Hamilton County Facilities

Champlin

A&D – JFS Director’s Office Renovation

08/30/19 – Champlin submits SOSS
09/11/19 – Champlin received approved SOSS & PO.
10/31/19 – Susan is coordinating furniture selection. Project will go to bid after that.
12/02/19 – Bids received from 3 bidders. RCF is apparent low and Purchasing is processing this to move forward.
06/25/20 – Furniture on site but may not be used given retirements and Covid. Project can be archived at this time.

A&D – JFS Director’s Office Renovation Read More »

CH – 6th Floor Office Build Out

08/27/19 – County requests onsite meeting to review scope.
09/10/19 – Champlin received approved SOSS & PO.
09/17/19 – Champlin & ThermalTech site visit.
09/27/19 – Check set given to Hamilton County for approval.
10/03/19 – CDs set given to Hamilton County and issued for permit.
12/03/19 – Bulletin #01 sent to County and Triton Services.

12/31/19 – Door and hardware submittals approved and sent to Triton

01/02/20 – CO #4 signed and sent to County

02/03/20 – Champlin performed Punchlist visit

02/04/20 – Punchlist report sent to County and Triton

02/14/20 – Champlin performed Back Punch visit

02/21/20 – Backpunch report sent to County and Triton

05/15/20 – Pay app signed and returned to Triton

CH – 6th Floor Office Build Out Read More »

A&D – JFS Internal Door Replacement

06/17/19 – County requests JFS Internal Door Replacement Project Scoping Meeting
07/02/19 – Meeting with Facilities (Tony Matre, Steve Sears, Cloude Toulson, Bert, Kru and Jeff)
07/11/19 – Champlin submits SOSS
09/11/19 – Champlin received approved SOSS and PO.
09/13/19 – Champlin performs site visit to verify all office door locations to be included.
10/28/19 – Champlin performs site visit with Hardware Consultant to confirm door hardware. Hardware consulting on going.
12/10/19 – Bid set sent to county
01/07/20 – Addendum #1 sent to County
01/16/20 – 5 bids were submitted to County.
01/22/20 – Champlin met with Megen Construction.
01/27/20 – Champlin sent official recommendation to award bid to Megen Construction.
03/26/20 – Waiting on official Contract to be given to Megen to return their door submittal
04/17/20 – Scope of work reduced to egress and security doors only.
05/04/20 – Megen given contract.
05/13/20 – Zoom meeting between Champlin and Megen to discuss scope changes.
05/28/20 – Waiting on revised estimate from Megen to proceed
06/24/20 – Waiting on revised estimate from Megen to proceed
06/29/20 – Megen provided revised estimate and other pre-construction information necessary.
07/21/20 – Pre-construction meeting attended by Champlin, Megen and County to further discuss the project. still waiting on project schedule and schedule of values from Megen.
07/28/20 – Door and Frame Submittal returned to Megen.
07/31/20 – Site visit scheduled to walk through areas of additional scope.
08/07/20 – Megen sent Safety materials.
08/18/20 – Schedule of Values and Project Schedule received from Megen construction. Megen has provided construction schedule showing NTP of August 3 and completion on December 7. On site work scheduled to start October 9. Mark-up of doors to be added sent to Claude/Steve for review and confirmation prior to creating a bulletin for contractor pricing. Waiting on direction to proceed.
08/24/20 – Change order for decrease in scope sent to Megen.
09/09/20 – Add services for Thermal Tech sent to Rycca.
09/21/20 – Megen workers complete background checks. Megen visits site to confirm existing conditions
10/09/20 – Scheduled start date.
10/29/20 – Construction started. OAC meetings scheduled for every Friday through end of construction projected by Megen to be December 7th.
12/10/20 – Working on new RFI for this project. Work on answer after tomorrow’s meeting.
01/15/21 – Restarted weekly construction progress meetings.
01/25/21 – Megen provided construction completion dates as follows: Basebid 2/23/21 bulletin 2 work. 03/02/21 Bulletin 1 work 3/22/21.
01/26/21 – Champlin returned comments requesting accurate pricing for 2 potential change orders.
02/08/21 – Progress Walk-thru attended by Sam Hofmann, Randy Johnson, John Nester, Steve Terheiden, and Rycca Thacker
02/19/21 – Bulletin #03 issued for replacement of existing closer/holders. RFI approved for supplier change from Interior Supply to LaForce.
03/19/21 – First Punchlist by Sam Hofmann, Mike Murphy, Rycca Thacker, Steve Terheiden, and Steve Kenneda.
03/26/21 – Second punchlist scheduled.
04/29/21 – Final punch scheduled for 4/30.
05/07/21 – Verified operation of closer/holders with fire alarm system. (attendees include, Rycca, Steve T, Mike B, Mike M, Sam)
05/10/21 – Champlin sent Rycca contractual dates and sequence of events as a word document.
05/12/21 – Final punch by Rycca, Steve T, Mike B, Mike M, and Sam.
05/14/21 – Punch list issued to Randy and Steve K.
05/18/21 – Rycca receives invoice from Phazor for replacement of fire alarm relays. Champlin send invoice to Megen. Randy acknowledges receipt and indicates he’ll forward it to accounting for payment.
05/25/21 – Contacted Megen regarding schedule of completion of punch list items.
06/24/21 – Megen notified us remaining materials received. intend to install on June 28th.
07/28/21 – Megen issued completion date of 7/28
08/26/21 – Waiting on Medeco Cores to be delivered.
11/08/21 – Final punchlist with County and Champlin. Still waiting on Medeco Cores from Megen.
11/17/21 – Finished second half of final punchlist
11/30/21 – Sent finalized report to Megen. Gave deadline of December 31. Requested filled out responsibility columns and schedule. Have not received either
01/21/22 – Final punchlist finally received from Megen.
01/25/22 – Backpunch by Sam and Rycca.
02/10/22 – Backpunch items completed. All construction services complete.
03/31/22 – Close out documents to be complete by friday.
04/28/22 – Close out documents received from Megen. Under final review.
05/26/22 – Close out documents to be reviewed.
06/30/22 – O&M manual reviewed and returned comments to Megen. Awaiting corrections
08/25/22 – Still waiting on Payroll information.

