/04 – New door has been cut in with plywood secure doors installed.

08/25/04 – Some prefabricated piping has been deposited on site.

08/25/04 | Date Answered: 08/27/04 Question: A conduit shown to be demolished contains boiler and chiller alarm wiring. Should this be kept and maintained?
Response: TE will confirm with John Noyes next week. The alarms provide remote alarming up to the night desk security shack where the on duty security officer is instructed to call John Noyes. The new control system has been installed with alarm paging service which provides the same functionality so this may not be required at all.

08/12/04 | Date Answered: 08/13/04 – Question: For the spool drawings, what is the most important factor for boiler dimensions.Response: TE stated that the boilers are to aligned under the breeching and centered between the columns but the contractor has some leeway with final and exact boiler placements

800 – BOILER REPLACEMENT PROJECT Read More »

800 BROADWAY Vacuum Pump Replacement

05/22/09 – We have turned over all the closeout paperwork from Process on this job to Tony. Joe signed the change order at Tony’s office. We created the as-builts and gave them to Bert in CD format with the original marked up drawing. TTC delivered to Bert’s mailbox on 05/18/09.

02/02/09 – TTC inquired about approving this change order again with Darnell & Tony.

01/05/09 – Process is not budging on the a negotiated settlement for their change order request. TTC talked to Joe Doxsey and Tony Matre and could not arbitrate a settlement. TTC asked Joe to call Tony directly to try to convince him of the extra monies. Tony stated the extra valve cost were fine. The sticking point is the extra labor and material mark-up from last year to this year. TTC mailed in payapps 4 & 5 for this proejct which leaves $1000 for closeout plus the change orders to resolve.

12/18/08 – TTC and Process have sent change order payment request to Tony. TTC requested final payment except retainage from Process.

11/25/08 – ThermalTech sent permit drawings to Ginter. Punchlist to Process Const and Change Order from Process to the County.

11/03/08 – Punchlist is completed. Pumps seem to be working fine when all four condensate pumps are left on to handle the building load. TTC has inquired about operation several times with bldg personnel but no response after visit.

10/16/08 – Vacuum pump testing is scheduled for 10/28. Rod will attend for TEI and do a final punchlist.

08/22/08 – TTC talked to Process about project completion which is about 98% complete. TEI asked that O&M’s include warranty letter, equipment submittals and contact information. Commissioning of system needs to happen after the unit is started up in October. Controls should be complete and main pumps should be working. TEI will want to see automatic backup of the pumps and vacuum pumps operate. Each lead pump should work first then each lag pump should take over if there is a failure on the main pumps. Electrical and Controls still have a little work to finish before TE punchlist. Process is submitting a new pay application for most of remaining budget.

08/05/08 – TTC visited the site today to do a pre punchlist check over. The project looks excellent. Piping is nearly complete. Insulation next and then electric and controls. The project should be a couple of weeks from completion. We are investigating the need for additional disconnects.

07/30/08 – Equipment is installed. Insulation and electrical will be installed over next two weeks. Contractor expects to be complete within one month. Process has experienced material cost increases and pay period increases and will be submitting a change order for our review. There is a question about physical disconnects for condensate pumps. EC says we need them. Mechanical schedule says they are provided with the equipment.

07/09/08 – New pipe routing and equipment locations finalized. Housekeeping pad size selected by owner and coordinated with contractor.

Equipment Ordered

Layout changed based on actual footprint of Skidmore equip.

800 BROADWAY Vacuum Pump Replacement Read More »

800 – Polygonal Pavilion Roof Repair

03-30/12 – THP Reviewed findings with Bert Watts and work complete. THP recommends completing repairs with coating. THP to issue a summary letter.

03/30/12 – THP Reviewed findings with Bert Watts and work complete. THP recommends completing repairs with coating. THP to issue a summary letter.
03/28/12 – THP Reviewed patches during gutter repair project and some patches are cracked. THP to review condition with Bert Wattts.

SSRG completed test patches on west and south elevation. Patches to be reviewed late spring by THP.

800 – Polygonal Pavilion Roof Repair Read More »

800 – Gutter Study

03/29/12 – SSRG completed test excavation with SSRG. Drain line not leaking. THP to review findings with Bert Watts. THP with support from SSRG plans to excavate and complete a test repair of gutter at drain line. THP to coordinate work with Darnell.

03/30/12 – THP Reviewed findings with Bert Watts. Water tests did not indicate the gutter or drain line was leaking; but transitions between the gutter and roof are leaking. In conjunction with the roof repairs, additional flashing repairs will be necessary during future projects.

800 – Gutter Study Read More »

800 12th Floor Courtroom Renovations

Project Lead: GBBN

07/11/12 – Bert Watts called and requested GBBN call Tim Moorman to discuss kick-off meeting. GBBN speaks to Tim and discusses project.

07/13/12- GBBN visits the site for the kick-off meeting. GBBN contacts Facilities to discuss original shower reportedly removed from Judge’s Chambers. No one has any knowledge of existing shower on this floor.

07/13/12 – Erica Farris calls requesting another visit to discuss more scope to project. Adding Prosecutor’s Waiting Area renovations or moving of existing Courtroom to other side of floor.

07/13/12 – GBBN verifies existing Facilities AutoCAD files are not fully accurate of existing conditions nor is millwork or furniture shown on these plans.

07/16/12 – GBBN performs field verification of existing spaces and updates AutoCAD drawing files.

07/18/12 – GBBN forwards SOSS to Facilities Department. HCFD emphasizes no work to be performed before SOSS approved.

07/18/12 – Erica Farris requests GBBN to visit site again to discuss additional scope items.

07/18/12 – Erica Farris requests GBBN to forward field verified drawings to Office Furniture Source.

07/19/12 – GBBN forwards updated AutoCAD drawing file via email.

07/23/12 – GBBN visits site again at request of Tim Moorman. Update of project given to Tim upon return from vacation. GBBN asked again about the option of moving the Courtroom to other side of floor. Tim mentioned this option was never discussed previously.

07/30/12 – Erica Farris requests update on design initiation. GBBN reports SOSS has not been approved yet.

07/31/12 – SOSS approved and sent via email from Bert Watts.

08/02/12 – GBBN sends updated AutoCAD files of Office Furniture Source.

08/02/12 – GBBN is contacted by Erica Farris to discuss changes to desgin to add an access corridor from Judge’s Chamber to the Courtroom and changes to the Prosecutor’s Waiting Room. GBBN responds that day.

08/03/12 – ThermalTech sends drawings of the existing 12th Floor mechanical system and description of operation.

08/03/12 – Erica Farris notifies GBBN that Office Furniture Source has suggested subdividing the Prosecutor’s Waiting Room into three space. GBBN is asked to investigate the possibilities. GBBN responds about code issues regarding occupant loads, egress, fresh-air for occupant load for conference rooms and waiting rooms.

08/13/12 – GBBN finalizes Options #1 through #5 along with Pros and Cons of each and an Estimate of Probable Cost for each.

08/17/12 – GBBN meets with Erica Farris, Judge Hunter, Case Manager and Sheriff’s Deputy to review options and discuss other programming issues. Options are reviewed and critiqued. GBBN is instructed to modify Option in Courtroom to include Deputy location and Additional Attorney Seating.

08/23/12 – GBBN sends updated Option #6 showing input from previous site meeting.

08/24/12 – JAVS contacted by GBBN about relocation of existing control box and Opinion of Probable Cost via email on website.

08/26/12 – Bert Watts is sent all Design Options and Opinions of Probable Cost.

08/27/12 – JAVS contacts GBBN about inquiry into relocation of existing control box and Opinion of Probable Cost. Future site visit may be coordinated in near future. Bert Watts indicates Judge Hunter’s Office is now requesting painting of Courtroom and adjacent spaces, refinishing of existing hardwood floors and carpet/base be added to scope. GBBN forwards pricing information for painting to Bert Watts.

08/29/12 – Erica Farris requests GBBN to visit the site again to discuss additional changes to the Option #6. GBBN visits site to meet with Erica Farris. The design is modified and resent via email that afternoon.

09/07/12 – Bert Watts and GBBN meet with Judge Hunter and Erica Farris to finalize latest schemes and options for the Courtroom and Attorney’s Waiting Areas. Discussions held to examine how to proceed from this point forward.

800 12th Floor Courtroom Renovations Read More »

800 Electrical Power Failure Emergency Response

Project Lead: TEI

01/24/14 – Due to sprinkler line freeze and break on the second floor, water infiltrated the electrical gear in the Sub Basement of the the building and caused a fault, which then left the building without utility power for 2-1/2 days. Hamilton county facilities department, ThermalTech, Duke, IBI, county electricians, and building staff worked collaboratively with each other to restore utility power to the building. The fault left the building with only one Duke feed (The Duke switching cabinet in the sub basement requires that one of the switches be re-built by Duke). The Control Power transformer in the building service was damaged. Jeff Jones from ECI has placed order for replacement CTT.

01/24/14 – TEI submits SOSS to Bert Watts.

02/25/14 – TEI receives approved SOSS and purchase order.

03/26/14 – TEI completes work associated with emergency response.

04/24/14 – Project Complete.

800 Electrical Power Failure Emergency Response Read More »

800 Electrical Switchgear Repair

Project Lead: TEI

01/24/14 – TEI communicating with CEPower and IBI to determine regulatory regulations that will be required to restore both services to operation (normal and standby service from Duke). TEI will then author and submit SOSS to Bert Watts for approval.

02/25/14 – TEI met with Matt Kennedy of CEPower on 2/20/14 to discuss scope of services that CEPower to provide. CEP and TEI had a conference call on 02/25/14 to discuss project, test plans, etc. TEI to submit SOSS to Bert watts upon receipt of CEP fees (to work as a sub to TEI). Anticipated ship date for CPT from General Electric is 03/13/14 (according to Jeff Jones).

03/26/14 – TEI received late on 03/25/14 proposal from CE Power to do testing. TEI authoring the SOSS for working with IBI, Jeff Jones, and CE Power to restore power to remainder of County owned equipment. TEI communicated with Duke Energy (Jeff Hesse) to advise that the anticipated restore power date from the County switchgear. Jeff Jones of CEI indicated that the replacement control power transformer and relays are at his shop and as soon as PO and contracts are executed, the re-install can be scheduled.

04/22/14 – SOSS submitted to HamCo. Project approved and commencing immediately. Duke repairs have began. TEi to schedule Work on getting the Permit completed sot that the gear can be restored to full pre-fault functionality.

05/28/14 – ThermalTech has met with CEPower and discussed with Jeff Jones the restoration of the switchboard. CEPower to identify length of time that the outage will take and then also give ThermalTech timing of when the testing can occur. Jeff Jones has equipment at his shop and plans is to install all parts that are in non-energized cabinets ahead of outage to keep the outage duration to a minimum. HamCo to identify timing when outage can and/or can not occur.

06/25/14 – The switchgear is restored on the County side. IBI inspection on 06/25/14 (approved – temporary release) and IBI to send release to Duke to get release to power up gear for final testing by CE Power. Duke anticipates to restore their switching and be prepared to get power back on week of June 30, 2014.

07/30/14 – Duke switchgear restored and ThermalTech received notification on 07/14/14 that Duke was ready to re-energize. ThermalTech contacted all of the parties (CEP, ECI, IBI HamCo Duke) and the final testing and restoration of the gear is scheduled for 08/09/14, work beginning at 8:00 AM.

08/25/14 – All associated parties met on site on Saturday 08/09/14. The primary and secondary sources are now connected and the auto-throw over equipment is fully functioning per the original design intent of the gear. IBI inspected the gear and gave a final approval of the restoration of the gear. power to both primary and standby services are now on and the building gear is back to being fully functional.