12/15/22 – All closeout documents and payroll information received. PROJECT COMPLETE

A&D – JFS Internal Door Replacement Read More »

Champlin – General Services

02/14/19 – County invites Champlin for MSA agreement
02/21/19 – County sent MSA Contract to Champlin
03/13/19 – County sent revised MSA Contract to Champlin
03/18/19 – Champlin sent proposed revisions to MSA Contract
03/29/19 – County sent final MSA Contract
05/23/19 – General Services P.O. approved
05/30/19 – Kru and Mike from Champlin attended Monthly Partners Meeting
06/03/09 – Bert requests code interpretation for safe room locks on certain areas within the 911 Communications Center.
06/07/19 – Champlin provides 2017 OBS interpretation for safe room locks on certain areas within the 911 Communications Center
06/14/19 – Champlin provides further clarifications on 2017 OBS interpretation for safe room locks on certain areas within the 911 Communications Center
06/27/19 – Kru from Champlin attended Monthly Partners Meeting
07/31/19 – Christy from Champlin attended Monthly Partners Meeting.
08/29/19 – Kru from Champlin attended Monthly Partners Meeting and updated website.
09/26/19 – Kru from Champlin attended Monthly Partners Meeting and updated website.
10/30/19 – Champlin visited Auto Title and currently working on space layout.
12/12/20 – Mike and Sam from Champlin attended Monthly Partners Meeting and Updated website
01/02/20 – Bert reached out to Mike and Kru for CAB signage replacement
01/10/20 – Kru and Sam from Champlin visit Taft Center for potential Alley Door Upgrade
01/24/20 – Champlin reached out to multiple vendors for information on existing conditions
01/28/20 – Champlin received CAD files of CAB elevations from THP.
01/30/20 – Mike and Sam attended Monthly Partners Meeting and updated website.
01/30/20 – CAB signage project to be added to an existing facade repair job currently active at the CAB
02/04/20 – Signage drawings sent to THP to give to AFR
01/27/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
02/25/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
03/25/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
04/08/21 – Sent County options for casework refresh.
04/29/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
05/27/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
06/25/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
07/29/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
08/26/21 – Mike Murphy, Sam Hofmann attend monthly partner meeting.
10/25/21 – Final Facilities kitchenette drawings sent to County for review.
10/28/21 – Sam Hofmann attend monthly partner meeting.
12/03/21 – SOSS approved for Design and consulting services.
12/14/21- Mike Murphy, Sam Hofmann attend Monthly Partner Meeting.
01/26/21 – Mike Murphy, Sam Hofmann attend Monthly Partner Meeting.
02/09/22 – Met with County, Triton, Thermaltech and Champlin to review scope of TPC 6th Floor ceiling replacement.
03/31/22 – Sam Hofmann attends Monthly Partner Meeting.
04/28/22 – Mike Murphy attends Monthly Partner Meeting.
05/26/22 – Mike Murphy and Sam Hofmann attends Monthly Partner Meeting.
06/30/22 – Sam Hofmann attends Monthly Partner Meeting.
07/28/22 – Mike Murphy attends Monthly Partner Meeting
08/25/22 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
12/15/22 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
01/26/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
02/25/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
03/30/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
04/27/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
05/25/23 – Sam Hofmann attends Monthly Partner Meeting
06/29/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
07/27/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
08/31/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
09/28/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
10/25/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
12/07/23 – Sam Hofmann and Mike Murphy attend Monthly Partner Meeting
12/07/23 – Evac plans for TPC 10th Floor returned . Champlin to correct 250 WHT plans.

Champlin – General Services Read More »

250 WHT – Egress Door

06/18/19 – Bert emailed regrading a question from the County’s Safety Specialist regarding a egress door and egress path at the 250 WHT Building.
06/18/19 – Bert emailed floorplan and egress door in question to Champlin for review prior to site visit.
06/25/19 – On site meeting with Bert, Tony Matre and Kru to review location of Exit Door in question and review egress path.
07/03/19 – John from THP shared building code notes from 2015 project for replacement of deteriorated concrete bridges.
09/01/19 – Champlin shared memo explaining removing exit door designation at mid-landing.
09/11/19 – Cincinnati Fire Department sent followup questions.
09/17/19 – Champlin reviewed existing hardware and access control with building manager. Champlin to review this with Fire Department.

10/24/19 – Champlin had a code review meeting with Cincinnati Fire Department (Darryl Meadows) and Building Department (Greg Wiles)

250 WHT – Egress Door Read More »

Master Planning 2019

04/09/19 – Champlin receives request for Master Planning proposal
06/24/19 – Master Planning Kick-Off meeting held at Courthouse
07/02/19 – Champlin sends initial Master Planning Form to County Facilities
07/22/19 – Champlin sends revised Master Planning Form to County Facilities
08/05/19 – Master Planning Form and Master Planning Department Meetings reviewed at meeting held at Courthouse with County Facilities
08/20/19 – Champlin met with Moira Weir and Michael Patton, JFS
08/20/19 – Champlin met with Todd Lang, County Engineer
08/22/19 – Champlin met with Greg Brush, Clerk of Courts
08/23/19 – Champlin met with Dave Pittinger, Recorder
08/27/19 – Champlin met with Michael Lonneman, Treasurer
08/27/19 – Champlin met with Ray Faller, Public Defender
08/29/19 – Champlin met with Adult Probation
08/30/19 – Champlin met with Frank Spatero & Sarah Irwin, HR
09/03/19 – Champlin met with Trina Jackson, Re-Entry
09/03/19 – Champlin met with Paula Drake, Auditor
09/05/19 – Champlin met with James Noyes, Planning & Development
09/05/19 – Champlin met with John Hetzel & Dale Wittmer, Sheriff (800 Broadway & JFS)
09/06/19 – Champlin met with Carla Guenther & Steve Rokich, Juvenile Court
09/06/19 – Champlin met with Lisa Gorrasi & Bev Davis, Domestic Relations Court
09/12/19 – Juvenile Courts tour as follow up to 09/06 meeting
09/12/19 – Champlin met with Joann Cramer, Purchasing
09/13/19 – Champlin met with John Hoffman, Telecommunications
10/25/19 – Master Plan Draft Presentation and Review with Master Planning committee
11/12/19 – Champlin met with Bert Watts and Tony Matre to discuss Master Plan Draft.
11/26/19 – Champlin submitted Master Plan Document. Financial review section still under review.
12/08/19 – Champlin received comments on the 11/26 document from Bert Watts.
12/13/19 – Champlin submitted final version of Masterplan to County
02/20/20 – Champlin received final comments. Updated master plan accordingly
05/12/20 – Final draft submitted to Bert.

Master Planning 2019 Read More »