800 Electrical Switchgear Repair Read More »

800 Energy Star 2014

Project Lead: TTE

09/23/14 – Terry and Bracken visited the building and took the air, people and light readings for the verification process.

10/23/14 – Final submission paperwork is complete. Ralph signed, ThermalTech is uploading to website.

12/12/14 – Building was certified in November and uploaded to LEED with an 88 score.

800 Energy Star 2014 Read More »

800 Freezestats

Project Lead: ThermalTech

08/29/12 – ThermalTech visited the site several times to discuss 2013 installation of freezestats by Process Construction. It was determined and recommend by TTE that freezestats on units which have had their non-glycol preheat hot water coils removed do not need freezestats reinstalled. This applies to most of the low rise units. A&M will leave the freezestats in the units and jumper across them so they don’t shut the fans down on morning warmup but will also implement a full morning warmup cycle in cold weather to prevent unnecessary overcooling of the Supply Air stream in these units.

11/28/14 – After investigating the L-71 rooftop unit with the same issue and getting prices from the vendor for a replacement unit or a electric preheat coil option it was determined the same strategy could be used for this unit. The freezestat will be bypassed, this was discussed and agreed on between Terry Cannon, Darnell Edward and Tony Matre. The unit has not frozen in the 14 years we have been working with the County at this building. The RF-1 also does not need to run to prevent the freezestat from tripping, A&M will bypass this freezestat too.

800 Freezestats Read More »

800 Lighting Study and Report

Project Lead: ThermalTech

08/29/12 – SOSS approved and PO received by ThermalTech. ThermalTech to work with BW and schedule kickoff to determine study schedule and needs.

09/26/12 – Initial daytime readings (Normal power) completed by ThermalTech on 9/25. Mike Barth reviewing findings and preparing night time night light and emergency light readings schedule. Coordinating with Darnell Edwards. Initial conclusions – most places are within guidelines, however, there are many areas that lighting is low and many other places where lighting levels are high.

10/31/12 – Night light night readings are scheduled to occur between 8:00 PM and 6:00 AM on Thursday night, November 1st, 2012. Mike Barth of ThermalTech coordinated with building manager and Tony Matre for access to building. Upon completion of the survey, the results and report will be written up and sent to Bert Watts for review.

01/30/13 – All light readings have been complied and indicated on drawings. Report is in process and will be completed in next few weeks for Bert Watts to review.

04/24/13 – Review copy of report to be sent to BW by end of April for comments.

03/25/15 – TEI received BW review comments, and printed 3 copies of final report for Bert Watts. Final report delivered to BW on 03/20/15. Project complete and can be archived.

800 Lighting Study and Report Read More »

800 Roof Repair

Project Lead: THP

06/01/12 – THP submitted SOSS.

09/13/12 – County approves SOSS.

10/04/12 – THP County kick-off meeting complete. DD documents due early November and Final bid documents due mid-December with a budget. Bid period mid-February.

10/31/12 – THP working on DD documents.

01/15/13 – THP Issued DD documents for review.

02/08/13 – County returned project manual comment.

02/19/13 – THP and County had a design review meeting.

05/17/13 – THP issued 95% Review documents to the County.

06/27/13 – Project update. Due to weather sensitive work, if project approved work will not occur until next spring. Possible bid project late 2012.

10/31/13 – Project on hold.

01/30/14 – Project on hold.

04/24/14 – Project on hold.

06/26/14 – Project on hold.

07/31/14 – Project on hold.

08/27/14 – Project on hold.

09/25/14 – Overall project on hold.

01/29/15 – Overall project on hold.

02/26/15 – Overall project on hold.

03/26/15 – Overall project on hold

04/01/15 – THP requested to assess current roof condition and provide a summary report letter.

04/17/15 – THP published roof assessment letter with updated opinion of probable cost.

800 Roof Repair Read More »

800 Domestic Relations Renovation

Project Lead: GBBN

06/23/15 – County requested GBBN attend a kick-off Meeting at 800 Broadway on Tuesday, June 30th at 2:00 pm.

06/30/15 – Kick-off Meeting held at Domestic Relations area. Scope drawings prepared by the users are distributed.

07/02/15 – Original SOSS submitted to Facilities Department.

07/15/15 – John Nester contacts GBBN about revising SOSS without walk-through permitting services.

07/16/15 – GBBN submits revised SOSS to Facilities Department.

07/30/15 – Approval came in yesterday. They would like to move in by September. Try to make renovation require no sprinkler work so split the sprinklers with walls.

08/18/15 – TEI confirms no fire suppression sprinkler head modifications are required on this project. Bert Watts finalizes the last scope questions to GBBN.

08/20/15 – GBBN submits combined Building and Mechanical Permit to the City of Cincinnati Permit Center.

08/25/15 – TEI submitted drawings to IBI for approval, pending plan review. TEI reviewed CAGIS page and plan review issued complete (CIC1503111).

09/23/15 – John Nester indicated that the electricians are ready for a rough-in inspection. TEI contacted IBI, and IBI can not perform any inspections until the building permit is issued. TEI is waiting on notification that the building permit has been issued to contact IBI again. HVAC is complete and measured airflows are at or above design CFM’s.

10/28/15 – Rough in inspection completed and passed with IBI. ThermalTech called IBI for the electrical final inspection, scheduled for Friday morning, 10/30/15. ThermalTech to contact IBI Friday between 7:30 and 8:30 for inspection timeframe window.

800 Domestic Relations Renovation Read More »

800 6th Fl Courtroom Renovations

Project Lead: GBBN

08/12/13 – Kick-off Meeting with Bert Watts and ThermalTech.

08/16/13- TEI submits break down of scope, reimbursable expenses and hours to GBBN,

08/17/13- County requests new SOSS based on lowered scope. Bert Watts confirms no scope of work involved on 12th Floor. Moving by Owner.

08/19/13- GBBN submits SOSS to Bert Watts.

08/19/13 – County requests break downs for consultant scope and hours for the SOSS to GBBN. ThermalTech is working on the CT strategy and will talk to the HVC chemical treatment contractor.

05/21/14 – GBBN requests full recycling tracking information beyond the paper only sent 5/24/14. Request also made for total waste disposal records from building to determine percentage of waste that is recycled.

05/27/14 – Bert Watts sends Sustainable Purchasing Tracking information to GBBN.

05/29/14 – GBBN receives word from USGBC that the review of the LEED EB+OM application has been received.

06/10/14 – GBBN receives word from USGBC that the review of the LEED EB+OM application is commencing.

07/09/14 – USGBC sends initial review comments to GBBN for review.

07/28/14 – All involved partners attend team meeting to discuss approach for returning responses to the review comments back to USGBC.

09/09/14 – Bert Watts requests estimate for this project to be authored and billed to General Services Contract.

01/28/16 – Project ready to archive.

800 6th Fl Courtroom Renovations Read More »

800 First Floor Staff Relocation

Project Lead: GBBN

08/09/15 – County requested GBBN attend a kick-off Meeting at 800 Broadway on Tuesday, August 11th at 2:00 pm.

08/11/15 – Kick-off Meeting held at 1st floor north Office Suite area. Scope drawings prepared by Facilities is distributed to GBBN. Photos taken of north and south side areas and existing systems furniture.

08/12/15 – GBBN notifies Facilities of the existing electrical code implications of disassembling and reassembling the existing workstation cubicles per TEI and IPM’s input.

08/25/15 – Facilities notifies GBBN of the two Archibus Pop-up Project Request numbers for the estimating input.

08/26/15 – GBBN completes both estimates in Archibus and reports to Facilities they are completed.

800 First Floor Staff Relocation Read More »

800 Court of Domestic Relations Wireless Study

Project Lead: TEI

09/23/15 – TEI submitted SOSS to Bert Watts, Pending Approval.

09/24/15 – Bert says they might already have some wireless in place so this scope may be altered.

10/28/15 – TEI gets approved SOSS and PO – Bert and TEI trying to schedule Kick off meeting with Shannon Supe et al.

12/07/15 – TEI met with Greg Wandstatt and Todd Coriell to review the requirements from the Tele-Comm department. TEI met with Lisa Gorrasi (Court Administrator – Domestic Relations) on 12/08/15 to walk the space and to determine where in the building the existing WAP are located and where the areas of low/no coverage are. TEI to coordinate final recommendations with Facilities and with Shannon Supe.

01/26/16 – TEI issues copy of study to Bert Watts for review. Bert Watts approves study and asks for cost to implement the recommendations. TEI to develop cost and send to Bert Watts.

02/23/16 – TEI issues final report to Bert Watts for distribution.

800 Court of Domestic Relations Wireless Study Read More »

800 – Building Envelope Assessment

Project Lead: THP

06/13/16 – Stone debris was discovered on the east elevation. THP requested to complete an emergency stone review then a more formal building envelope assessment. ZSR to provide contractor support.

06/17/16 – THP submitted an SOSS.

06/21/16 – County approved SOSS.

06/22/16-06/28/16 – Emergency inspections of the façade via aerial platform and rappelling.

06/22/16 – THP started five day aerial survey of the base of the building and rappelling survey of the tower. THP provide details to stabilize (4) critical stone conditions on the base of the building.

06/27/16 – THP issued sketch of locations of stones to receive supplemental anchors. Waiting on some additional scans from archives.

07/25/16 – THP published a worst case stone and angle repair budget for the County to consider during short term planning.

07/28/16 – Final report anticipated to be complete mid-September.

01/26/17 – THP published final report.

02/03/17 – THP published report to County.

02/17/17 – THP updated cost estimate and published revision to final report.

800 – Building Envelope Assessment Read More »

800 Flat Roof Leak Assessment

Project Lead: THP

02/16/17 – Hamilton County requested SOSS.

03/10/17 – Met with Hamilton County to review scope and field conditions.

03/23/17 – THP provided Hamilton County with a SOSS.

04/06/17 – SOSS approved.

04/27/17 – Thermal scan rained out earlier in April. Next scheduled scan is May 2nd (weather permitting).

05/23/17 – THP completed thermal scan of roof.

05/25/17 – THP visited site to meet with County to observe and document areas of flat roofs where water was trapped behind membrane at south-facing parapet wall.

06/27/17 – County and THP to review active leak areas.

06/29/17 – THP working on report.

07/27/17 – THP working on report.

08/31/17 – THP published report for review by County.

800 Flat Roof Leak Assessment Read More »

800 Adult Probation Sub-Basement Project

Project Lead: ThermalTech

02/22/17 – TEI and Facilities met with Assistant Chief Probation Officer to scope out the project for the renovation of existing paper storage room. TEI to develop SOSS and submit to BW by 03/03/17.

03/20/17 – Met onsite to do more fieldwork. We found plumbing, HVAC and electrical locations for this work. Our belief after this field trip is that we can make this job work in this room.

03/22/17 – Project in design – fast track project to meet client deadlines.

04/12/17 – THP ThermalTech requested structural review of the proposed unit on the raised floor.

04/26/16 – Permits are in for electric and mechanical. Queen City Mechanical is submitting a permit for the plumbing but it should also be in by now. Mechanical bids have been submitted and forwarded to Bert Watts.

04/26/17 – THP published findings that design capacity of the raised flooring would support the listed weight of the AU480.

04/27/17 – Electrical Plan review approved. ThermalTech to pick up permit and drop off with facilities prior to monthly partner meeting.

05/22/17 – Electrical permit picked up and dropped off with facilities department.

06/08/16 – Feldkamp asked if they can route the new ventilation line form the room duct in flex. TTC reluctantly agreed but only if it can bring in the 50cfm required on the drawings.

06/22/17 – Electrical Installation complete, and the project has been inspected and final IBI approval received.