P&D – Office Renovation

PM: John Nester, Sam Hofmann
06/24/19 – Krutarth and Christy from Champlin meet with County Facilities and P&D Garage manager to review scope of work on-site
07/02/19 – Christy from Champlin sends concept sketch and scope of work description to Bert Watts for his review
07/18/19 – Christy from Champlin met with County Facilities and PD Garage manager to refine scope of work in CAB building
07/24/19 – Christy from Champlin sends preliminary SOSS to Bert Watts for his review for SD scope of work and cost estimating
07/25/19 – TTC created category and Champlin drafted SOSS for SD and Cost Estimates.
08/22/19 – Christy from Champlin sends revised SOSS to Bert Watts for his approval for SD scope of work and cost estimating, revised to include THP
08/28/19 – TEI created preliminary HVAC load calcs and HVAC upgrades prior to the job starting to make sure the existing equipment can be reused if this project moves forward. It is our belief that the existing air handler can be reused with a new VAV with Elec RH for this job.
09/20/19 – SOSS is approved via email from Jessica Powell.
09/24/19 – No updates on this project from ThermalTech this month.
10/16/19 – Meeting w/ Jessica Powell, Mohammad Islam, Bruce McClain & Greg Smorey at P&D Garage to review SP-02.
10/21/19 – Champlin issued SP-03 plans in response to meeting comments.
10/23/19 – Greg commented on SP-03 plans.
10/23/19 – Champlin revised SP-03 and reissued based on Greg’s comments.
10/24/19 – Greg approves SP-03 drawing.
12/12/19 – We discussed in detail how to price up the expansion of the storage room with THP recommendations from their fieldwork. Bert suggested we put together the cost to do the storage room work as two alternates for this work. We then discussed how to do that work and what to price up in the Alternate. TTE to give new prices to CA for this change.
12/16/19 – Project is given new job number 19-PDFO-0486-2040
01/24/20 – Champlin Cost Estimate is uploaded.
01/29/20 – THP’s opinion of probable cost uploaded to Archibus. DD drawings to be sent to Champlin by 1/31/20.
01/30/20 – CA, THP and TTC to edit the estimate one more time and potentially upload drawings. TTC and JM to discuss with Jessica after Partner Meeting.
02/26/20 – Alternate estimates added to comment section. Waiting on P&D decision.
03/24/20 – Cost estimate updated to reflect flooring changes.
07/30/20 – On hold.
08/27/20 – On hold.
03/25/21 – Facilities to circle back on renovation with Engineers next month. It has been on Covid hold.
04/29/21 – No Update.
05/27/21 – No Update.
06/25/21 – No Update.
08/26/21 – No Update.
01/27/23 – THP – Champlin requested structural proposal for Garage improvements.
02/02/23 – THP provided draft proposal to Champlin for review.
02/22/23 – SOSS is at P&D approval.
02/20/23 – THP provided final structural proposal to Champlin.
03/30/23 – SOSS returned. Kickoff meeting to be scheduled
04/27/23 – Kickoff meeting held on site. Minor changes in scope. Design development in progress.
05/25/23 – Drawings and re-estimate to build budget in progress.
06/28/23 – CD documents by 6/30/2023.
06/29/23 – Met with users on 6/26 to finalize plans. Estimate and complete set to be sent next week.
07/14/23 – THP sent Opinion of Probable Cost and Owner Review Set of drawings to Champlin. Waiting to hear back on comments and bid date.
07/27/23 – Owner review set and opinion of probable cost to be submitted on friday.
08/23/23 – THP no updates.
08/31/23 – Project to go out to bid 9/5.
09/01/23 – THP sent Bid Set drawings to Champlin.
09/28/23 – Project is out to Bid.
10/25/23 – K&T construction won the bid. Contract phase until further notice.
11/27/23 – No updates from THP.
12/07/23 – Project scheduled to kickoff in March.
02/01/24 – Submittals under review, permits submitted on this project.
02/26/24 – THP – Pre-construction meeting held on site. Preliminary schedule for construction to start 03/19/24. TTE has responses ready for review, TTC to look over.
03/28/24 – Submittals returned. Background checks mostly complete. Waiting Permit approval.
04/22/24 – Building permit has been approved and picked up by the contractor. Tentative mobilization date 04/24/24.
04/25/24 – K&T mobilized Wednesday. They will work Mon-Thur starting at 8:30AM.
05/29/24 – Structural scope of work has been completed. THP to attend Progress Meeting on 6/4 to review work and punchlist with contractor. Still on tract for Phase 1 to move on schedule. Emcor submitted change order cost to move the electric disconnect, controls enclosure and add controls to the duct heaters. TTC discussed with Tony.
06/27/24 – Construction in progress. Phase 2 to be complete in 2 weeks.
07/24/24 – Phase 1 complete and ready to start Phase 2.
08/29/24 – Phase 2 complete. Furniture to be delivered next week. Punch to be scheduled.
09/26/24 – Final punch list provided to K&T. Closeouts received.
10/31/24 – Closeouts under review.
12/12/24 – Closeouts complete and final pay app processed.