06/23/17 – Talked to Feldkamp and HVAC is complete, they were unclear about submitting for their own electrical IBI permit just for the unit but they are taking care of that.

07/25/17 – TEI provided Feldkamp revised drawing for IBI approval. TEI Checked EZ Track (Cagis) at 3:00 PM on 07/25 and no change in status (last update on Cagis was 06/26).

07/27/17- Electrical inspection complete, plumbing approved waiting for startup, mechanical permit approved, electrical HVAC permit awaiting approval. A backflow preventer may be added after startup of the new equipment.

08/31/17 – HVAC permit has deficiency concern for refrigerant in the boiler room ancillary room. TTC to check with Feldkamp.

09/25/17 – Called the City Permit department about comment on condenser being in mechanical room. I don’t understand this comment as R-410a has no flame propagation potential and its less than 5 lbs so there should be no issue with permitting, plus there is no OA for AHU in this space. I sent all this info to Feldkamp HVAC as well hoping to resolve this issue.

10/26/17 – Pat says this will be wrapped up by the week’s end.

11/28/17 – Feldkamp says that permit is cleared up with Reggie at the City and they will get this job closed out. TTC contacted them today to push that along. Reggie has clossed and approved the project.

800 Adult Probation Sub-Basement Project Read More »

630 Main – Community Development Renovation

03/15/05 – Indrolect reported the lamp was replaced with a Philips bulb. We will watch the fixture and see how long it last. If this bulb burns out, then Indrolect will verify ballast and wiring between the two fixtures to see why one is working and one is not.

03/14/05 – PHB delivered the FINAL O&M’s to Thermaltech today. TTC will review, approve and then hand deliver these to the County and in particular Joe Merkt within a

week (i have seen all this paperwork before but now i have it in book format). There are 3 manuals black in color and named Operation & Maintenance 630 Main Building. TTC also talked to John Nagel on status of outside spotlight and they are still working on it. Give them one more day so they can trouble test the wiring as I have asked them to do.

02/18/05 – Greg asked if one of the spotlights can be replaced at 630 as the lighting was not working. Indrolect had Bobby Potter visit the site and replace the bad lamp.

11/18/04 – Peck will be on site this Saturday to remove the internal insulation in AHU-1. This has been coordinated with Joe Merkt and represents that last item to take care of from the punchlist on this project.

11/17/04 – Indrolect and Square D ordered a complete new speed drive for RF-2 to replace the one that burnt up this week. We are hoping this is replaced within a week’s time. No cost to the project and contractors are to coordinate with Joe Merkt on the fix.

10/25/04 – Indrolect & Carrigan & Grimm Substantial Completions are signed and approved.

10/15/04 – TE has requested the PHB provide a price to remove or reword the existing ductwork on AHU-1 that has internal insulation that won’t be acceptable for winter humidification. The insulator was onsite on 10/14/04 with Joe Merkt. The price is forthcoming. All other punchlist items on this project are complete.

10/15/04 – TE has approved Indrolects O&M manuals and is sending one to Greg Smorey for record keeping and one directly to Joe Merkt for record keeping on this project.

10/15/04 – ThermalTech sent all substantial completion documents to the contractors for signing. All were dated for August 8 except for Peck which was dated for October 1, 2004. Four originals were sent to each contractor with instructions for them to sign and send all four to Greg Smorey. Greg was instructed to sign them and return one to the contractor and a copy of one back to ThermalTech.

10/13/04 – Five originals “AIA Certificate of Substantial Completion” documents mailed to each Contractor (Indrolect picked-up).

Temporary occupancy permit has been issued.

Door hardware issue remains to be solved.

Final punchlist and commissioning on controls must be completed.

Final balancing must be completed.

Final humidifier installation must be completed.

Joe Merkt to attend training course in October to meet training requirements of specifications.

630 Main – Community Development Renovation Read More »

2012 General Services – TEI

09/17/12 -Joann Cramer sent a new PW packet without the Terrorist statement included. TTC will udpate and distribute.

09/26/12 – SOSS-F056 Approved. TTC received, reviewed, updated and sent out the revised Prevailing Wage packet for Hamilton County Purchasing. Several edits were made by TTC. TTC updated the website for the new design with all buildings in facilities, black bar titles and updated projects for use and unloacked all building files for others to work on.

2012 General Services – TEI Read More »

Master Space Plan

Partner: GBBN

04/12/10- An email from Bert Watts requested a Kick-off meeting with Bud Wells in Courthouse B-90. First Phase of three to be performed in2010 requiring SOSS submittal.

04/15/10- Kick-off Meeting held with Bud Wells and Bert Watts. Handouts included Survey Form, Project Activity Timeline, Charter for Space Utilization Study and Buildings to be incorporated into study.

04/27/10- Clarification emails from Bud Wells and Bert Watts answered questions related to SOSS.

04/28/10- SOSS to be submitted to Bert Watts at Monthly Partnering Meeting.

05/21/10- Signed and Approved SOSS returned. Email from Bert Watts indicates schedule is to commence 6/24/10- Archibus Drawings to be updated are sent to GBBN from Bert Watts. Progress is on hold until In4 completes all Archibus polyline revisions and Michelle Ray completes all reviews.

08/04/10- Attended kick-off meeting to change this SOSS to another masterplan for the 237 Internalization study.

Master Space Plan Read More »

Master Plan Internalization Study

Partner: GBBN

08/04/10- Attended Kick-off meeting with Ralph Linne and Diana Supe.

08/18/10- Internal Kick-off meeting with Keven Speece, Thomas Rottinghuas, Jack Herbet Ralph Linne and Diana Supe along with Craig Landers and KEvn Maue of DDS.

08/30/10- Meeting with Ralph Linne and Diana Supe to discuss changes to the scope of this project. Project will now contain five options for relocation.

08/31/10- Met with Tony Matre and Bill Scholl at 237 WHT to walk the entire building and field verify the existing drawings.

09/01/10- Meeting with Jeff Alutto, Ralph Linne and Diana Supe to discuss all the various options, including those generated by GBBN, and decision affecting data to be considered.

09/01/10- Meeting with Craig Landers and Kevin Maue of DDS to discuss programming issues and schemes for possible relocation to 237 WHT for their existing employees in lease facitlities.

09/09/10- Meeting with Jeff Alutto, Ralph Linne and Diana Supe to discuss variations in options to be considered including possible tenants into 237 WHT.

09/17/10- GBBN met with Ralph Linne and Diana Supe to restructure the options to be investigated for the study. A report was requested to summarize the options and all data to be considered for the approval of the options to be developed further.

10/25/10- Kick-off Meeting with Ralph Linne and Diana Supe. SOSS requested for additional Options for Jeff Alutto to review for Masterplanning Studies.

11/03/10- Meeting with Jeff Alutto, Ralph Linne and Diana Supe to review report and options documented in Partner study.

Master Plan Internalization Study Read More »

2013 GENERAL SERVICES THP

12/24/13 – SOSS Requested

01/03/13 – SOSS Submitted to County.

01/07/13 – SOSS Executed.

03/20/13 – THP met with County to review beam condition in the basement of the Administration building. Based on the initial visit an additional assessment needs to occur to determine the effect of the active deterioration on the beam. The assessment will determine the need to stabilize or repair the beam.

06/04/13 – Coroner building is reporting long term leaks in the basement under the entry slab. Bert requested THP contact Mike Jackson and determine the possible leak/scope.

06/14/13 – Coroner building – THP reviewed entry after short term heavy rain. Evidence of long term water infiltration was evident, but entry did not leak. Reported findings to County with to recommendations: water test or wait for soaking rain to determine water leak. County directed THP to wait for a soaking rain; then publish a letter of findings.
10/31/13 – THP waiting for active water infiltration in the Coroner Building to evaluate scope of work.

01/30/14 – THP plans to archive project.

2013 GENERAL SERVICES THP Read More »

2013 GENERAL SERVICES GBBN

01/16/13 – SOSS submitted.

01/23/13 – Signed SOSS returned by Bert Watts to GBBN.

12/24/12 – THP – GBBN issues permit drawings; THP documents included.

01/23/13 – GBBN confirms to Millay & Company there is to be no Mechanical Permit initiated by the Owner due to no work required unless required by the Building Department.

01/31/13 – Attended HCFD Partnership monthly partner meeting. GBBN delivers signed General Services Contract to Bert Watts.

02/28/13 – Attended HCFD Partnership monthly partner meeting. GBBN delivers CD to THP and IPM for 2013 Estimating binder.

04/25/13 – GBBN attends monthly HCFD monthly partner meeting.

05/30/13 – GBBN attends monthly Partnering Meeting.

05/30/13 – We discussed the SBE packet for new bids. If we are 0% we do not have to include the actual packet in the bid specification to save paper.

05/30/13- County requests GBBN submit payment on Alms and Doepke Building Pinnacle Engineering Invoice on the General Services SOSS,

06/26/13 – GBBN performs Website updates.

06/27/13 – GBBN attends monthly Partnering Meeting.

07/25/13 – Monthly Partnering Meeting is suspended.

08/29/13 – GBBN attends monthly Partnering Meeting.

2013 GENERAL SERVICES GBBN Read More »

2013 GENERAL SERVICES THERMALTECH

11/19/12 – SOSS submitted.

11/29/12 – SOSS Approved.

12/12/12 – TTC updated front end documents to remove Terrorist documents.

02/01/13 – TTC updated front end bid documents to remove change President to Chris Monzel.

02/12/13 – TTC & SJ updated front end documents to add the non English speaking language to the Supplemental Conditions.

02/15/13 – TTC updated font end documents to remove the SBE paperwork and language.

03/14/13 – 800 Broadway Vacuum Pumps – TTC recommends doing the following after tracking down some factory information and meeting with Process Construction: 1. Temperatures coming back in the condensate piping are high indication leak-by at the traps: Recommendation-do a full trap survey and repair dysfunctional traps. 2. Temperature in “hurling” chamber start low when system is off and then rise to 190F. The aquastat on the hurling chamber is set at 190F so this tank will quench and drain continuously when the temperature is above 190F. We changed the MUW to this unit from softener water to standard city water because it is typically drained upon use. There is no need to use soft water for this mark up. This work was already completed today when I was there. 3. The condensate pumps are on a mechanical alternator and take turns pumping condensate in the lower chamber to the DA tank for boiler feed water make-up. 4. The vacuum pumps however are lead/backup. VP-1 is always the first pump on when the system vacuum gets close to 0″HG. It provides up to 4″ HG of vacuum, if this pump cannot provide vacuum, it automatically turns on the second pump and both VP-1, VP-2 run together to provide 4″HG. The vacuum limits are between 4″ to 8″HG. 5. Please leave all four HOA switches in the Auto position at all times. 6. With this knowledge, I believe I can report the Vacuum Pump Package on the left in the boiler room is working properly. 7. The vacuum package on the right appears to have a pump seal leaking and should be repaired prior to putting back into service. 8. Please repair the building steam traps to reduce the inlet temperatures from the traps to approximately 180F. Process stated that the vacuum system must be used when the building has low loads but you may find that under high loads (32F or lower) the steam system has enough pressure to push the condensate through the system and you can turn them off the vacuum pumps-that is for your users to decide if that can be done without leaving so much condensate in the building systems.

03/26/13 – Updated Website. Sent out some new formatting rules for users.

2013 GENERAL SERVICES THERMALTECH Read More »

ROYAL GLEN PUMPING STATION Pump Station

Lead Partner: ThermalTech

10/05/12 – IBI approved 98% inspection today. MB at TEI called Steve Twehues of Duke and requested power get restored ASAP. Steve to contact IBI, get release letter, and schedule restoration of power with Steve Wessels (likely early next week). Project can then be closed out.
10/31/12 – IBI released approval. Duke energy powered the pump up, but there is no meter at this time. Duke energy is insisting that the exiting PT’s are relocated up approximately 2-3 feet on pole, they feel that this is a safety issue once the platforms are installed, they will be too close to be within reach. TTE and trades argued that this area is only accessed by “qualified personnel”, and Duke CPC agreed, but metering division is requiring that they are moved, stating that kids are thrift and can climb fences and that this is a safety issue.

08/28/13 – TE met with Steve Wessels and FD Lawrence. FDL pulled report on soft start, and determined that the soft start was starting/stopping every time that the pump ran. TE sent wiring diagram to Steve Wessels to wire a stop float and a start float.

01/24/14 – Back punchlist complete. This project is complete.

ROYAL GLEN PUMPING STATION Pump Station Read More »

2014 COST ESTIMATES

Partner: All Partners

04/25/13 – Bert reported that we are still probably doing estimates for next year but it may be later this year than most. They will handle resubmitted projects and the partners will get the new projects.

05/30/13 – BW reported that they are getting close to releasing the list to the partners but RWL has to review several items. This list may be bigger than usual if we get to do the entire list this year. This may include some work on the 20 year project.

07/08/13 – GBBN receives the “Capital Roof Plan” showing the historical replacement data and estimated pricing of the six downtown campus buildings from Tremco Roofing.

07/11/13 – GBBN submits SOSS to County for approval.

07/30/13 – GBBN receives approved SOSS from County.

07/23/13 – GBBN meets with Darnell Edwards to review elevator replacement estimating scope.

07/25/13 – GBBN meets with Joe Merkt to visit the Justice Center Roof for the roofing replacement estimate.

07/26/13 – GBBN meets with Mike Florimonte to visit the CAB and 230 WHT Law Center Roofs for the roof replacement estimates.

08/08/13 – GBBN meets with Aluminum Resources to discuss the Window Replacement estimates for the six downtown campus buildings.

08/09/13 – City of Cincinnati Elevator Inspection Department responds with Elevator Code Requirements applicable to the 800 Broadway Elevator Equipment Replacement.

08/10/13 – Kone Elevators responds with Estimating data to GBBN for the 800 Broadway Elevator Equipment Replacement. Existing equipment is Montgomery-Kone.

08/13/13 – GBBN meets with Maria Karvelas to discuss the 230 WHT Pre-Trial Estimating Scope.

08/15/13 – GBBN sends preliminary plans to Maria Karvelas for review.

08/16/13 – Maria Karvelas indicates preliminary drawings for the Pre-Trial estimate meet the requirements.

08/21/13 – GBBN receives pricing back from Seeger Glass for the replacement of the Justice Center High Security Windows.

08/26/13 – GBBN completes all estimating into Archibus.

08/28/13 – TEI reviewed combined estimates and made minor changes.

09/03/13 – GBBN contacts ARC to notify of impending printing requirements within the next two to three weeks.

07/08/13 – County provided list of project estimates for 2014.

07/17/13 – THP submitted SOSS for review.

08/08/13 – County approved SOSS.

08/27/13 – THP completed structural estimates and entry into Archibus.

2014 COST ESTIMATES Read More »

BOARD OF ELECTIONS ADA Ramp Entrance

Lead Partner: GBBN

12/07/12 – THP 824 ADA upgrade project requested from the County. THP to provide structural services for entry ramp. Building Owner forwards existing PDF files of building floor plans.

12/08/12 – GBBN- issued SOSS to Hamilton County.

12/10/12 – GBBN, THP and TEI kick-off meeting and building tour.

12/12/12 – Existing hard copies of original building drawings received from Owner. ARC creates electronic copies for GBBN who distributes to TEI and THP.

12/13/12 – GBBN receives signed SOSS from Hamilton County.

12/14/12 – THP – THP issued SOSS to Hamilton County.

12/17/12 – GBBN meets with Building Owner and Contractor to discuss scope and walk existing building.

12/18/12 – THP – County executed THP SOSS. Building Contractor sends Otis Elevator ADA upgrade estimate to GBBN.

12/18/12 – GBBN sends ADA handicap access ramp layout to TEI and THP. CUH added by TEI and steel structure added by THP.

12/19/12 – Meeting with BOE staff that changes scope of work to include Lobby lift not ramp, no 2nd or 3rd floor restroom renovations and modified 3rd Floor renovations. Drawings generated by GBBN and circulated to BOE/ Facilities and Building Owner/Contactor.

12/19/12 – THP entry scope modified to allow for lift in lobby vs. constructing a room with a ramp adjacent to the entry.

12/20/12 – Ralph Linne notifies GBBN to proceed with generation of construction documents based on Building Owner original scope drawings.

12/21/12 – Small changes request to new scope drawings on the3rf Floor Office Area. Changes made by GBBN and sent to BOE. BOE signed off on new scope drawings.

12/28/12 – Final pricing and scope drawings sent to Millay & Company by GBBN.

01/02/13 – GBBN forwards new card reader lockset to BOE for approval.

01/04/13 – Ralph Linne notifies GBBN to proceed with amended scope from original SOSS per BOE Staff requests. GBBN sends approval to commence to TEI/THP. GBBN calls City Transportation and Planning to ask about handicap parking space in front of building. Left voice mail. No return call ever received.

01/07/13 – GBBN and TEI perform reflected ceiling field verification.

01/08/13 – GBBN meets with Midwest Accessibility Products to discuss details on lift installation and code approval.

01/12/13 – Ralph Linne confirms Prevailing Wage Rates required in specifications for contractor work on this project.

01/14/13 – Millay & Company confirms storefront replacement to be from existing horizontal door header and down. Existing transoms to remain.

01/15/13 – TEI sends stamped and sealed drawings to GBBN for permitting.

01/16/13 – THP sends stamped and sealed drawings to GBBN for permitting.

01/16/13 – GBBN notifies Millay& Company that stamped drawings, electronic CD and permit application available for pick-up at GBBN offices. Millay & Company requests electronic drawing files sent for review. GBBN complies.

01/21/13 – Millay & Company pick-up drawings from GBBN offices.

02/20/13 – Milay & Company sends a copy of the City of Cincinnati Permit Center building application response letter to GBBN. Most issues deal with existing building conditions.

02/22/13 – GBBN contacts Norwood Hardware about response letter issue on access control

02/25/13 – TEI reports findings concerning existing outside air repairs by building owner and test results from TEI research on existing units.

03/13/13 – Millay & Company receives letter from The City of Cincinnati Permit Center. Two items require further information for building permit approval.

03/14/13 – GBBN issues directive to BOE and Building Owner about front door over-swinging existing steps as code violation that must be addressed.

03/25/13 – GBBN receives return call from Plans Examiner with additional information concerning front door potential solution.

03/26/13 – The Building Owner and BOE agree upon GBBN Scheme B solution for addressing front entrance existing code violation solution.

04/12/13 – GBBN submits City of Cincinnati Permit Center requested Response letter and drawing corrections.

04/19/13 – City of Cincinnati Plans Examiner requests Mechanical Permit drawing for submission for earlier Mechanical Permit.

04/23/13 – TEI delivers stamped and signed Mechanical Drawing to GBBN for submittal to the City Permit Center.

08/22/13 – GBBN and THP attend meeting with Millay and Company to discuss structural coordination of steel support steel under the existing Lobby for lift elevator installation.

BOARD OF ELECTIONS ADA Ramp Entrance Read More »

2015 20-YEAR PROJECT ESTIMATES – ThermalTech

Lead Partner: TTE

09/17/14 – SOSS submitted.

09/26/14 – Prep work started for these estimates. Waiting on Administrator approvals.

10/29/14 – THP completed initial field work and estimates. THP entering data into Archibus.

12/12/14 – BW called with an SOSS update. This project is approved for work at a new SOSS. TTC marked approved and gave Becky the PO for future billing. Coroners office 20 Year cost to be added to scope.

01/19/15 – All 20 year estimates are complete. TTE coordinate with THP and GBBN for roof estimate at Coroners Office to complete the entire list.

01/21/15 – GBBN reported that Coroner’s Roof Estimate was complete.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

2015 20-YEAR PROJECT ESTIMATES – ThermalTech Read More »

2015 PROJECT ESTIMATES GBBN (20-Year and 2015)

Lead Partner: GBBN

0717/14 – Bert Watts sends email to partner with initial listing of projects.

07/18/14 – GBBN inquires about 20/30 year projects, cost of living increases and approaches for delivery of these estimates. Bert Watts responds to GBBN.

07/21/14 – Bert Watts responds to questions via email and deliverable date.

07/22/14 – THP initials email and spreadsheet for discussion on lead partner roles in shared project estimates. GBBN responds back to THP.

07/29/14 – GBBN informs ARC Reprographics of probable schedule for deliverables of printing and binder assembly.

10/07/14- GBBN visits Burlington Garage and completes roof replacement estimate.

10/09/14- GBBN completes all 20-year Capital Improvement Estimates.

10/17/14- GBBN coordinates with Bert Watts on scope for the Technology Estimates at the Courthouse and Justice Center.

10/23/14- GBBN completes all 2015 Project Estimates including LEED Silver Estimates.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

03/22/15 – GBBN picks up empty binders from Facilities department for pickup by ARC Reprographics.

03/24/15 – ARC Reprographics picks up empty binders from GBBN for assembling final volumes of Project Request Estimating Volume Sets.

2015 PROJECT ESTIMATES GBBN (20-Year and 2015) Read More »

ADA Building Assessments

Partner: GBBN

05/04/11 – Bert Watts notified GBBN of prospective project via email.

05/19/11 – GBBN attended the SWOBOA seminar in new ADA requirements.

06/16/11 – Bert Watts indicated this Project Request should be broken into eight (8) separate SOSS’s based on each of the separate buildings. See the SOSS’s F045 through F052 below.

02/12/12 – Otis Elevator declines to assist GBBN in Elevator Assessment due to liability reasons. Suggests local consultant for assistance.

08/21/12 – GBBN completes last ADA Assessment Report for the Courthouse.

08/28/12 – GBBN begins estimating portion of Assessment Reports.

08/24/13 – GBBN completes estimating impacts of ADA Assessment findings on each building.

02/26/14 – Assessment report has now been fully reviewed and finalized. The cost estimate component is now in the preliminary stage of completion.

ADA Building Assessments Read More »

BURLINGTON RD GARAGE Damaged Wall Panel Replacement

Lead Partner: GBBN

10/14/14 – GBBN contacts Metallic Building Company about information on original pre-engineered building fabrication. Voice Mail is left.

10/18/14 – Project manual cover from original building construction sent to Metallic Building Company

02/24/15 – County requested a full letter report and authorized additional field work.

10/24/14 – GBBN contacts Metallic Building Company about information on original pre-engineered building fabrication. Voice Mail is left.

11/18/14 – GBBN contacts Metallic Building Company about information on original pre-engineered building color samples

11/25/14 – County Engineers reported existing overhead door stuck and has been closed temporarily not to be used until repairs completed.

12/15/14 – Metallic Building Company delivers quote for replacement part list to GBBN.

12/26/14 – GBBN authors and delivers SOSS to Bert Watts.

02/25/15 – Bert Watts emails approved SOSS and Purchase Order to commence work.

03/13/15 – GBBN attends Owner Review Meeting to review bid package documents.

03/13/15 – GBBN issues informational requests to five (5) selected bidders for project.

03/17/15 – GBBN sends invitations to Bid to all five (5) selected bidders. Electronic copies of documents included in email.

03/24/15 – GBBN holds Pre-Bid Meeting at Offices of County Engineers’ Burlington Road Garage. Hard copies of bid drawings and specifications handed out to potential bidders and owner.

03/25/15 – John Nester forwards scope quote from Overhead Door Company for overhead door repairs.