P&D – Office Renovation Read More »

Project Cost Estimates 2020

07/24/19 – Bert discussed 2020 project schedules with team today. All partners can edit this project for updates this year.
08/28/19 – ThermalTech has received our SOSS back from Facilities and fieldwork has been started. HVAC and Plumbing have bee updated for Admin air compressors, auto title and vestibule projects. We should discussed a revised completion date for all the partners.
08/22/19 – THP provided SOSS for project cost estimates.
08/28/19 – County approved THP SOSS.
09/01/19 – ThermalTech completed preliminary estimates awaiting schematic design documents for changes.
09/10/19 – County approved Champlin SOSS.
09/26/19 – THP completed loading dock estimate and information loaded into Archibus.
10/07/19 – We met back at the Admin Building on vestibule job and modified the MEP cost a little bit. All ThermalTech projects are updated and ready to go.
10/03/19 – Project request made Scott Weikel for glass security panels to be installed at public counters on the 9th and 10th floor of the Taft Building.
10/07/19 – THP attended kick off meeting for review CAB entry project. Based on current project request, THP will not have a role in this project.
10/31/19 – THP estimate up loaded into Archibus.
11/01/19 – Champlin scheduled for field visit to verify locations and dimensions of work area.
11/05/19 – CA cost estimate for Justice Center Security Barriers uploaded to Archibus.
11/08/19 – CA updated SD plan for Autotitle project.
11/12/19 – CA cost estimate for Autotile uploaded to Archibus
11/18/19 – Cost estimate uploaded to Archibus. SD drawings sent to County.
11/11/19 – Bert Watts provided CA with new contact information for someone to walk the scope of JC Door replacement.
12/02/19 – CA cost estimate for Cab Entry uploaded to Archibus.
12/13/19 – CA visited Justice center to review scope for Justice Center Frame Replacement
12/17/19 – TEI updated plans and cost for 2020 Projects for CAB Auto Title and Vestibule project in Archibus.
01/16/20 – CA received list of doors and frames to be replaced in Justice Center from Sgt. J. McAuliffe.
02/25/20 – CA reached out to vendors for more information. In the process of putting together cost estimate based on vendors information.
02/27/20 – PDF 2020 estimates by Friday 2/28 and share with Bert when complete. No binders required for this year.

03/09/20 – Champlin reached out to Sgt. McAullife for questions regarding Justice Center Door Replacement project. Waiting on Stg. to schedule a meeting with higher ups to discuss scope.

05/01/20 – Stg. McAullife provided answers to questions of scope. Reached back to to clarify scope

06/17/20 – Scope finalized. Estimate uploaded to Archibus.

 

Project Cost Estimates 2020 Read More »

Millvale – Lease Tenant Fit-Out

06/14/19 – IPM and TTE Met County onsite for kickoff field trip for lease space renovation.
06/21/19 – CHA, IPM and TTE put proposal together and submitted to County for consideration.
06/25/19 – Split proposal up into SD & Estimating and CD & Bidding for consideration.
06/27/19 – Submitted new SD & Estimating SOSS to Facilities for approval. Based on the findings in the SD phase we will update the DD, CD, Bidding & CA SOSS later if the project moves forward.
07/24/19 – SOSS approved. Four week time clock has started. TTE has visiting the site and taken off additional plumbing, HVAC and electrical. Bert gave us the contact to do additional fieldwork at the site. One additional plumbing drawing was found on site.
07/25/19 – County stated today that the all disciplines must have permittable style SD documents to attach as exhibits to the lease.
08/28/19 – The team completed the SD phase and cost estimate and submitted to the owner for review. The cost was higher than expected and a value engineering meeting was held with Facilities and JFS. We removed the HVAC from the project, removed one restroom, changed some of the finishes in the space. We then we updated the floor plans, furniture plans, HVAC, Electric and Plumbing and uploaded the new drawings to Archibus. Finally we updated the cost estimate to match the new scope. We are awaiting review and approval by owner.
09/24/19 – No updates. We are waiting on funding and approval to move to next phase.
10/09/19 – Master lease between CMHA and the city is approved. Project will move forward.
10/23/19 – DD set given to Hamilton County.
10/31/19 – Waiting on lease documents to City, waiting on approval to move forward on bidding.
11/01/19 – CD set scheduled to be given to Hamilton County. Bert gave us the background on using this space now and in the future. This may take some time to work this through the City process for DD drawings.
12/10/19 – CA attended walk through of Space with TTE, County, and Cincinnati to discuss scope of work.
01/30/20 – CHMA approved our proposed plan. The County needs this in writing so they can sublease this space and agree on amount of stay past end of lease. Bert said we are just getting through the administration stuff, the project is good to go in concept.
06/25/20 – Project on hold for now. RT will check on future feasibility.

Millvale – Lease Tenant Fit-Out Read More »