04/02/15 – Bids received and bid tabulation compiled for Facilities Department. GBBN commences interviews with those bidders submitting bids.

04/03/15 – GBBN forwards Recommendation Letter to Facilities for lowest and responsible bidder.

04/03/15 – Hamilton County approves recommendation and instructs GBBN to author contract to Century Construction Inc.

04/03/15 – GBBN hand delivers hard copies of AIA contract to Facilities Department.

04/07/15 – Century Construction delivers signed copy of Safety Receipt Form to Facilities Department.

04/10/15 – GBBN receives color samples chips from Century requiring approval.

04/13/15 – GBBN visits building and approves color samples from manufacturer and sends approved submittals to Century.

04/21/15 – GBBN receives Schedule of Values from Century, via Facilities Department.

04/29/15 – Pre-Construction Meeting held at site. Signed and executed contract hand delivered to Century from the Facilities Department. This date established as the contract commencement date.

05/15/15 – Century reports all construction work is completed. Facilities performs site inspection and punch list. One item, caulking bead at overhead door jamb is required.

05/19/15 – Facilities performs site inspection back punch list. The one item, caulking bead, has been installed as requested.

05/20/15 – GBBN signs first/final Application for Payment.

05/26/15 – GBBN sends email to Century requesting all close-out documents be processed and executed.

06/03/15 – Change Order #1 for additional signage scope, authored by GBBN and sent to Century for signatures.

06/15/15 – GBBN receives close out documents from Century Construction.

06/16/15 – GBBN receives executed Change Order #1.

06/16/15 – GBBN receives Application for Payment #0002 from Century but without Change Order #1 included. Century to revise and sent to GBBN once project change order work is completed.

07/20/15 – GBBN receives Application for Payment #0002 with Chan ge Order #1 included. GBBN signs and delivers to Facilities Department.

07/20/15 – Century Construction announces the change order signage has been installed on the building facade. John Nester confirms the work has been completed to the User Group’s satisfaction.

BURLINGTON RD GARAGE Damaged Wall Panel Replacement Read More »

2015 Electric Deregulation Bid

12/11/14 – Bert requested new SOSS this week for several end of year projects including A&D General Service, BW General Service, and 2015 Dereg Services.

03/31/15 – TTC requested updated account numbers for the Elec Dereg project from all clients for the 2015 bid.

04/01/15 – Greg Gelhausen replied to my account number request and wants to add one account to the bid. TTE said no problem.

04/14/15 – ITB 010-15 has been assigned to this project.

04/15/15 – TTE requested billing data from Duke on all accounts included in this bid.

04/20/15 – David Hisser returned all billing data to TTE for Calendar Year 2014.

05/25/15 – First Draft should be ready this week for Ralph and Tony to review and approve.

06/24/15 – Project is out for bid. Addendum 1 has been sent out. Addendum 2 is being prepared. We have 4 bidders registered.

07/16/15 – Dynegy contract approved for all four departments. Service starts in Jan 2016.

08/26/15 – Dynegy offered all Hamilton County employees a Preferred Discount plan on home electricity through 2015 or 2017.

2015 Electric Deregulation Bid Read More »

2016 Project Request Estimating

05/16/15 – County requested SOSS from Partners.

05/18/15 – Bert Watts forwards email with “List of Projects by Partner” to all partners.

05/26/15 – GBBN hand delivers SOSS to Bert Watts.

05/29/15 – THP anticipates issuing SOSS.

06/02/15 – THP issued SOSS

06/05/15 – County executed SOSS for THP

06/24/15 – ThermalTech is complete with all but 3 estimates which are to be worked on tomorrow. Bert added #1824 for 800 Broadway Emergency Generator to TEI scope today. THP completed estimates and data entry into Archibus.

06/25/15 – GBBN completed with all but four estimates. ADA/Title II/III Projects Request Estimates are ongoing. Bert said that all projects must be done by 6/25 so he can make the early July deadline for the County.

07/20/15 – Facilities Department sends binder summary documents to GBBN for printing. GBBN informs ARC of the impending printing schedule.

08/26/15 – A call to ARC Reprographics confirmed the binder printing and assembly is nearly complete. ARC expects to deliver the binders to GBBN on Monday August 31st right on schedule.

08/31/15 – ARC Reprographics delivers all binders and existing documents to GBBN Offices.

09/01/15 – GBBN delivers Hamilton County copies of binders to Facilities Department.

2016 Project Request Estimating Read More »

Fire Alarm & Sprinkler Testing

Partner: ThermalTech

06/24/15 – Project is out for bid. Addendum 1 has been sent out. Addendum 2 is being prepared. We have 4 bidders registered.

07/29/15 – Two day prebids complete. Add01 is issued. Add02 will be issued tomorrow. Bid opening on schedule for August 27.

08/27/15 – Bid opening scheduled for today. 2 Addendums issued total on this project.

09/23/15 – Tony selected SA Comunale form base bid initial term as the recommended bidder for this project. ThermalTech to author the contract for Facilities.

10/28/15 – Contracts approved. Project can be archived.

Fire Alarm & Sprinkler Testing Read More »

Emergency Generator PM Bid

02/24/16 – Tony called and said that this project and PO are approved. Bid in March, Award in April, current contract runs out in May.

03/30/16 – Barth has made progress on the specifications they are about 90% complete. We are ready to get dates and an ITB and for Owner review.

04/26/16 – Project manual is ready. Date of Issuance will be 4/28/16. Bid Opening 5/26/16.

04/27/16 – Bid package sent to purchasing on 04/26/16. Pending bidding process.

05/25/16 – Bids open tomorrow. Two Addendums on project so far. All seems to be going well.

06/17/16 – Bids opened and there were anomalies. Tony to get information to ThermalTech as to which bidder each of the user groups has selected (Facilities, Cell Towers, Engineers).

06/27/16 – TTC to write a contract for Cummins for the Facility project. OK to share this contract with other departments if they need this. I told Tony this would be done last week, I will try to finish today.

07/18/16 – Tony is discussing with Kerry and is trying to stick with Cummins for the this contract. Kerry questioned the Alternate no bids by Cummins as legitimated on this job.

07/22/16 – Kerry and JoAnn and Tony are discussing rebidding this project due to Cummins not submitted Alternate bids for years 4 & 5.

07/25/16 – Talked to Tony and Gina today about the Alternate items in the Egen bid and we are going to rebid this project and we have change front ends to the standard county non-prevailing wage front end document and change Alternates to Optional Years. New ITB is 059-16.

07/28/16 – Talked to Tony and we are going to rebid all departments. I discussed a small SOSS to just pay for the the hours of this bid. We have a new ITB but no bid schedule yet.

08/03/16 – Tony said he approved my SOSS-A for rebidding this work. TTC to proceed.

08/25/16 – Egen PM Rebid sent out for bidding.

09/02/16 – No substantial questions on rebid yet. Bid opening scheduled for 9/8/16.

09/08/16 – Bid opening is today. Results to follow.

09/23/16 – IC won the second bid but didn’t include any battery replacement in year three. After several emails and reviews with Purchasing and the Prosecutors department, they are going to let their bid stand if they provide the battery replacements in year three.

10/25/16 – Post bid and Pre-Award meeting was held last Friday. Everything seems to be in order and TEI will write the contract for IAC today.

11/10/16 – All three revised contracts sent to Tony today for use on the Rebid work. IAC is the new vendor.

Emergency Generator PM Bid Read More »

Energy Star Validations

09/02/16 – Buildings should be ready for certification after August bills are entered in late September. ThermalTech to draft SOSS for each building for approval.

10/14/16 – All fieldwork is complete for the certifications.

10/18/16 – TTC has reviewed all the SEP and found most to be compliant. The Courthouse requires some changes prior to submitting to the EPA. TTC contacted Tony Matre to discuss and make changes.

10/19/16 – TTC to meet Dave Johnson on site to reocver steam usage data for Courthouse Energy Star.

10/21/16 – These buildings have, 230,250,800,Admin, A&D have been uploaded to Energy Star. The Courthouse is not ready for SEP yet until we work out some occupancy issues that TEI is flagging as potential issues.

10/25/16 – TTC created a new SEP for the Courthouse with the updated numbers agreed upon between Tony and Terry. TEI will take to Ralph for signing on Thursday and hopefully upload to Estar on Friday.

11/10/16 – All six buildings have been submitted. Five buildings have been approved. We are waiting on the Courthouse approval at this time.

Energy Star Validations Read More »

230 – Humidification in Rooftop Unit

04/22/05 – TTC faxed over a letter stating the deficiencies of Application # 01 on this project. All final paperwork is missing.

03/25/05 – TTC completed punchlist on job. There are no items to fix. Geiler submitted final pay application without any final paperwork. TE will ask for closeout documents.

02/25/05 – TTC asked Geiler for update and if they are ready for TE to punchlist this project.

02/11/05 – TTC talked to MF today. Geiler has the piping complete. The insulation is on the piping now. TTC will perform the punchlist next week on Monday or Tuesday.

02/08/05 – TTC visited the site today with Geiler and MF. Geiler should be wrapping up by end of week. Systems are online. Insulation needs to be completed. Geiler is in cleanup stages of piping work. TE to do punchlist within a week. Valve, steam and humidity control appear to be working.

02/02/05 – TE talked to Geiler today. They will be off the job for a couple of days. They have to soak some unions they are having trouble disassembling for re-use. They will be back next Monday for sure if not earlier (I think Bob wants to stop down to soak the unions tomorrow). Elevator and space access issues have been resolved. We were original trying to finish by 02/07 but I believe it will be at least 02/14 before the changes are complete.

02/01/05 – Geiler has started the project during the evening schedule. TE to follow up the MF this week for progress.

01/26/05 – Geiler delivered tools and piping, but wont’ start project until Monday 01/31/05.

01/25/05 – TE and Mike F. walked the project with Bob Burlege of Geiler. We feel as though they won’t be able to start the project unit Wednesday per Bob’s comments but it could be later than that. We are planning on shutting down the steam once in the evening to weld the thread-o-lets on to each header. Then add an isolation valve to shutdown each header and work on each side independently, keeping the building without humidification to a minimum. The pipe machine will be setup on the dock. Piping will be hauled in the elevator. The 230 staff will stay with Geiler the first night to ensure the boiler plant and steam come back online properly. MF will show Geiler how to shutdown and lockout/tagout the AHU’s when working. 120V welder must be used.

01/17/05 – Submittals received by TE. Walk through scheduled for Jan 24, 3:30 p.m. provided that TE approve the control valve submittals.

01/11/05 – Pre Construction Mtg Complete. Geiler projects this to be a 2 week job maximum. They will begin work and stay on site to complete work throughout the project. Pre Construction Notes added below.

09/29/04 – Original Bid Documents have arrived and TE sent to County via UPS on 09/29/04 for approval.

09/23/04 – TE contacted contractor and we are awaiting original bid documents to submit with final contract (3 copies).

09/20/04 – Contract written. Awaiting for TTC to approve and deliver.

09/13/04 – Bids are compiled. Geiler is low bidder. County please advise how to proceed.

230 – Humidification in Rooftop Unit Read More »

230 – Ninth Floor Microfiche Project

03/14/06 – Bill Scholl and Mike Florimonte have both reported that the systems are working great and permits have been approved. This project is being archived at the end of this week.

01/10/06 – HVAC has work above Julie area’s almost complete. They have scheduled an HVAC inspection with Steve Ossege in the coming days. Exhaust was hard to get routed but they are almost complete.

12/28/05 – The microfiche permit was picked up and emailed down to the County approved for use. TE paid and will reimburse the cost to the County.

12/14/05 – TTC setup a meeting for THP to review the space ceiling construction to approve the ductwork hanging method on this job for 12/15. Aaron Bennett will be contacting Mike Florimonte for access to the building. MF reported that the piping, boxes and louvers are nearly installed so far.

12/09/05 – TTC applied for the permit today at the City. The permit number is 2005P09839. It cost $75 to the application fee today and the remainder will be paid when we pick up the permit. All of this cost is a reimbursable cost to the owner on this project for this work.12/02/05 – County trades can’t put the ductwork in as designed on the plans. MF is going to inspect the above ceiling layout and call TTC with details. TTC will stop by the building and give direction as to the best way to proceed to finish the job. TTC informed Tony of the plan. Terry contacted THP by email to verify ductwork loading won’t overstress the ceiling arrangement.

12/05/05 – Terry meet HVAC trades on site to discuss ductwork routing and relocating light fixtures on this job. It was decided the best and easiest way to fit the ductwork into the room was to rotate the lights 90 degrees and remove the remaining light that is interfering with the light fixture. Carpenters will have to do some ceiling work to patch and paint the areas that are affected by the ductwork and fan supports.

11/29/05 – HVAC called with questions about moving the VAV box in Julie’s office because it was interfering with new ductwork. TE said this was fine. HVAC called with a question about framing the fire dampers in one big angle frame and TTC said this was fine also. In email correspondences today, we believe all issues are up to date and the work in on track.

11/21/05 – TE and the County met at the site to discuss Sam’s HVAC design and coordinate with the tenant and trades for making this work out. Everyone was in agreement that if we could bring both ducts into one corner and just create a matching column in Linda’s office that would be fine. The people in attendance were Mark Perry, Tony Matre, TTC, SRB, MS, Dave S, Bill S, Jim E, Ernie, Mike F, Paul and Jerry.

11/16/05 – TTC and Tony discussed the bidding out of this project and the method in which the money and trades would do the work on this project. Wayne would like more controls11/15/05 – Review drawings were sent to the County today. TE would like to get comments back about this job as the County’s convenience.

11/10/05 – Wayne called and said that the draft design is OK and to proceed with a permit set of drawings, so trades can do the work. He will also contact TE when he has set up a Archibus job number, so we can enter a cost estimate.

11/10/05 – Wayne called and said that he would like trades to do the work. He said that he would check with Mike Florimonte to see if draft design is OK. After final client approval, TE will then put together a drawing set for trades.

11/04/05 – TE sent Mike Florimonte a draft of the HVAC layout to see if Manager of that area is OK with design. Design included exposed ductwork in the Vault to avoid redoing the ceiling, to allow for concealed ductwork.

11/02/05 – TE is putting final design together. Sam and Mike will be making a field trip down to the building on Friday to set routing and check clearances.

10/13/05 – TE and CR met with the client to finalize building and design standards for this project. CR has to submit an SOSS. The equipment will be in the building in about 2 months for this job. TE must do the design immediately for bidding.

08/30/05 – TTC received installation manual from vendor in San Diego. TTC sent pdf to County for their use. Heat and Electrical requirements were provided by vendor. TTC got many other calls from salesmen at Anacomp who because ThermalTech was inquiring believe they were somehow being left out of the purchase loop of the equipment. TTC assured them that the County is in control of purchasing the unit and ThermalTech was only designing the room that the equipment when and if purchased would reside in.

08/25/05 – TTC contacted manufacturer today to collect engineering information on unit for installation including btuh rejection, power req’s, exhaust req’s and mfgr’s installation instructions. I had to leave a message with their main office.

08/22/05 – MF called to say that after talking with some people, the belief is that the vault walls are reinforced concrete and not just metal stud walls. TTC and MF talked about airflows in the room and the floor and TTC believes that the design should most likely be to add one separate VAV box for the microfiche machine and exhaust the entire room. The machine should most likely go into the vault area where the room can be separated from the general airflow of the space.

08/19/05 – TA & TTC met Tony on site for field work.

230 – Ninth Floor Microfiche Project Read More »

230 East 9th Street Electric Device Study

01/10/07 – This project is complete and archived on 01/10/07

08/18/06 – Drawings have been delivered to Hamilton County Facilities. There are no open issues on this project.

06/14/06 – Close-out meeting; no open issues. All work by Queen City has been completed. I will be working on getting the drawings completed within the next several weeks and send (3) full sized sets to Hamilton County Facilities (Attn: Bert Watts, Jim Eby, Mike Florimonte). Queen City presented (2) binders, each with copies of the old and new panel schedules. On the new panel schedules the items listed in bold have been verified; the items listed in normal type are transferred over from the old schedules. The binder also includes diagrams of the MCC’s and Switchgear. A CD was also provided which contains all of the new panel schedules in Excel format.

11/15/05 – Contracts have been submitted.

230 East 9th Street Electric Device Study Read More »

230 – Boiler Stack Study

Journal:

03/05/08 – TTC and Tony figured out the billing issues and TTC sent an email to Grady on how to bill for extra services. The actual project is complete. The County has to fix its own PO to pay Triton but TEI work is complete on this project.

01/25/08 – Tony and I talked today about closeout on this project. Grady is to bill the County the remaining balance as a change order to this job. I will write a change order to match the total amount owed to Triton on this job. The County has a PO invoicing issue on this job (JC bill to this PO).

11/16/07 – TTC talked to Mike F today about project status and sent AKM the following email:

The summer boiler flue temperatures are still no where near 310 F so the fix worked to make things better but we are still probably going to have condensation issues.

The winter boilers are on now and they are slightly better also but we are still not getting 310 F at the outlet of the boiler stack. I told Mike that we should re-smoke test the boiler stack just like we did at the start of the project to see if any drafts are still cooling the boiler stack down as the flue gasses go up.

Mike believes that Triton did a pretty good job buttoning everything on the boiler stack from the job that we bid out and the extra work that you had them do on T&M inside the building. We just aren’t getting as good as results as we would have liked.

The summer boiler is slightly over 2,000,000 btuh which means it would take 4 of the Knight boilers to replace it and meet the same load. We could do this if it was the only problem you still had. The large winter boilers are 5mil btuh so those cannot be replaced by these hot water boilers so we are still kind of faced with some of the same problems with temperatures that you have faced from the beginning in that the outlet temperature at the top of the boiler stack is under 310 F.

and told the County that when they were ready to take the next step to let ThermalTech know and we can help with the design or problem solving.

05/22/07 – Triton submitted their final payapp for the project. There is a $980- change order for the extra camera work. This increases the contract amount and TEI needs approval from the County to pay that. Please advise.

05/14/07 – TEI contacted Triton for closeout documents. Grady said they would send them in ASAP. TEI will return a video copy of the boiler stack video to Grady to closeout the project. TEI has been in contact with MF about the type of brick to replace in the chimney wall to maintain integrity and this would be solid lightweight concrete block according to Spencer at Cole Russell. This project is ready to archive. 12/04/06 – TTC questioned the use of the full allowance today ($5000) and requested an itemized breakdown from Triton for the work completed. The dwgs ask for the the wall to be built by the contractor but that has not been completed to date. The additional work that TEI is aware of is sealing the upper stack and the camera record of the interior. TEI asked for the requested change order to seal the outer stack to be taken from the allowance not as a change order.

11/30/06 – TTC asked about writing a change order to the project for Triton to do the stack sealant work. The project itself is complete. We are moving into the next phase for 2007 where we will address insulation the stack in some way to keep air from overcooling the inner shell. The County is going to open up the wall sections to allow Triton to patch the outer wall of the boiler stack. This can happen right away if the PO gets approved for Tony. TTC asked the County for an update today.

11/13/06 – A lot has happened since the last entry to which i will summarize. Triton has been on site and finished the work. A camera was dropped down between the stacks for a record of how they were built. We discovered that the outer shell had 3 large rectangles removed where spaces were welded to the inner stack. The stack was not support to the outside wall as originally intended. We believe these holes are contributing to the excessive draft up the stack causing a high cooling effect on the boiler flue gas. We instructed Triton to seal the top of the outer stack to the inner stack with a metal seal and put the breeching cover back on seal it air tight with caulk. In the basement Triton sealed the inner stack against the outer stack where the new stack enters the side of the old stack. They did this with steel plates and welds. The temperature sensor is installed and monitoring outlet temperatures and we can only see a 2-degree rise in temperature with the stack being sealed top and bottom. This is not surprising since the are three gaping holes in the outer stack wall on the 4th, 8th and 12th floors that may still be an escape route for air movement. As this is the first stage of the fix it plan being used for investigation as well, we are formulating the second stage now. We want Triton to patch the remaining three holes by change order if necessary. In step two we may try to fill the interstitial space between the stacks with concrete and create a permanent insulation space between the two stacks and this way when the inner stacks rusts out, the concrete stack will remain providing a permanent stack for a long time. We have to get a structural involved at that point to help check the loads on the building.

08/28/06 – We held a construction meeting to get a new handle on where the project stands and to review the R&P chimney stack report. Grady brought one copy of the report and Tony asked for 3 copies to be made and given to the County. The report has basically found that the stack is in FAIR condition. The stack was basically constructed in two different segments, the bottom 130 ft and the top 40 ft. In reviewing the original report from 2001 and the new report from 2006 there is considerable degradation from low temperature condensation and corrosion inside the stack. Photographic evidence was provided in the report to support this claim. The wall thicknesses have decreased and will continue to decrease and the new temperature outlet sensor installed in phase 1 of this project has further provided trending and data to prove that decent outlet temperatures at the boiler flue’s in the basement are significantly reduced in their upward travel to leave the building. Mike Florimonte provided a trend that showed summer boiler leaving temperatures of over 500 F but at the outlet of the stack temperatures were only 210 F. This is a condition that will cause low temperature corrosion. R&P is recommending a spray on coating to protect the interior of the stack. Triton and ThermalTech recommend further investigation into the over cooling effect on the boiler stack. For this much temperature loss to occur, we believe it must be related to the high velocity draft witnessed around the boiler stack at a previous field trip by TE. We have scheduled a Saturday visit with Triton to set off a smoke test inside the boiler stack. We want to witness the path of the released smoke and find the air path that is causing the stack losses. In essence the space between the inner stack and out stack should be dead air space. In addition, Triton will investigate the OA paths surrounding the boiler stack to help ensure that no OA is subjected directly to the boiler stack space. Once this data is resolved, we can isolate the boiler room from the chimney stack and address other “sealant” issues with the new and old breeching. We are scheduled to meet on Sat, Sept 9th. MF will alert the building occupants. AKM requested a synopsis of or plan of attack.

06/16/06 – R&P Industrial Chimney showed up on site. At 2:17 they completed their fieldwork and reported the seems in the stack appear to be the worst off. The took a disposable camera and ultrasonic machine into the stack with them. TTC asked for them to call with a report after they packed up.

05/22/06 – Boiler stack inspection still set for June 19th. Grady is checking on controls and trending.

04/06/06 – Mike called today about getting study complete and temperature sensor in place. Grady replied that the inspection could be the middle of May. The County will need this inspection to be completed either after hours or on the weekend because of hot water reheat. TTC to review and try to find a holiday instead that may work better.

03/09/06 – Pre-construction Mtg was held and notes distributed.

01/17/06 – Wayne reported today that the Bid from Triton did not included a personal property tax statement or a ohio dept statement. TE to check and correct for Wayne.

12/13/05 – Contracts were returned for corrections. TE corrected, printed and returned to the County for submission to the commissioners.

12/01/05 – TTC found the original bids for the job (in sbu’s mailibox) and sent them on to Tony for his use. As soon as contract is approved we can have a pre-construction mtg and get the project moving.

11/08/05 – Tony authorized ThermalTech to write the contract for this work. TE will try to get it done in one day.

10/18/05 – All bids came in and contractors are calling for bid results. TTC gave to Tony and Mike on 10/20 for review. Bid Results – PDF

10/14/05 – No addendum had to be issued. Bids are due next week. TE has received a couple of “No Bids” on this project already.

09/29/05 – Final Project manuals have been created. IES information added for controls. Prebid is set for Oct 6 at 9:30 a.m. TE invited Peck, Triton, Process, Geiler, DK and Langdon to bid the project.

09/09/20/05 – TTC is reviewing Sam’s final drawing and project manual.

08/31/05 – MF reported that with their flow hood the outdoor access door when opened drew 1600 CFM with boiler make-up and exhaust running and 650 cfm with the MUA and EF off. This may contribute to extra cooling down of the boiler flue and TE is investigating welding the outer shell closed during our project. TTC cannot explain the huge draft of air up the shaft at all times

08/30/05 – TTC stopped by the site today to review an access door in the side of the building. There appears to be a huge draft from the outdoors into this access door and it apparently is going up the stack and exiting somewhere that in undetermined. This presents a problem with finalizing our design. We can still go about sealing the basement mechanical room as planned but after we are all done there may still be another step to isolating the inner/outer stacks when we are complete and re-measure the infiltration airflow. In talking with Mike, TE may give Mike the cutout for the future access door. If we cut the whole in the drywall now so we can investigate better how the inner and outer stacks are routed through the building. TTC needs to look at original report and talk to contractor about installation method. There are still unknowns about the original design that are affected an effective solution to this problem.

08/25/05 – TTC sent out final bid manual for review today to MF and AKM. Bid opening might be on 9-7-05.

07/18/05 – TE started the small project manual for bids today. TE has to create a new SOSS because the study used up the first SOSS but since so much of the design is already complete TE only wants to write the new SOSS for $2000 instead of the standard $3500 for bid and contract administration.

06/17/05 – TTC and MF discussed the report today and TTC recommended that we put a small packet together now to close up the air space around the stack. An incremental approach to fixing the problem is best. After the space is enclosed, the stack losses should be re-measured at various conditions to asses the new operating characteristics of the boiler plant. This should be done this year if possible. At the same time, a drywall access hole should be cut to inspect how stacks are anchored together. TE will wait for the County to advise.

06/16/05 – TE sent the final report to Tony and Mike for review and use. TE recommended closing off the bottom of the stack leading into the basement and re-creating a dead air space that can be used for isolation the temperature and creating a thermal barrier.

06/06/05 – TE had a meeting today to discuss recommendations. Our report will be out later this week and 2006 estimate will be estimated based on this report. We plan on discussing with Tony and Mike after Mark Miller sends final report to County. TTC and Mike discussed field findings from last week in an impromptu meeting at B-95 today.

05/24/05 – Mike called today and TTC told him that ThermalTech has not done any construction documents yet on this project and that might be due to the fact that we haven’t given Tony a final report on the condition of the stack (awaiting the re-evaluation from either HC Nutting or the other contractor that MF was going to call into survey the breeching) and TE has not provided a written report to Tony and Mike with recommendations about how to proceed. As MF and TTC discussed the situation though, we decided that if something is to be done this year before heating season, the design and SOSS must begin immediately. TTC will email AKM and ask about how to continue work on this project. TE still has $1172 left from the original SOSS that we do not need to used except to provide a written summary to AKM about our findings.

05/11/05 – TTC gave MF HC Nutting as contact for pipe thickness survey.

03/28/05 – TTC & MM met on site and went over boiler stack calcs and heat losses. Too much heat is being loss going up the stack. We need too look at insulating the stack to keep the heat higher throughout the path.

02/22/05 – TTC and MM reported that initial reports look like stack losses primarily are contributed to the low outlet temperature and condensation issues at the 230 building and not stack sizing or entrainment.

02/10/05 – TE received a signed SOSS and posted it to the website today.

02/01/05 – TTC & Mark Miller visited the site for field investigation and SOSS scope.

230 – Boiler Stack Study Read More »

250 WHT – Asbestos Study

Project Lead: GBBN

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sens list of buildings to be included in Asbestos Abatement Reporting.

02/06/12 – Pinnacle Engineering requested drawing files for the purpose of documenting findings.

02/07/12 – GBBN sent drawing files to Pinnacle Engineering in PDF form.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

01/26/13 – BRG confirms entry of ACM data into Archibus is completed.

01/28/13 – GBBN conducts spot review and confirms data entry is accurate.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

02/24/14 – GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/WebCentral is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14 – GBBN sends another email and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

8/29/14- Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications to finalize the remaining invoices to close out these projects.

250 WHT – Asbestos Study Read More »

250 WHT – Plumbing Division Upgrade

06/14/05 – Phasor turned in a new change order for Fire Alarm additional work at 250. The Change Order cost including all the additional inspections is $967.82. TE will approve and send to Diana for signing. Please return a signed copy to both ThermalTech and Phasor when complete.

06/08/05 – TTC sent final Reupert paperwork to Diana for complete project closeout. Noise issued on floor is being address by Mark Hardin.

05/11/05 – Sound issues arose from the toilet room and accompanying space being too quiet. GBBN made a field visit to investigate and the consultants gave recommendations about white noise or another exhaust fan. The County is to advise on how to proceed from here.

05/10/05 – TE emailed GBBN to advise that toilet exhaust on this project is connected to the main building toilet exhaust. If there is a problem have Tom check the main fan and if that doesn’t work, TE will measure the airflow and check the existing conditions contingent on a future request by the County.

05/02/05 – The building passed it fire alarm inspection this morning at 6:00 a.m. TTC, Jack Lamping, Darnell, Jim McFarland and Darryl Meadows were present and witnessed the test and the paperwork was signed. The City Inspector had issues with the existing system but did not hold up or not pass the test but these are issues, he wishes the County would fix because the system is technically not installed properly. Item (1) any smoke or pull device on the first floor reports as “Smoke & Pull Stations”. The inspector strongly urges that these two actuation devices be separated and report separately when in alarm. Item (2) when in alarm and the “Alarm Silence” button is pushed it disengage all the horns AND strobes on the first floor – this is against code as ONLY the horns should be disabled and the strobes should continue to flash until the system is RESET (it was shown many times during our testing periods that they are not wired properly). Item (3) They questioned the “fail-secure” status of the doors upstairs and downstairs. When the FA system is in alarm all the door holds release as they should and all the security access is disabled so that a key is required to enter the space. I confirmed with TA and MS that this is the correct operation for your building. The people inside can always egress out as there are strike bars or non locking door handles from the inside to the outside so none of that is required to change. Item (4) The first floor system is a “System Sentry” type system which was in place when Simplex received the second contract to renovate the second floor space. They did this by daisy chaining all the existing 4-wire devices through a ZAM (Zone Actuation Module) which is why they all report as the same device back at the Simplex panel. TE would recommend putting in a project right now that upgrades that existing system to 100% Simplex (which is a fully addressable system 4010 model). We estimate about a $23,700 project (30 devices @ $9000, 3000LF @ $9000, 6 ZAM’s @ $3000, Programming @ $1500, Permit and Testing @ $1200). Please advise.

04/28/05 -TE spent most of the day at the building trying to get the Simplex system working in conjunction with the System Sensor system. We tried many custom programs but in the end nothing worked perfectly. TTC has 3 ways to try to get system fixed this morning and will meet Simplex back on site to repair the system. (1) write a custom program that actually works, (2) replace the 4 smoke detectors with authentic Simplex devices, (3) add a UL listed manual reset to reset the 1st and Bsmt floors. TTC will keep DES up to date as we go through the day.

04/27/05 – The project failed the initial Fire Alarm test this morning. Not from device malfunction but the actual FA panel would not reset after receiving an alarm from a smoke head. The system was pre-tested using pull stations and reset fine on Tuesday. Because of this the City did not issue an approval. Phasor, TE and the County contacted Simplex for an emergency call into a technicians to repair or reprogram the main FA panel. Jack talked to Simplex and will be back on site as soon as they arrive today to work on the system to assist in figuring out what is going on and wrong. He believes that he was able to get the technician to understand what was happening and hopes to resolve the issue today. The inspectors agreed to come back this week to approve.

04/26/05 – Phasor bought two strobes locally and will install them today and have everything ready for tomorrow morning. Jack said it was a scramble but he found them and is ready to install. They will be ready for tomorrow’s test. At 2:48 p.m. they reported that everything is set for final FA inspection on Wed at 6:00 a.m.

04/19/05 – Final fire alarm test is scheduled for 04/27/05 at 6:00 a.m. Tom will be on hand from the County for FA issues. TE will attend as Owner’s Rep. Phasor will be EC. Copp stated that all egress issues are resolved and will be working fine for our final test.

04/15/05 – TE contacted Phasor about final completion and inspection by email to make sure everyone is ready for next week.

04/06/05 – TE and Phasor and County are coordinating final inspection details for April 25th. TE waiting on contract interior information from County before confirming

04/05/05 – Project Meeting today. Set new schedule for completion. JB Schmidt scheduled to be complete by April 15. Phasor to be work on 4/15 and 4/18-4/20. Final Inspections to be tentatively scheduled for 04/25/05. TE to contact Phasor for FA inspection coordination with JB. TE to contact Copp about schedule for plumbing space and general building space and to work on resolving software issues. County ES/Facilities to contact Sheriff’s Dept about Panic button for receptionist in ES.

03/25/05 – Reupert delivered some of the final paperwork with no payapp today. TE will contact them about this.

03/15/05 – Portions of the project have been on hold awaiting the replacement of drywall and water sealant. TE received final paperwork and O&M manuals including balance reports from Reupert. The manuals are not bound or copied. TE will copy and make sets for County use and turn them in at the end of the project with final paperwork and payapp from HVAC contractor.

01/31/05 – TE attended last Thursday’s Const Mtg. HVAC is complete. EC is nearly complete. PC is complete with working fixtures. Hot water reached the LAV in under 60 seconds. All fixtures appeared to drain properly. Security is nearly complete but Copp has some final work to do.

01/26/05 – TE faxed one copy and mailed three copies of the Affidavit of Release of Liens to Reupert.

01/24/05 – Jamie of Reupert called TE and indicated that she was preparing final document packet but did not know where to find the Affidavit of Release of Liens forms. TE to mail the Affidavit of Release of Liens to Reupert.

01/18/05 – TTC sent Reupert their punchlist item (balance report) and asked for their O&M’s.

12/27/04 – TTC stopped by the building to coordinate lighting layout with Jack Lamping. Some of the HVAC piping is too close to the ceiling grid and the deep parabolics don’t fit into the grid and below the ductwork and 3-way heating piping and valves. We remedied this situation by moving some lights over a grid space or 2. TTC has a copy of the new locations for as-built purposes. TTC believes the new layout will provide sufficient lighting levels and be a workable layout for the building occupants. The only outstanding issue with the lighting at this point is that the light nearest the column near the restroom can either be swapped out with a shallower fixture like the ones slated for the storage room and the lens be replaced with a paracube or (2) 2×2 fixtures can be used instead of (1) 2×4 fixture. The former would cost the project little or no money, the ladder may cost $200 – $300 out of the remaining allowance. We should have an a final answer later today.

12/20/04 – Ken Reupert out of the office, Jamie will have both of the Affidavit of Original or Subcontractors sent to ThermalTech today or tomorrow (12/21/04).

12/09/04 – Reupert revised Pay Applications 1 & 2 received in the mail. Voice message left for Ken Reupert to disregard earlier message and that the Pay Application will be held for the “Affidavit of Original or Subcontractor” form to be submitted.

12/09/04 – Reupert Pay Applications 1 & 2 Voided due to $600.00 allowance shown on application as a Change Order. Voice message left for Ken Reupert explaining that the Applications were incorrect and will need to be revised.

12/03/04 – TTC talked to Reupert today. All the above ceiling ductwork is complete at this point. The 3-way valves are all piped in. The controls on on schedule at this point. The GC will contact the MC when the diffusers and final connections are ready. The MC has to attach some angles around the fire dampers to meet code and should take of that work next week.

11/22/04 – Reupert called today to discuss the 3-way valves ordered on this project via the submittal change. TE instructed them to pipe the valves in as 3-way valves and use up to $1250 of the allowance for this work and to make the necessary scheduling changes to make this happen. Per our submittals to the MC and CC we changed the 2-way valves to 3-way because this building has constant speed pumps and to prevent dead heading the heating hot water system will require 3-way valves in most installs.

11/18/04 – Reupert called to ask for a size change in the return grill. TE approved a 24 x 12 return opening above the ceiling for this project. TE to verify on site at today’s meeting all their request

10/27/04 – Reupert submitted a $600 allowance request to rework the piping at the bulkhead pursuant to our last construction meeting. TE approved the request from the $2500 mechanical allowance for this project, new balance $1900.

Change order request in approved for security change order and is the amount is not being subtracted from the allowance. TEI issued a revised sketch that corrected the access controlled door locations.

10/21/04 – TE contacted Reupert about missing today’s construction mtg, making the next meeting for sure, submitting their schedule of values, change order pricing for relocating piping and VAV box submittals. Everything is in the works. Reupert is going to send us the schedule, the VAV boxes are already in their shop (we now have to approve them (don’t worry they will be fine)), they will begin working on the change order request.

10/13/04 – AIA Change Order for $1,854.46 mailed to Phasor

10/11/04 – The Plumbing Permit Number is: # 2004P07058.

10/08/04 – TEI to prepare electrical bulletin #1 for 1854.36

10/07/04 – GBBN provided the permit number for the project: The permit number is as follows: #2004P05650

10/05/04 – TEI received devices submittal via email from Phasor.

10/05/04 – DES confirmed that TE sent Lisa the stamped drawings for permit. TE sent them on Thursday 10/07/04.

09/29/04 – Jeanette provided a dimensioned drawing for HamCo plumbing to use for this project – TE reviewed and approved for use, TE to pickup plumbing fixtures from Bo for approval, TE to provide stamped drawings for permit use to Lisa, TE to coordinate revised security (Copp to upgrade entire building including 2 new doors) and TE to write change order for this work to Phasor, Reupert was not at meeting and TTC to confirm that Reupert will be at next meeting, TE requested that GBBN reschedule Oct 20 mtg as it conflicts with CH Archive mtg.

09/20/04 – Ben has asked TTC to coordinate water closet locations with Bo Blank.

09/14/04 – Copp is providing a price to upgrade the whole 250 building, this has to be coordinated through TE and Phasor since our electrical contractor has security money in their bid to do this work.

09/08/04 – Bo advised to remove sanitary so that Reupert can begin construction.

09/08/04 – Pre Construction Mtg completed.

09/03/04 – DES advised that contracts are approved. GBBN will setup pre-construction meeting.

09/28/04 – Lighting submittal approved 9/22/04

10/01/04 – Request for change order pricing from Reupert for Fire Damper

10/02/04 – Reupert gave a verbal price of $375 for the addition of a fire damper

250 WHT – Plumbing Division Upgrade Read More »

250 WHT – Electric Device Study

10/18/06 – Final close-out meeting was held on location. Queen City has completed all contracted work. I have the drawings and will have the information put into electronic format over the next few weeks. I also took the panel index binders. I will have all documents delivered at the same time.

09/19/06 – Construction meeting was held on location. All field work was to be completed by this afternoon. Dick Kuhn of Queen City will be in contact with me when he if finished with his circuit verification. When I have been contacted I will contact all necessary persons to set up the close-out meeting.

08/28/06 – Kick-off meeting held on location.

07/18/06 – Contracts have been submitted.

06/19/06 – Pre-bid meeting was held on location.

250 WHT – Electric Device Study Read More »

250 WHT – Security Camera Upgrade

7/31/08 – Bert reported that the project is finished and final paperwork has been received. Final payment is approved to the contractor. Broken camera has been fixed. Contractor is awaiting final payment.
07/30/08 – Project is complete. County has all final paperwork.
05/16/08 – Bert sent back changer order and payapp #3 signed by County.
05/02/08 – Stapleton has submitted all final paperwork and sent back a signed change order on this project. TEI has reviewed and approved all closeout documents on this project. They are being UPS to Bert Watts for closeout on this project. The change order has to be signed by the owner and copies sent back to TEI and Stapleton for our records.
03/06/08 – Stapleton and Copp have reached substantial completion. The translator has been installed. Remaining items on the job include: our punchlist (early next week), training for the county, programming at the sheriff’s office, Copp is going to replace one camera that is acting up.
02/08/08 – Stapleton sent the change order cost to TEI for the translator and TEI passed it along to Bert Watts for approval on this project. TEI updated the website with current CO and Allowance costs.
01/23/08 – TTC requested a const meeting for this project this Thursday or Friday.
01/22/08 – MAH met with Dick (Stapleton) and Paul (Copp) about the mounting of the exterior cameras. Copp will supply (3) corner mount brackets for $267 allowance. Stapleton will install camera mounts when they arrive (should arrive 1/23). Also discussed was the data port being included on same plate as existing phone jack in lobby, lobby camera location (NE corner and viewing doors), and location of exterior camera at rear entrance door (will be mounted on adjacent wall approximately 24″ above window to avoid washout from wallpack light fixture).
12/14/07 – Stapleton discovered that the holes in the pole bases are only 2-1/2″ and will not accommodate (3) 1″ conduits as the design calls for. Stapleton requests a $500 change order to install junction boxes in the pole bases to solve this problem. TEI agrees with this solution and the change order amount.
12/12/07 – MAH clarified for Stapleton that the control signal for the PTZ cameras was sent over the coax video cable so no additional control wiring is necessary. Also, siamese RG-59 wire with 18AWG power is acceptable for all interior and building mounted cameras. A separate coax and #12AWG power pair is required for the pole mounted cameras that is wet/direct sunlight rated. Copp Systems submittals are approved and should be sent back 12/13/07.
12/04/07 – Const Mtg #2 was held today and TEI distributed meeting minutes. Stapleton will be staring site work this Friday. Ken Edgell will advise the tenants of the 250 WHT building. Stapleton will be boring the light pole bases and conduit routes this weekend. TEI, Ken and Stapleton pick light pole locations in the field for this work.
11/29/07 – The pre construction meeting was held last week. GM typed up the meeting notes. Stapleton called with questions about submittals, dwgs and const mtg time. TEI setup another const mtg for next week with the owner and facilities. We will discuss the RFI’s about the lamp bases and base diameter. Bert sent out the list of approved employees for this project today which included Barnett, Ronald J., Eckart, Carl, Hammitt, Wayne, Leopald, Mike, Leopold, Douglas A., Stevens, Brian K. Terry Cannon emailed Stapleton to ask about Copp system background checks. Mike Huntwork approved all submittals with No Exceptions noted.
10/03/07 – TTC sent the contract for Stapleton to Bert today via City Dash with an allowance of $2500 added to the project. If acceptable, the County can begin the contract process. Stapleton won the bid with a bid of $90,586.00 + $2500 in allowance money. Our electrical plan review was approved on 09/11/2207 with an application # of CIC0703025. The contractor will now have to pay and pick this permit up when the job begins.
09/10/07 – TEI is submitting plans to IBI for plan review and permit # for this job. TEI will provide permit numbers to County for record keeping purposes when we are complete with this process. It will be the contractors responsibility to pick up and pay for the balance of the permit when one is assigned for this project.
08/27/07 – This project has been sent out for bid with hard copies to Mark Donnelly.
08/24/07 – TEI has been instructed to move forward with this project. This project is set to open for bid on 09/26/07. The pre-bid meeting has been set up for 09/11/07.
08/10/07 – A project review meeting was held at the 250 WHT building on Tuesday, August 7, 2007. Items discussed included camera locations and specifications, new light pole locations, access into building, and budget. TEI is awaiting word from the Hamilton County Facilities Department on when this project will go out to bid.
07/30/07 – The drawings and specs are completed. The package is to be sent out today. There will not be front end or ITB# for this project because construction has been postponed until next fiscal year. When TE is given the go ahead from the Hamilton County Facilities Department on this project they will put together the front end of the project manual and issue for bid at that time.
07/09/07 – TE is finalizing the design. Drawings will be turned over to Hamilton County Facilities Department when complete.
06/29/07 – At the monthly Partnering Meeting with Hamilton County it was decided that the money to perform this work would be budgeted for a 2008 project. TE was directed to complete the design and turn over the drawings to the Hamilton County Facilities Department.
06/22/07 – A new cost estimate was presented to Mark Donnelly. TE is awaiting response on whether or not to proceed with the new latest layout and additional cost.
06/15/07 – Project moving along as expected. Changes per meeting with Mark Donnelly are being incorporated and a new cost estimated is being generated.
06/08/07 – New parking lot lighting and camera layouts were presented to Mark Donnelly along with a cost estimate. TE is moving forward with this project. There are a few slight adjustments; number of new poles, location of new poles, and number of cameras. These modifications will be made and presented again to Mark Donnelly.
06/01/07 – TE will present Mark Donnelly with new parking lot lighting and camera layouts early next week. A cost estimate will be included with the new layouts.
05/22/07 – Project review meeting was held today. Various points were discussed as described in the meeting notes. TE is laying out different schemes of possible lighting and camera layouts with the points discussed in the meeting kept in mind.
05/21/07 – Meeting to review current status is schedule for May 22, 2007 with Mark Donnelly.
04/27/07 – Estimates are complete and will be forwarded to Hamilton County Facilities Department today, April 27, 2007.
04/20/07 – Estimates are near completion and should be turned over the Hamilton County Facilities Department by the end of next week, April 27 2007.
04/13/07 – TE is working on the estimates to be turned over to Hamilton County Facilities Department.
04/06/07 – Review meeting was held today, April 6, 2007. TE is to provide pricing on 2 systems and then await owner’s selection.
03/30/07 – Preliminary layouts have been presented to Hamilton County Facilities Department for review. Review meeting will be scheduled for the first week of April 2007.
03/20/07 – TE met with camera vendor. Parking lot lighting and camera layout is currently underway.
03/20/07 – Design is continuing. Parking lot lighting is under design.
03/14/07 – NR created project journal and filled in back data from previous meetings.02/14/07 – Proposed parking lot lighting and camera locations has been completed by TE. This information is awaiting review by Hamilton County Facilities Department.
02/28/07 – Foot candle readings were taken by Phil Lambing in the evening of this date.
02/27/07 – Kick-off meeting held on location by Phil Lambing of ThermalTech. Attendees include Mark Hardin and Bill Scholl of Hamilton County Facilities Department. IT was decided that TE will collect foot candle readings in the parking lot to get a good idea of what will be needed to ensure personnel safety

250 WHT – Security Camera Upgrade Read More »

250 WHT – Monitoring Room Upgrade

Current Status: Construction

03/30/11 – This project is complete. TEI finalized the HVAC permit and paid for it at the City of Cincinnati so EDI can close out this project.

03/02/11 – TTC checked on braided hose install by EDI on humidifier. Brady said they are working on this. TTC review wall mounted installation and there is no good way to clean this install up with a simple product. TTC asked EDI to closeout project and send in final payapp.

12/30/11 – TEI released the punchlist on the project today.

12/15/10 – EDI on board and working on project towards punchlist completion

250 WHT – Monitoring Room Upgrade Read More »

Scroll to Top